Cebu-Cordova Link Expressway 83% Complete

By: Philippine Resources September 22, 2021

Photo credit: Cebu-Cordova Link Expressway

As of August 31, 2021, the construction progress of the Cebu-Cordova Link Expressway (CCLEX) project was at 83.84 percent.

The P30-billion toll bridge, which will be substantially completed by the end of 2021, will use a full electronic toll system when it opens to motorists in the first quarter of 2022 to enable faster traffic flow and seamless travel.

The project recently marked a milestone with the completion of the installation of all 56 stay cables that hold the main bridge deck. On September 11, the Cebu Cordova Link Expressway Corporation (CCLEC), through its contractor, installed the last and longest stay cable, which is 219 meters long.

The gap on the main bridge, on the other hand, is now down to only two meters before span closure and preparations are underway for the lowering of the form travelers. These form travelers, which weigh 500 tons in each tower, were used to construct the main bridge’s pier table and deck.

Also, all 434 NU (Nebraska University) girders for the entire project have already been installed. With this, the mobile launching gantry used to install the girders have been demobilized.

At the Cebu South Coastal Road (CSCR) on ramp and off ramp sections of CCLEX, construction of its substructures is complete. Ongoing works are now on the installation of precast planks and the concreting of deck slab.

Also finished is the 200-meter pedestrian footbridge beside the CSCR with all six prefabricated steel walkways already installed. The footbridge will start near the U-turn slot of the South Road Properties’ welcome tower and will connect to the on-ramp sidewalk of CCLEX.

At the Cebu viaduct, the construction of deck slab is ongoing. The Cordova viaduct, on the other hand, is now structurally complete with its substructure already done. Installation of handrails are underway.

At the causeway, embankment works continue to progress with the placing of 20 vent pipes, which equalize the flow of seawater along the Cordova Channel, is finished.

Also structurally complete are the four low-level bridges along the causeway, which will provide fishermen continued access to their fishing grounds.

Aside from these, works are ongoing for the toll plaza and the CCLEX Operations and Maintenance Center.

CCLEX, highlighted by its iconic crosses on top of the twin pylons of the cable-stayed main bridge over the Mactan Channel, is Metro Pacific Tollways Corporation’s (MPTC) first toll road project outside Luzon.

CCLEX, which will be the third link to Mactan Island from Cordova Municipality to mainland Cebu through Cebu City’s South Road Properties, has a design speed of 80 kilometers per hour (kph) and a navigational clearance or height of 51 meters to allow large vessels to pass underneath the bridge.

Not only is CCLEX seen to reduce traffic and make traveling more convenient but also spur trade activities and open greater economic opportunities for Cebu and the rest of the Visayas region.

CCLEX is a project of Cebu Cordova Link Expressway Corporation (CCLEC), in partnership with the local government units of Cebu City and Municipality of Cordova.

CCLEC is a wholly owned subsidiary of MPTC, the toll road arm of Metro Pacific Investments Corporation (MPIC), a publicly listed infrastructure holding company and a member of the MVP Group of Companies.

MPTC is the largest toll road concessionaire and operator in the Philippines, which expansion goals include establishing toll operations in the Visayas, other parts of the Philippines, and in neighboring countries notably Vietnam, and Indonesia.

 

Article courtesy of Cebu-Cordova Link Expressway