ADB SUPPORTS DPWH CONSTRUCTION OF 3 MARIKINA BRIDGES

by Philippine Resources - April 06, 2022

Photo credit: Department of Public Works and Highways

The Philippine Government and Asian Development Bank (ADB) have reaffirmed their strong partnership for long-term economic growth through infrastructure projects to accelerate economic recovery by improving connectivity.

Department of Public Works and Highways (DPWH) Secretary Roger G. Mercado announced that ADB will co-financed the construction of three (3) new bridges to help solve the increasingly severe traffic problem in Metro Manila.

“A loan agreement with ADB is an exciting assurance of the construction of three (3) new climate and disaster resilient bridges as well as added training program to strengthen DPWH institutional capacity in bridge operation and maintenance”, said Secretary Mercado.

The ceremonial exchange of the financing agreements between ADB and the Department of Finance (DOF) representing the Government of the Republic of the Philippines for the DPWH Metro Manila Bridges Project was held on Wednesday, March 30, 2022.

Receiving the loan documents on behalf of the Philippine Government is Finance Secretary Carlos G. Dominguez while receiving on behalf of the Asian Development Bank is Managing Director General Woochung Um.

The exchange of documents was witnessed by DPWH Secretary Mercado; DOF Undersecretary Maria Edita Z. Tan; ADB Philippine Country Office Director Kelly Bird; and ADB Deputy Director General Winfried Wicklein.

Also in attendance in the event held at DOF Podium Conference Room, BSP Complex, Roxas Boulevard, Manila were DPWH Undersecretary for Unified Project Management Office (UPMO) Operations and Build Build Build Chief Implementer Emil K. Sadain; Project Director Rodrigo I. Delos Reyes of DPWH UPMO - Bridges Management Cluster; ADB Alternate Executive Director Paul G. Dominguez; DOF Undersecretary Mark Dennis Y.C. Joven and Assistant Secretary Neil Cables; ADB Advisor to the Executive Director Ms. Tuya Darinchuluun; and other DOF, DPWH, and ADB officials.

Loan Agreement 4168-PHI between the Philippine government and ADB amounting to 175 million-dollar will be utilized exclusively for the financing of the Metro Manila Bridges Project. The loan was approved by the ADB Board of Directors and signed by ADB and DOF last December 2021.

As part of the overall Metro Manila Logistics Network with a total of 12 bridges being eyed over Pasig River, Marikina River, and the Manggahan Floodway, the ADB-assisted Metro Manila Bridges Project involves the construction of three (3) new bridges which is aimed at improving efficiency of road travel crossing Marikina River.

These bridges are the Marcos Highway-Saint Mary Bridge (Formerly J.P. Rizal-St. Mary Bridge) with a total length of 1,582.6 meters including the main bridge length of 325 meters; Homeowners Drive-A. Bonifacio Ave. Bridge (Formerly J.P. Rizal-Lopez Jaena Bridge) with a total length of 691 meters including the main bridge length of 461.5 meters; and Kabayani-Matandang Balara Bridge (Formerly Marikina-Vista Real Bridge) with a total length of 723.2 meters including the main bridge length of 364 meters.

To achieve seamless travel and connectivity, three (3) of the bridges in the Metro Manila Logistics Improvement were completed with one (1) due for opening on April 5, 2022, two (2) are in the procurement stage, and three (3) under financing negotiation. Completed across Pasig River are the Bonifacio Global City – Ortigas Center Link Road Project that involves the construction of a 4-lane Sta Monica to Lawton Bridge or Kalayaan Bridge, Estrella - Pantaleon Bridge, and Binondo - Intramuros Bridge.

Secretary Mercado expressed confidence that the construction of new bridges in Marikina City will be effectively and expeditiously implemented by the team of Undersecretary Sadain in the UPMO Operations.

According to Undersecretary Sadain, ADB is involved in other flagship infrastructure projects of DPWH such as the technical and financial assistance for the on-going detailed engineering design of Bataan – Cavite Interlink Bridge and Laguna Lakeshore Road Network Project, and the on-going civil works construction of Improving Growth Network – Mindanao Sector Improvement Project.

These ADB-assisted big-ticket projects will ensure the sustainability of infrastructure development under Build, Build, Build Program even beyond the term of President Rodrigo Roa Duterte, Undersecretary Sadain said.

 

Article courtesy of The Department of Public Works and Highways


Place your Ad Here!


Related Articles

Construction

Philippine Resources - June 30, 2021

DPWH Targets Substantial Completion of Binondo - Intramuros Bridge by December

Public Works and Highways Secretary Mark Villar announced that construction of access ramps are underway for the iconic Binondo-Intramuros Bridge Project. Secretary Villar said that civil work activities for the ramps and viaduct structure are moving forward as it aims for the bridge substantial completion towards December 2021. In his report to Secretary Villar, Undersecretary for Unified Project Management Office (UPMO) Operations Emil K . Sadain said that the project has already attained 70 percent completion with the 70-meter Main Bridge with steel arch and support steel bowstring over Pasig River permanenly positioned at pier 4 and 5 and installation of pre-fabricated precast slab available on-site will soon start. The fabricated steel box girders which will be utilized for the viaduct and ramp over Estero de Binondo are expected to arrived from China by August 2021, added Undersecretary Sadain following his occular inspection on Tuesday, June 29, 2021 together with UPMO Roads Management Cluster 1 - Bilateral OIC-Project Director Benjamin A. Bautista, Project Manager Melchor Kabiling, Project Engineer Joey Doria and contractor China Road and Bridge Corporation. The 3.39 billion peso Binondo-Intramuros Bridge Project will connect the historic districts of Binondo and Intramuros in Manila having a 418 meter viaduct structure and ramp over Estero de Binondo and 298 meter Binondo up-ramp at Muelle Dela Industria Street at Binondo side, and 191 meter up-ramp at Magallanes/Riverside Drive and 164 meter down ramp at Solana Street in Intramuros. Funded by a grant of People’s Republic of China, the arch bridge design symbolizes the friendly cooperation between Philippines and China and being built in accordance with new seismic design specifications and climate change considerations. Bored piles for the up/down ramps and abutments at Intramuros side are all completed while works are in full swing for the 98 bored piles at Binondo side, 61 of which are completed. DPWH and the contractor continues to coordinate with Meralco and Telco for their lines along Dasmariñas Bridge and as strategy are formulated to minimize service disruption with the launching of steel box girders along Estero de Binondo towards Plaza del Conde and Rentas Street and the relocation of affected lines along Muelle de Binondo near San Nicolas Fire Station. The Binondo-Intramuros Bridge will carry extra traffic of around 30,000 vehicles per day and will also help extend the life of existing Jones, Delpan and MacAthur Bridges by decongesting traffic. The project is part of the Metro Manila Logistics Improvement Program to address the long-held dilemma of traffic gridlock in major roads by constructing new bridges crossing Pasig and Marikina Rivers, and Manggahan Floodway.

Construction

Philippine Resources - July 14, 2021

Estrella Pantaleon Bridge Nears Completion

Finishing works of the Department of Public Works and Highways (DPWH) for the Estrella Pantaleon Bridge Project across Pasig River are in full swing and set to be completed towards the end of July. Public Works and Highways Secretary Mark Villar said that although the Covid-19 pandemic has impacted construction activity of various flagship infrastructure projects like Estrella Pantaleon Bridge, the DPWH-Unified Project Management Office (UPMO) Team geared up to take up this challenge by keeping focus on the importance of delivering completion and opening this bridge project this early month of the third quarter. In his report to Secretary Villar, Undersecretary for UPMO Operations Emil K. Sadain said that complete layers of asphalt concrete base, binder and wearing course on the 146 meters main bridge and 66 meters Makati approach bridge are almost done. Installed successively on main and approach bridge using paving and compaction equipment, the wearing course or the uppermost layer will provide an even profile for the comfort of motorists while providing enough texture to ensure minimum and safe skid resistance, explained Undersecretary Sadain. Having put up the upper layer, bridge expansion joints are now being installed to allow for continuous traffic between the bridge and the interconnecting abutment structures. This expansion joints is designed to adjust the bridge length accommodating movement or deformation by external loads, shrinkage, or temperature variations Among the completed ancillary works for the bridge project with V-shape piers includes protective barriers and railings along both sides of the bridge, storm water drainage structure, and lightings. Meanwhile, Project Director Benjamin A. Bautista and Project Manager Melchor Kabiling of the UPMO Roads Management Cluster are keeping an eye on the on-going paving works for the 50.5 meters approach road on Estrella Street, Makati City and 243.96 meters approach road at Barangka Drive connected to Pantaleon Street in Mandaluyong City which are being accelerated by successively placing complete layer packages. The layers of approach road are consists of base course or the foundation made of different aggregate rocks to support the top layers of the pavement; cement-treated base or mixture of aggregates with amounts of portland cement that hardens after compaction and curing to form a strong, durable, frost-resistant paving material; asphalt concrete base or asphalt treated base that acts as waterproof barrier to prevent fines infiltration into the subgrade and pavement structure; finally the binder and wearing course. The P1.46-billion bridge project will have four lanes and will be a 506.46-meter pre-stressed concrete rigid frame bridge with corrugated steel webs, replacing the temporary two-lane box truss bridge made of modular steel components dismantled in 2019. The bridge project is one of two grant bridges from China — the other one is Binondo-Intramuros Bridge.

Construction

Philippine Resources - June 21, 2021

Villar: Estrella-Pantaleon Bridge On-Track for July 2021 Opening

Photo Credit: Department of Public Works and Highways Public Works and Highways Secretary Mark Villar reassured on Friday, June 18, 2021 that remaining civil works are being fast-tracked to open the new and modernized Estrella-Pantaelon Bridge by next month. “We are here on-site to show you that all substructure and superstructure of the Estrella-Pantaelon Bridge have been constructed and we are confident that we will be able to finish remaining works on approach road and ancillary/miscellaneous works by July 2021,” said Secretary Villar. Secretary Villar together with BCDA President & CEO and Presidential Adviser for Flagship Programs and Projects Secretary Vince Dizon, Transportation Secretary Arthur Tugade and DPWH Undersecretary for Unified Project Management Office (UPMO) Operations Emil K. Sadain inspected the substantially completed Estrella Pantaleon Bridge following an on-site Press Conference on Progress Update of Build, Build, Build Program. Citing a report from Undersecretary Sadain, Secretary Villar noted that the ongoing bridge project across Pasig River linking Estrella Street in Makati City and Barangka Drive in Mandaluyong City is now 93 percent complete. When completed, the new Estrella-Pantaleon Bridge widened from two (2) lanes to four (4) lanes is expected to accommodate as much as 50,000 cars daily, improving traffic situation in the area and decongesting the Epifanio delos Santos Avenue. The bridge-modernization project is implemented by the DPWH-UPMO Roads Management Cluster 1 (Bilateral) and is funded under a Chinese Grant together with Binondo-Intramuros Bridge.   Article Courtesy of the Department of Public Works and Highways

Place your Ad Here!


Recent Articles

Mining

Philippine Resources - June 10, 2023

DMCI Mining Targets 1.5 Million WMT Nickel Ore Shipment in 2023

Photo Credit: dmcihouse.net DMCI Mining Corporation is targeting to ship 1.5 million wet metric tons (WMT) of nickel ore in 2023, after its subsidiary Zambales Diversified Metals Corporation (ZDMC) was granted an Environmental Compliance Certificate (ECC) in January to produce 2 million WMT of nickel ore. Prior to the ECC issuance, ZDMC was only allowed to extract 1 million WMT. “We have the necessary facilities and mitigating measures to minimize the impact of our operations on the environment. With these in place, we’re targeting to produce anywhere between 1.7 million to 2 million tons of nickel ore this year,” said DMCI Mining president Tulsi Das C. Reyes. From January to March, ZDMC nickel ore production soared by 88 percent from 318,000 WMT to 599,000 WMT, its highest-ever quarterly output. This led to a 16-percent improvement in total inventory, from 154,000 WMT to 178,000 WMT. However, total shipment declined by 21 percent from 620,000 WMT to 487,000 WMT owing to the depletion of the BNC mine and stockpile, cushioned by the double-digit growth of ZDMC shipment. Average selling price increased by 11 percent from USD44 to USD49 owing to higher Zambales shipments of higher-grade nickel ore. Despite the mine and stockpile depletion of Berong, DMCI Mining standalone revenues narrowly declined (-8%) from P1.4 billion to P1.3 billion due to better selling prices while reported net income contracted by 15 percent from P543 million to P463 million.

Industry

Philippine Resources - June 10, 2023

DMCI Power to build wind facility in Semirara Island

Leading off-grid electricity generator DMCI Power Corporation (DPC) is set to build a wind power plant in Semirara Island, home of the biggest coal reserve in the Philippines. DPC intends to finalize the wind power capacity in the coming months, with projections ranging from 8 to 12 MW, and operational implementation expected within 12 to 15 months. The project will be funded and undertaken independently by the company. “We are also looking at solar energy to augment the supply in the island, but we are prioritizing wind resource development because it has shown the most promise,” said DPC president Antonino E. Gatdula, Jr. “Current studies suggest that wind power could potentially deliver a 33% plant utilization rate, compared to just 17% for solar. Capital expenditure per megawatt for both wind and solar projects are also roughly the same,” he explained. In a 2001 wind resource study conducted by the National Renewable Energy Laboratory (NREL), a United States Department of Energy (DOE) laboratory, it was found that Semirara Island has some of the best wind resources in the Philippines. The wind corridors between Luzon and Panay (including Semirara Islands and extending to the Cuyo Islands) were found to have good-to-excellent wind power density and speed for utility-scale or village power applications. DPC is in the process of validating these wind resource estimates to determine the final location and capacity of its wind project.

Mining

Philippine Resources - June 05, 2023

Semirara Mining and Power Corporation eyes Japanese market expansion

Photo credit: Bilyonaryo Integrated energy company Semirara Mining and Power Corporation (SMPC) is set to make its second trial shipment to Japan this June, in a bid to reduce its dependency on the Chinese market. The company will export 50,000 metric tons (MT) of Semirara coal to Shikoku Electric Power Corporation for its 700-megawatt coal fired ultra-supercritical power station. “China is still our main foreign buyer but with their industrial output growing slower than expected, we want to develop other Asian markets like Japan,” said SMPC president and COO Maria Cristina C. Gotianun. From January to March, Semirara coal shipments to China plunged by 50 percent from 2.2 million MT to 1.1 million MT, accounting for 72 percent of exports. South Korea was a steady market at 300,000 MT, representing one-fifth of export sales. The rest of the exports went to Japan (5%) and Brunei (3%). SMPC first made a trial shipment to Japan in January 2023, selling 78,410 MT of mid-grade coal to J-Power, a utility company that operates coal, hydroelectric, wind and geothermal power stations. “For 2023, we are targeting to export around 30 percent of our full-year sales target of 15 to 16 million MT,” added Gotianun. In the first quarter, standalone coal revenues sank by 40 percent from P25.7 billion to P15.5 billion mainly due to high base effect of record production, shipments and selling prices. Standalone reported net income slumped by 51 percent from P14.2 billion to P7 billion on topline weakness and slower decline in cash costs.

Place your Ad Here!

Place your Ad Here!

Join the Philippines'

Mining, Construction and Industry Community

Be the "First" to get our exclusive Digital Magazine & Newsletter.