Metro Manila subway project 30% complete: DOTr

by Philippine Resources - March 09, 2022

Photo credit: Department of Transportation 

Some 30.55 percent of the Metro Manila Subway Project (MMSP) is already complete, Department of Transportation (DOTr) Undersecretary for Railways Timothy John Batan said on Tuesday.

“Despite the effects of the Covid-19 pandemic, again, back-to-back to back major milestones were still realized despite all odds,” Batan said during an inspection of the MMSP’s Valenzuela depot.

He said 576 out of the 6,400 tunnel rings needed for the partial operability segment of the MMSP have been completed, with more underway at the MMSP’s 7.5-hectare fabrication yard in Norzagaray, Bulacan.

The DOTr has acquired 197,000 square meters of land and 585 structures from 324 property owners as part of the project’s right-of-way acquisition.

Despite this, he said there has been no “forced eviction resettlement” of the 183 informal settler families affected by the project through the help of the Valenzuela City government.

Through a right-of-way agreement signed with the Department of National Defense – Armed Forces of the Philippines (DND-AFP) in December 2020, he said the MMSP will make use of 50,000 square meters of DND-AFP land, with an additional 60,000 square meters of land for tunneling works, and additional 55,000 square meters of land for temporary works.

“This partnership forged between the DND-AFP and DOTr, under the leadership of Secretary [Delfin] Lorenzana and Secretary [Arthur] Tugade, will not only enable DOTr to fast track its access to construction and work sites needed for the subway but will also give DND and the AFP a fair and recurring source of resources,” Batan said.

He said the first two out of 25 tunnel boring machines to be used in the project arrived in February 2021 while the PHP66 billion contract for the MMSP’s electromechanical systems has been awarded to Mitsubishi Corporation in October 2021

The PHP27 billion contract for 240 subway train cars was awarded to the J-Trec-Sumitomo Joint Venture in December 2020.

“With today's inspection of the MMSP, we are showing how decades of ‘plan, plan, plan,’ how decades of ‘drawing, drawing, drawing,’ and how decades of talk, talk, talk’ have changed to ‘Build, Build, Build,’” Batan said.

The MMSP will be the country’s first underground railway system and will provide mass transit in the National Capital Region (NCR)—from Valenzuela City to FTI in Taguig City, Parañaque City, and Ninoy Aquino International Airport (NAIA) Terminal 3 in Pasay City, and will further extend to the north and south of NCR.

With 17 stations—two of which are interoperable with the North-South Commuter Railway line—the MMSP is seen to reduce travel time between Quezon City and NAIA from one hour and 10 minutes to just 35 minutes. By Raymond Carl Dela Cruz

 

Article courtesy of the Philippine News Agency


Place your Ad Here!


Related Articles

Construction

Philippine Resources - July 27, 2021

Japan, PH sign P253m tranche for Metro Manila Subway Project

Japanese Ambassador KOSHIKAWA Kazuhiko and Foreign Affairs Secretary Teodoro Locsin Jr. signed today the second tranche of the 253.307 billion yen (253,307,000,000) financing for the Metro Manila Subway Project (phase 1). The Metro Manila Subway will be the Philippines' first completely underground railway system, began the construction in February 2019, funded by the Government of Japan. This 27km subway project is one of the flagship developments under the Build, Build, Build program, which will live on for generations to come. The subway will address the worsening congestion in Metro Manila caused by poor road network and the rising population's demand for transportation. Today’s additional funding will provide for the expansion of the original planning line to include 2 more stations (17 stations in total), a spur line to Ninoy Aquino International Airport and rail tracks that will also be used by the North-South Commuter Train. Japan's assistance, through a variety of ODA support, will provide the Philippine government funds to build this quality infrastructure utilizing Japanese state-of-the-art technologies and expertise from years of railway experience in its design, construction and operation stages.

Construction

Philippine Resources - November 15, 2021

Prep works for Metro Manila Subway at Camp Aguinaldo begins

The pre-construction works for the Metro Manila Subway Project (MMSP) at Camp Aguinaldo have officially begun on Thursday through a groundbreaking ceremony. During the event, Department of Transportation Assistant Secretary Fidel Igmedio Cruz Jr. said the ceremony marked the beginning of the construction of 192 housing units, repair and rehabilitation of Warehouse No. 1 and supply unit, general headquarters and headquarters service command, and construction of the medical gas and manifold vacuum plant housing at Camp Aguinaldo. These structures and facilities are part of the MMSP’s Advanced Works Package 2 and are meant to replace or improve those affected by Metro Manila Subway in Camp Aguinaldo—where the MMSP’s Katipunan Station will be located. “This advanced works package will replicate and improve affected DND-AFP structures and facilities with similar specific purposes and functions employing modern design, technology, and materials,” Cruz said. The project package, he said, was awarded to and will be built by a local contractor, Specified Contractor and Development Incorporated. “'Yung packages MMSP 102 and 103 are about to complete procurement. That's why ito po 'yung advanced package para ma-clear 'yung right-of-way nung madadaanan ng train (MMSP packages 102 and 103 are about to complete procurement. That’s why this advanced package has commenced so that we can clear the right-of-way for the train service),” Cruz said. To date, he said the detailed designs for the MMSP are at 60 percent complete while the replication and improvement of affected facilities at the Veterans Memorial Golf Club—where the MMSP’s North Avenue Station will be located—is at 45 percent complete. In total, he said five DND-AFP properties would be developed to create “convenient access points and multi-modal transport plazas” for five subway stations. Some stations of the Metro Manila Subway System will rise on government properties, such as Camp Aguinaldo, to ensure that it is accessible to the riding public. In December last year, DOTr Secretary Arthur Tugade and Defense Secretary Delfin Lorenzana signed a right-of-way usage agreement for the MMSP. The MMSP is a 33.103-kilometer underground rail system traversing Ugong Valenzuela to the Ninoy Aquino International Airport Terminal 3 and aims to accommodate up to 370,000 passengers per day by its first year of operation. 

Construction

Philippine Resources - May 09, 2022

Tugade signs P17.75-B deal for phase 1 of Metro Manila Subway

Department of Transportation (DOTr) Secretary Arthur Tugade Thursday signed a contract worth PHP17.75 billion as part of the first phase of the Metro Manila Subway. The contract package, dubbed CP104 and that was awarded to Tokyu-Tobishima Megawide Joint Venture (TTM-JV), includes the construction of two subway stations and tunnels at Ortigas North and South. The contract was signed at an event at Edsa Shangri-La in Mandaluyong City between Tugade and executives of the TTM-JV. During the event, right-of-way usage agreements were also signed between DOTr and partners in the private sector including Blemp Commercials of the Philippines, Megaworld Corporation, Robinsons Land Corporation, and Ortigas & Company Limited Partnership. In a speech, Japanese Ambassador Koshikawa Kazuhiko congratulated the DOTr and the TTM-JV for the “milestone” in bringing the Metro Manila Subway closer to reality. Koshikawa noted that Tokyu construction, head of the TTM-JV, is “well-known for their significant expertise in the construction of railways and its related developments.” “I am confident that they certainly will apply Japan's cutting-edge technology and knowledge to the Metro Manila Subway’s best advantage,” Koshikawa said. The Metro Manila Subway is part of the Duterte Administration’s ‘Build, Build, Build’ program and is seen to be partially operational by 2025. Primarily funded through grants and loans from the Japanese government, the 35-kilometer subway will run from Valenzuela City to the Ninoy Aquino International Airport (NAIA) Terminal 3. It will consist of 15 subway stations, can serve up to one million passengers daily, and is seen to reduce travel time between NAIA and Quezon City from 70 minutes to 35 minutes.

Place your Ad Here!


Recent Articles

Construction

Philippine Resources - March 21, 2023

PBBM boosts transport sector thru big-ticket projects

Photo credit: Department of Transportation Several big-ticket infrastructure projects in the transportation sector have been approved or are already being implemented by the administration of President Ferdinand R. Marcos Jr., the Department of Transportation (DOTr) reported Monday. In a statement, the DOTr said the Cebu Bus Rapid Transit Project, Davao Public Transport Modernization Project, EDSA Greenways, the Light Rail Transit Line 2 (LRT-2) West Extension, and the Light Rail Transit Line 1 (LRT-1) Cavite Extension are all ongoing as of March 9 according to the National Economic and Development Authority (NEDA). These projects are among the 67 infrastructure flagship projects (IFP) that have been greenlit or are already underway out of the 194 high-impact projects under Marcos’ "Build Better More" program. In the rail sector, these approved and ongoing projects include the Metro Manila Subway Phase 1, Mindanao Rail Phase 1, Metro Rail Transit Line 3 (MRT-3) rehabilitation, Metro Rail Transit Line 4 (MRT-4), Metro Rail Transit Line 7 (MRT-7), New Cebu International Container Port, New Manila International Airport (Bulacan International Airport), North-South Commuter Railway (NSCR), Philippine National Railways (PNR) South Long Haul, and the Subic Clark Railway. The New Dumaguete Airport Development Project (Bacong International Airport) and the Integrated Flood Resilience and Adaptation (InFRA) Phase 1 have also both been approved by NEDA, with six projects awaiting approval. Last week, the NEDA Board, led by Marcos, approved 194 high-impact priority projects with a total cost of around PHP9 trillion. The board also approved amendments to the 2013 Joint Venture guidelines to support the government’s push for more investments in the country’s infrastructure. PNR suspension Meanwhile, Senate President Pro Tempore Loren Legarda has expressed alarm over an impending suspension of select PNR routes due to the NSCR, saying it will affect thousands of commuters, mostly students and workers. “The welfare of the riding public should always be prioritized yet it remains to be seen whether such proposed solutions would effectively and sufficiently address the riding public's urgent demands in time for the imminent suspension of the operations of the PNR,“ Legarda said in her explanatory note on Senate Resolution No. 546. The PNR plans to suspend operations of certain routes for up to five years to facilitate the faster construction of the 55-kilometer NSCR. The construction will start in May and PNR may suspend the routes between Governor Pascual in Malabon City and Calamba City in Laguna, and well as Alabang, Muntinlupa City to Calamba. The Tutuban, Manila-Alabang route will be suspended in October and will affect between 20,000 and 25-000 passengers daily. Legarda urged the Committee on Public Order, chaired by Senator Grace Poe, to look into the impending suspension and come up with alternative solutions.   Article courtesy of the Philippine News Agency

Mining

Philippine Resources - March 21, 2023

Global Ferronickel Holdings, Inc. signs purchase agreement with Baosteel Resources for 1.5 million WMT

Photo credit: Global Ferronickel Holdings Global Ferronickel Holdings, Inc. (FNI), has just signed an Annual Purchase Agreement with Baosteel Resources International Co. Ltd. for the supply of 1.5 million WMT of nickel ore for the 2023 mining season. The nickel ore will be coming from FNI’s operating mines in Surigao del Norte and Palawan, operated by Platinum Group Metals Corporation (PGMC) and Ipilan Nickel Corporation (INC), respectively. “Our two operating mines have given us the ability to undertake year-round production to better support the growing demand from China. The easing of COVID-19 restrictions and the robust growth of China’s property sector that is driving the need for stainless steel will help boost the nickel industry,” said Dante R. Bravo, FNI President. Should stockpile inventory permit, one-third of the shipment will be composed of lowgrade nickel ore with 0.90% nickel content and 49% iron content while the remainder will be medium- to high- grade nickel ore with 1.30%-1.60% nickel content and 15%- 25% iron content. The selling price of each shipment will be set on a monthly basis according to the prevailing market price at the time of price setting. Baosteel Resources International Co., Ltd. is a wholly owned subsidiary of the top Chinese steel manufacturing corporation China Baowu Steel Group and is engaged in the business of mineral resource investment, trading, and logistics services. Notably, the company highly specializes on trading of metallurgic raw material with annual volume of over 60 million tons covering a vast range of products such as iron, ore, coal, alloys, non-ferrous metals, ferrous scraps, metallurgical flux, etc. Baosteel Resources maintains over 100 overseas suppliers and over 40 overseas clients. The Company’s headquarters is located in Hong Kong with footprints in Australia, Singapore, South Africa, Indonesia, and several others.   Article courtesy of the Philippine Stock Exchange

Mining

Philippine Resources - March 21, 2023

Celsius enters into initial binding deed and agreement with local companies to progress MCB Project

Photo: Signing of Binding Deed and Agreement (Left to right: PMR Holding Corp. President Dan Chalmers, CLA Chairman and MMCI President Atty. Julito “Sarge” Sarmiento, Sodor, Inc. President Ms. Erika Chalmers, and CLA Executive Director and MMCI Country Operations Director, Peter Hume). Celsius Resources Limited  is pleased to announce that on 17 March 2023 the Company’s wholly owned subsidiary, Makilala Holding Limited ("MHL"), entered into a binding deed with Sodor, Inc. for Sodor to acquire a 60% legal ownership in Makilala Mining Company, Inc. (“MMCI”) for consideration of PHP 300 million (approximately A$8.2 million as at the date of this announcement), on terms and conditions described in the following paragraphs. The signing of the Deed is a significant milestone as it will enable MMCI to apply for an MPSA for the MCB Project with the Philippine Government. As previously advised by the Company, under Philippine law, an MPSA must be held by a company that is at least 60% Filipino owned. In addition, the Company and its wholly owned subsidiaries MHL, MMCI, and PDEP Inc. (“PDEP”) entered into an accompanying binding letter agreement with Sodor and its affiliate PMR Holding Corp. (“PMR”) (together, the “Parties”) to agree on the timeline for, and that delivery to Sodor Inc. of share certificates representing 60% of MMCI’s outstanding shares pursuant to the Deed shall be made only after, the funding by Sodor Inc. and PMR of approximately ~US$43 million for a 30% economic interest in the MCB Project ("Funding Commitment"). 3 The MCB Project will be composed of MMCI and PDEP, both wholly owned subsidiaries of Celsius. The Parties shall rescind the Deed if Sodor and PMR are not able to provide the Funding Commitment within two years from signing, unless the period is shortened or extended by mutual agreement of the Parties. As at the date of this announcement the amount of the Funding Commitment, which is inclusive of the MMCI Consideration, is approximate as the Parties will confirm the size and timing of payment of the Funding Commitment following completion of a bankable feasibility study on the MCB Project. Provision of the Funding Commitment also remains subject to completion of negotiation and execution of binding definitive long form legal documentation. The Philippine Government has otherwise advised MMCI that it has met all of the other technical requirements to obtain the MCB Project’s required environmental and mining permits. Celsius Non-Executive Chairman and MMCI Chairman and President, Atty Julito R. Sarmiento, commented: “We are indeed honored to have Sodor Inc. as our local partner in our vision to develop the MCB Project as a model for Transformative Mining in the Philippines. Our principles and visions are aligned, which is a powerful step towards developing and operating the MCB Project in a responsible and sustainable manner benefitting both our shareholders and local stakeholders. It has always been our commitment, particularly to the Balatoc Tribal Community, that central to the mine development is cultural respect, social development, and environmental protection. Sodor Inc. shares the same commitment, and is thus a perfect partner in developing the MCB Project.”   Article courtesy of Celsius Resources. The full press release can be found HERE

Place your Ad Here!

Place your Ad Here!

Join the Philippines'

Mining, Construction and Industry Community

Be the "First" to get our exclusive Digital Magazine & Newsletter.