PROPOSED INTER-ISLAND BRIDGE IN LUZON FEATURED AT ADB MEET IN INCHEON, SOUTH KOREA

by Philippine Resources - May 15, 2023

Photo credit: the Department of Public Works and Highways

Korean construction and engineering companies are interested to participate in the procurement of the design and build of a mega inter-island bridge project in Luzon.

Upon the invitation of the Korea Trade-Investment Promotion Agency (KOTRA) which organizes the Global Project Plaza 2023 to bring together foreign government organizations, contractors and financial institutions, the Department of Public Works and Highways (DPWH) represented by Senior Undersecretary Emil K. Sadain, provided a detailed briefing about the 32.15-kilometer four (4)-lane Bataan-Cavite Interlink Bridge Project that can be joined by Korean and other international companies when the procurement for the civil works roll out in the coming months.

The Global Project Plaza 2023 was held in conjunction with the Asian Development Bank (ADB) annual meeting in Incheon, South Korea and mostly focused on ADB related projects.

In his discussion, Senior Undersecretary Sadain said that the on-going detailed engineering design (DED) of Bataan-Cavite Interlink Bridge Project is at 85 percent and target for completion by this June 2023.

The Bataan-Cavite Interlink Bridge Project is being developed by the DPWH Unified Project Management Office – Roads Management Cluster 2 (Multilateral) with technical assistance funding from the ADB to advance the detailed engineering design with the DED contract awarded to the joint venture of TY Lin International and the Republic of Korea’s Pyunghwa Engineering Consultants, working with Switzerland-based Renardet and the Philippines’ DCCD Engineering Corporation.

Feasibility study for the Bataan-Cavite Interlink Bridge Project that was started in March 2018 was funded under ADB’s Infrastructure Preparation and Innovation Facility Loan. Together with Asian Infrastructure Investment Bank (AIIB), ADB has also committed to co-finance the civil works construction.

As one of the promising projects featured in the ADB project seminar on the sidelines of 56th Annual Meeting of the ADB Board of Governors, Senior Undersecretary Sadain also had an opportunity for one-on-one engagement with ADB executives and Korean engineering and construction companies.

The alignment of the proposed bridge will cross over the Manila Bay – a natural harbor that is bounded by Cavite and Metro Manila on the east, Bulacan and Pampanga on the north, and Bataan on the northwest.

No less than President Ferdinand R. Marcos Jr. with DPWH Secretary Manuel M. Bonoan led on March 31, 2023 the ceremonial switching of the button signaling the start of the geotechnical investigation in evaluating underground conditions – the last of missing pieces to complete the foundation design and deliver the final DED bridging to the new project milestone of civil works implementation.

Due to the scale of the project, seven (7) design packages have been identified reflecting a convenient division of future construction packages. The construction will first begin in the two on-land packages, 5-kilometer Bataan Land Approach under Package 1 and 1.3-kilometer Cavite Land Approach under Package 2 .

Packages 3 and 4 are North and South Marine Viaducts with a total length of 20.6-kilometer.

The Bataan-Cavite Interlink Bridge Project includes the construction of two cable-stayed navigation bridges on either side of historic Corregidor Island.

Called the north channel bridge and south channel bridge, the structures that will stand in water as deep as 50 meters will have main spans of 400 meters and 900 meters, respectively.

The North Channel Bridge with high level approaches of 2.1 kilometer in length will constitute Package 5, while the South Channel Bridge with high level approaches at 3.1-kilometer length will be the Package 6. The 7th Package involves a project-wide ancillary works.

New opportunities will be created by the Bataan-Cavite Interlink Bridge Project, including the development of seaports in the two (2) provinces of Bataan and Cavite, making them potential international shipping gateways of the country.

Once completed, the inter-island bridge which will be one of the longest bridges in the Philippines and the world will cut travel time between Bataan and Cavite from the current five (5) hours to 45 minutes.

 

Article courtesy of the Department of Public Works and Highways


Place your Ad Here!


Related Articles

Construction

Philippine Resources - June 30, 2021

DPWH Targets Substantial Completion of Binondo - Intramuros Bridge by December

Public Works and Highways Secretary Mark Villar announced that construction of access ramps are underway for the iconic Binondo-Intramuros Bridge Project. Secretary Villar said that civil work activities for the ramps and viaduct structure are moving forward as it aims for the bridge substantial completion towards December 2021. In his report to Secretary Villar, Undersecretary for Unified Project Management Office (UPMO) Operations Emil K . Sadain said that the project has already attained 70 percent completion with the 70-meter Main Bridge with steel arch and support steel bowstring over Pasig River permanenly positioned at pier 4 and 5 and installation of pre-fabricated precast slab available on-site will soon start. The fabricated steel box girders which will be utilized for the viaduct and ramp over Estero de Binondo are expected to arrived from China by August 2021, added Undersecretary Sadain following his occular inspection on Tuesday, June 29, 2021 together with UPMO Roads Management Cluster 1 - Bilateral OIC-Project Director Benjamin A. Bautista, Project Manager Melchor Kabiling, Project Engineer Joey Doria and contractor China Road and Bridge Corporation. The 3.39 billion peso Binondo-Intramuros Bridge Project will connect the historic districts of Binondo and Intramuros in Manila having a 418 meter viaduct structure and ramp over Estero de Binondo and 298 meter Binondo up-ramp at Muelle Dela Industria Street at Binondo side, and 191 meter up-ramp at Magallanes/Riverside Drive and 164 meter down ramp at Solana Street in Intramuros. Funded by a grant of People’s Republic of China, the arch bridge design symbolizes the friendly cooperation between Philippines and China and being built in accordance with new seismic design specifications and climate change considerations. Bored piles for the up/down ramps and abutments at Intramuros side are all completed while works are in full swing for the 98 bored piles at Binondo side, 61 of which are completed. DPWH and the contractor continues to coordinate with Meralco and Telco for their lines along Dasmariñas Bridge and as strategy are formulated to minimize service disruption with the launching of steel box girders along Estero de Binondo towards Plaza del Conde and Rentas Street and the relocation of affected lines along Muelle de Binondo near San Nicolas Fire Station. The Binondo-Intramuros Bridge will carry extra traffic of around 30,000 vehicles per day and will also help extend the life of existing Jones, Delpan and MacAthur Bridges by decongesting traffic. The project is part of the Metro Manila Logistics Improvement Program to address the long-held dilemma of traffic gridlock in major roads by constructing new bridges crossing Pasig and Marikina Rivers, and Manggahan Floodway.

Construction

Philippine Resources - July 14, 2021

Estrella Pantaleon Bridge Nears Completion

Finishing works of the Department of Public Works and Highways (DPWH) for the Estrella Pantaleon Bridge Project across Pasig River are in full swing and set to be completed towards the end of July. Public Works and Highways Secretary Mark Villar said that although the Covid-19 pandemic has impacted construction activity of various flagship infrastructure projects like Estrella Pantaleon Bridge, the DPWH-Unified Project Management Office (UPMO) Team geared up to take up this challenge by keeping focus on the importance of delivering completion and opening this bridge project this early month of the third quarter. In his report to Secretary Villar, Undersecretary for UPMO Operations Emil K. Sadain said that complete layers of asphalt concrete base, binder and wearing course on the 146 meters main bridge and 66 meters Makati approach bridge are almost done. Installed successively on main and approach bridge using paving and compaction equipment, the wearing course or the uppermost layer will provide an even profile for the comfort of motorists while providing enough texture to ensure minimum and safe skid resistance, explained Undersecretary Sadain. Having put up the upper layer, bridge expansion joints are now being installed to allow for continuous traffic between the bridge and the interconnecting abutment structures. This expansion joints is designed to adjust the bridge length accommodating movement or deformation by external loads, shrinkage, or temperature variations Among the completed ancillary works for the bridge project with V-shape piers includes protective barriers and railings along both sides of the bridge, storm water drainage structure, and lightings. Meanwhile, Project Director Benjamin A. Bautista and Project Manager Melchor Kabiling of the UPMO Roads Management Cluster are keeping an eye on the on-going paving works for the 50.5 meters approach road on Estrella Street, Makati City and 243.96 meters approach road at Barangka Drive connected to Pantaleon Street in Mandaluyong City which are being accelerated by successively placing complete layer packages. The layers of approach road are consists of base course or the foundation made of different aggregate rocks to support the top layers of the pavement; cement-treated base or mixture of aggregates with amounts of portland cement that hardens after compaction and curing to form a strong, durable, frost-resistant paving material; asphalt concrete base or asphalt treated base that acts as waterproof barrier to prevent fines infiltration into the subgrade and pavement structure; finally the binder and wearing course. The P1.46-billion bridge project will have four lanes and will be a 506.46-meter pre-stressed concrete rigid frame bridge with corrugated steel webs, replacing the temporary two-lane box truss bridge made of modular steel components dismantled in 2019. The bridge project is one of two grant bridges from China — the other one is Binondo-Intramuros Bridge.

Construction

Philippine Resources - June 21, 2021

Villar: Estrella-Pantaleon Bridge On-Track for July 2021 Opening

Photo Credit: Department of Public Works and Highways Public Works and Highways Secretary Mark Villar reassured on Friday, June 18, 2021 that remaining civil works are being fast-tracked to open the new and modernized Estrella-Pantaelon Bridge by next month. “We are here on-site to show you that all substructure and superstructure of the Estrella-Pantaelon Bridge have been constructed and we are confident that we will be able to finish remaining works on approach road and ancillary/miscellaneous works by July 2021,” said Secretary Villar. Secretary Villar together with BCDA President & CEO and Presidential Adviser for Flagship Programs and Projects Secretary Vince Dizon, Transportation Secretary Arthur Tugade and DPWH Undersecretary for Unified Project Management Office (UPMO) Operations Emil K. Sadain inspected the substantially completed Estrella Pantaleon Bridge following an on-site Press Conference on Progress Update of Build, Build, Build Program. Citing a report from Undersecretary Sadain, Secretary Villar noted that the ongoing bridge project across Pasig River linking Estrella Street in Makati City and Barangka Drive in Mandaluyong City is now 93 percent complete. When completed, the new Estrella-Pantaleon Bridge widened from two (2) lanes to four (4) lanes is expected to accommodate as much as 50,000 cars daily, improving traffic situation in the area and decongesting the Epifanio delos Santos Avenue. The bridge-modernization project is implemented by the DPWH-UPMO Roads Management Cluster 1 (Bilateral) and is funded under a Chinese Grant together with Binondo-Intramuros Bridge.   Article Courtesy of the Department of Public Works and Highways

Place your Ad Here!


Recent Articles

Mining

Philippine Resources - May 23, 2023

MEMORANDUM OF AGREEMENT SIGNED WITH TVI RESOURCE DEVELOPMENT (PHILS.) INC.

Photo credit: TVI Resource Development The Board of RTG Mining Inc. is pleased to announce that a comprehensive settlement of all outstanding issues with the Villar Family controlled Sage Capital and TVI Resource Development (Phils.) Inc. (“TVIRD”) has been reached and a binding Memorandum of Agreement signed. On execution of the final documents, expected in the next month, all litigation that RTG had launched will be withdrawn as part of an agreed restructuring of the Mabilo Project. The Villar Family is one of the most prominent families in the Philippines and RTG is pleased to partner with them in the development of the Mabilo Project, which is a significant mining project for the country. The key terms of the agreement for RTG include the following: RTG (through SRM Gold Limited) will retain a 40% interest in Mt. Labo Exploration and Development Corporation (“Mt. Labo”) with the project also developed by Mt. Labo, in line with Philippine regulatory requirements, with Sage Capital (which is owned by TVIRD) holding the remaining 60%; RTG will have a 2% net smelter royalty (“NSR”); RTG’s debt together with interest, currently in the order of US$27M (subject to audit) will be repaid out of the proceeds of Stage 1 of the project, the Direct Shipping Operation subject to customary requirements to address liquidity and ongoing operations of Mt. Labo; Funding arrangements for the project as between the major shareholders of Mt. Labo have been successfully renegotiated, (relieving RTG of a sole funding obligation) and replaced with a pro-rata funding obligation, together with a disproportionate funding obligation of Sage Capital, as set out below; With debt repayments in full and the NSR, RTG will be entitled to approximately 57% of the proceeds of Stage 1, the Direct Shipping Operation; RTG will be entitled to 40% of the operating cashflow of the project, together with the 2% NSR and repayment of its debt, which is currently in the order of US$27M; The first US$5M of expenditure for Mt. Labo (or 12 months of expenditure, whichever occurs the earlier), will be funded pro-rata between the two shareholders (ie RTG will provide 40%) and thereafter, Sage Capital/TVIRD will sole fund the next US$5M of expenditure, with all additional funding thereafter to be provided on a pro-rata basis; All parties are required to act in the best interests of the project and not compete; A shareholders’ agreement will be finalised which will provide typical minority interest protection clauses including reserve matters for voting including annual budgets and appointments of key personnel; Any disputes will be resolved by the Singapore International Arbitration Centre; and On completion of final signed documents, all litigation matters will be withdrawn and settled in full. With the restructuring of the Mabilo Project now agreed, over the balance of this year, the remaining permitting matters and financing plans will be finalised, a review of the 2016 Feasibility Study will be completed, together with finalising the acquisition of surface rights, following which, a commitment to development will be formalised by the Board of Mt. Labo. RTG is pleased with the outcome of the discussions and the co-operative and constructive approach adopted by the Villar Family representatives. RTG believes they can be a strong and positive partner to work with to take the Mabilo Project forward, with both a near term development and future exploration activities to expand the project, which will start to unlock the value of the project for all stakeholders, not only the local communities but for the country as a whole.

Mining

Philippine Resources - May 22, 2023

Mining Operational Excellence Through Digital Transformation

Part 1: Mining Operation Challenges and Mine Operations Management Domains 1 & 2. By Mae Ann Cabasag, EM Mining companies encounter numerous challenges throughout their operations. However, initiatives to mitigate these challenges and improve efficiency are often limited. Most of these limitations emanated from a common factor: the challenge of “poor visibility” in mining operations. A viable solution is to adopt digital transformation in mining operations by incorporating available real-time data into an integrated system— capable of ensuring automatic updates and reliable source of information. Through this, mining companies not only understand simulations and plans developed but also anticipate potential outcomes. Various mining industry analysts have found that using non-digital methods in the mining operations can lead to a 27% reduction in production time and 25% increase in data inaccuracy. For a mining company to remain competitive in an industry susceptible to operation challenges, i.e. production processes, workers’ and equipment performances, ore quality and quantity, compliance to regulations, and inter-departmental collaboration, it needs to embrace digital transformation. Dassault Systèmes Mine Operations Management provides transformative digital solution for mining companies to achieve excellence in their operations. Mine Operations Management (MOM) equips mining companies with an integrated system for their mining operations, enabling them to achieve efficient plan and schedule. This system integrates entire operation data into a single repository source of information, known as the “single source of truth”, ensuring complete transparency of the company’s processes from mine to port. By leveraging MOM, we can address the following global mining industry challenges: Maintaining competitiveness amidst market volatility. Eliminating waste materials, poor communication, and error duplication. Improving site productivity and efficiency. Utilizing assets and sharing best practices across the value chain. Ensuring an utmost level of safety. Reducing environmental impacts and achieving sustainable operations. The transformative digital solution, Mine Operations Management, is composed of eight work packages, split across four domains, namely: Data Management, Material Reconciliation, Operational Control, and Assets Performance. These domains help generate valuable insights from integrated operational data for rapid and informed strategic decision-making.  The Data Management consists of Master Data Model and Integration Framework packages essential for material tracking, stockpile management, task and workforce management, machine performance, and asset maintenance. It enables users to manage master data objects such as Site, Material, Location, Equipment, and Operator through manual data entry or third-party source systems.  With this, mining companies can ensure efficient and integrated management of critical data required for seamless operations. Material Reconciliation, on the other hand, consists of Material Tracking and Stockpile Management packages. Material Tracking enables us to track material movements across different stages, i.e. from the least accurate grade estimated in geological model to the most precise information on shipped material quantity and quality, to account for any inaccuracies. While in the Stockpile Management, users not only can calculate daily stockpile balance, add Survey or Sampling data, analyze inventory levels and trends, create graphical representation of the stockpile balances and movements, calibrate stockpile using volumetric survey and sampling, enables comparison of different models, track movement genealogy and review stockpile slices for stockpiles with LIFO and FIFO calculation type but can create a different type of analysis such as actual vs plan vs model. In the upcoming article, we will explore the two remaining domains of Mine Operations Management to where assigning operational tasks, tracking compliance to plan, monitoring equipment down to workers’ performance are feasible in the mining operations. To know more about MOM, mining innovations and solutions, contact Dassault Systèmes Value Solutions Partner: Paramina Earth Technologies Inc. through paramina_solutions@paramina.com   References: Make it happen for mine execution excellence: Dassault Systèmes®. MEGATrends. (n.d.).  https://events.3ds.com/make-it-happen-for-mine-execution-excellence  Dassault Systèmes. (2021, August 12). Digging deeper: The virtual solution for Mining Operational Excellence. Dassault Systèmes. https://discover.3ds.com/virtual-mining-operational excellence  dassault3ds. (2022, June 16). The mining industry needs to adapt, but how? Dassault Systèmes blog. https://blog.3ds.com/brands/delmia/the-mining-industry-needs-to-adapt-but-how/

Mining

Philippine Resources - May 22, 2023

Customer’s First Choice: Sandvik Philippines Delivers 11th and 12th Pantera DP1500i Drills to Filminera Resources Corporation

Sandvik Philippines has successfully commissioned and delivered to loyal customer Filminera Resources Corporation (“Filminera”) their 11th and 12th Pantera DP1500i Top-hammer Surface Drills last 25 January 2023 at the Masbate Gold Project (MGP) located in Masbate Island, Philippines. Photo shows Sandvik Technician Larry Lugnas (second from left) and Service Operations Manager Jorge Cabello (third from left) handing over the drills to MGP representatives. Located 360 km southeast of Manila, the Masbate Mine is operated by Filminera, the Philippine subsidiary of TSX- and NYSE-listed B2Gold with headquarters in Vancouver. In 2022, the mine produced a record-setting 212,728 oz of gold out of 7.93M tonnes of ore milled at an average grade of 1.11 g/t.  B2Gold also operates the Fekola Mine in Mali and the Otjikoto Mine in Namibia. Their projects under development include the Anaconda Area in Mali and the Gramalote JV Project in Colombia. The Masbate Mine started operating in 2008 initially using 4 x Atlas Copco ECM660 Drills owned and operated by the erstwhile mining contractor, Leighton. When the opportunity for re-fleeting came about in 2012, Sandvik succeeded in winning the tender which came packaged with a full maintenance contract for 24,000 service meter hours of five years. Ironically, the said maintenance contract almost led to the cancellation of the order for the first 4 x DP1500i due to a dispute with the rates. Eventually, both Leighton and Sandvik were able to arrive at a mutually acceptable arrangement, and Sandvik ran the service contract for five years without incurring penalties in the availability guarantees. The contract was so profitable, Sandvik even had to share some of the residual profit at the end with Filminera under the pain-and-gain proviso of the contract. The next re-fleeting opportunity came in 2017, with the Masbate Mine. This time, there was no service contract attached to the equipment and Leighton was no longer the mining contractor; the mine has shifted to owner-miner operation. Sandvik managed to secure the repeat order for another batch of 4x DP1500i, banking on the proven performance and reliability of the first four. That brings the total to 8 units. Drill numbers 9 and 10 were ordered in July 2020 and delivered in 2021. Numbers 11 and 12 in the photo above were ordered in January 2022 and are now handed over to the customer. Filminera ordered two more DP1500i’s in November 2022; these machines are now awaiting completion in Tampere, for delivery later this year. That should bring the total to 14 x DP1500i units spread over 11 years for our most loyal Pantera DP1500i customer in the Philippines – Filminera Resources Corporation!

Place your Ad Here!

Place your Ad Here!

Join the Philippines'

Mining, Construction and Industry Community

Be the "First" to get our exclusive Digital Magazine & Newsletter.