DOTr targets partial operation of MRT-7 in 2021


The Department of Transportation (DOTr) is targeting the partial operation of MRT-7 in 2021.


DOTr Undersecretary for Railways Timothy John Batan said the project will definitely ease the burden of commuters as travel time from Quezon City to San Jose del Monte in Bulacan will reduce significantly from four hours to about 35 minutes once the project is completed.


On Wednesday (July 17), Batan and DOTr officials inspected MRT-7’s construction site in Quezon City to check the work in progress.


According to the project’s contractor San Miguel Corporation, the ongoing construction is already 44% complete which includes the train stations, platforms and the line where the railings will be placed.


The DOTr also announced that the procurement of 36 new train sets from South Korea has already been done.


MRT-7 is a 23-kilometer railway system that connects North Avenue in Quezon City to the province of Bulacan.


The train system traverses 14 stations namely North Avenue, Quezon City Memorial Circle, University Avenue, Tandang Sora, Don Antonio, Batasan, Manggahan, Doña Carmen, Regalado, Mindanao Avenue, Quirino, Sacred Heart, Tala and San Jose Del Monte.

It can load up to 500,000 passengers daily.


To prevent similar glitches as those in MRT Line 3, the DOTr is in close coordination with the agency’s private partners in terms of the regular maintenance of the MRT-7.


Usec. Batan said the completion of the entire project is expected in 2022.


Source: https://www.untvweb.com/news/dotr-targets-partial-operation-of-mrt-7-in-2021/

PHILIPPINE RESOURCES JOURNAL ​

2nd Floor, Suite 6,

Corinthian Plaza Building,

Paseo De Roxas, Legaspi Village,

Makati, Philippines

Phone: +632 251 5599

Subscribe to Our Newsletter

  • White Facebook Icon

© Philippine Resources Journal