Estrella-Pantaleon Bridge Expected to Open in June 2021
by April 06, 2021
-
The Department of Public Works and Highways (DPWH) is concentrating not only on the civil work’s development of the Estrella-Pantaleon Bridge Project but also on keeping the workplace secure and clean.
DPWH Secretary Mark A. Villar said, "that at 86 per cent and with just a few more days to fully complete the new Estrella-Pantaleon Bridge, we are mindful that a single case of COVID-19 in the project can lead to an interruption, if not total work stoppage"
Secretary Villar recently issued revised guidelines in Department Order #30 for the implementation of ECQ, MECQ, GCQ, and MGCQ infrastructure projects, both public and private, during the public health crisis.
"Although the bridge project is being rushed for completion in June 2021, it is critical that construction firms be proactive rather than reactive in dealing with the increased risk of illness from COVID-19," Secretary Villar added.
Emil K. Sadain, Undersecretary for Unified Project Management Office (UPMO) Operations, and UPMO Roads Management Cluster 1 Project Manager Benjamin Bautista checked the physical progress of the bridge project on Monday, April 5, 2021, and the contractor's compliance with protocols that cover prevention, detection, and rapid response to maintain construction work continuity as workers who have been living in the barracks resume work after the Lenten season.
“Let’s get to work healthy to get the job done”, Undersecretary Sadain reminded the contractor China Road and Bridge Corporation citing the current health situation, particularly in the NCR Plus bubble.
In his report to Secretary Villar, Undersecretary Sadain reported that the project is more than 12% ahead of time, having completed all bridge substructure works for abutments A and B on both sides and piers of the Makati approach bridge; the V-shaped piers for the Main Bridge; concrete box girder for the approach bridge; and the V-shaped piers for the Main Bridg; and two (2) prestressed concrete box girder segments using the traditional approach.
Post-tensioning and grouting works, formworks and rebar installation for the closure section in the side spans, formworks installation for the 2-meter closure section in the main bridge span, and preparatory works for approach road construction on both sides are now the focus of bridge construction activities.
The new 506-linear meter bridge, funded by China and introduced by the DPWH UPMO - Roads Management Cluster 1 (Bilateral), would have a diameter of 21.65 meters, capable of four (4) lanes instead of two (2), and three-meter sidewalks on both sides.
The P1.46 billion new Estrella-Pantaleon Bridge, which is scheduled to be completed in the second quarter of 2021, will handle 50,000 vehicles a day and minimize travel time between Mandaluyong and Makati to 12 minutes.
The bridge will connect Estrella Street in Makati to Barangka Drive in Mandaluyong, helping to relieve traffic congestion on EDSA by providing an alternative route for motorists.