The sixth and final tunnel boring machine (TBM) for the Metro Manila Subway Project's largest construction package has been launched, marking another milestone in the development of the country's first underground railway system.
Japanese construction company Shimizu Corp. said the machine was launched from Tandang Sora Station under Contract Package 101 (CP101), which is being undertaken by a joint venture comprising Shimizu, Fujita Corp., Takenaka Civil Engineering & Construction Co. Ltd. and Philippine contractor EEI Corp.
Four of the six tunnel boring machines deployed under the contract package have completed excavation. The fifth machine was launched on September 7, while the sixth is scheduled to reach Quirino Highway Station by the end of 2027.
Upon completion of the tunneling works, the underground sections connecting the project's three stations and depot under CP101 will be completed.
The Metro Manila Subway is a major public infrastructure project designed to help ease chronic traffic congestion in the capital region. Financed through a loan from the Japan International Cooperation Agency (JICA), the railway project has a total estimated cost of more than 800 billion yen.
The 33.1-kilometer underground railway will connect Mindanao Avenue in northern Metro Manila to Ninoy Aquino International Airport in the south, with 17 stations, a depot and related facilities.
Construction progress
CP101, the subway's largest contract package, covers four stations: East Valenzuela, Quirino Highway, Tandang Sora and North Avenue.
It also includes six shield tunnels with a combined length of approximately 9.5 kilometers and an internal diameter of 6.1 meters, as well as a depot comprising 45 buildings, including maintenance and training facilities.
Shimizu reported that overall progress under the contract package had reached 62 percent. Station construction was also 62 percent complete, while shield tunneling had reached 71 percent and building construction 27 percent.
The contract is valued at approximately 245 billion yen, making it the largest contract ever awarded for a single urban railway package financed through a Japanese yen loan.
Construction of CP101 began in August 2021, with completion scheduled for the end of 2030.
Engineering changes accelerate construction
Shimizu said engineering reviews and constructability improvements helped shorten the original construction schedule by 10 months.
Under an early contractor involvement arrangement with the Department of Transportation (DOTr), the joint venture reviewed the original design and recommended several changes to improve construction efficiency.
These included replacing the New Austrian Tunneling Method with shield tunneling, simplifying station layouts and reducing the number of underground station levels.
The joint venture also introduced adjustments to construction planning, including prioritizing land acquisition in areas where work could begin earlier and developing interim specifications for systems such as tunnel ventilation.
It also deployed Japanese technical specialists, including riggers, formwork carpenters and plasterers, to train local workers and introduce Japanese construction quality and safety management practices.
Local employment and technology transfer
The project is supported by a multinational workforce of approximately 1,300 staff members from the Philippines, Japan and other countries, including Australia, Cambodia, India, Malaysia, Myanmar, Singapore, Sri Lanka, Taiwan, Thailand and the United Kingdom.
Shimizu said the joint venture was also expanding opportunities for Filipino engineers to undergo construction management training in Japan as part of its technology transfer commitments.
Approximately 7,000 workers are currently employed at the project site, most of whom are Filipinos, supporting local employment and economic activity.
The Metro Manila Subway, which took about half a century to progress from proposals to construction, is expected to provide an alternative mass transportation system for commuters across the capital region.
Shimizu said the joint venture would continue working to improve productivity and advance construction towards the completion of CP101.
President Ferdinand Marcos Jr. inaugurated a new section of the North Luzon Expressway (NLEX)-C5 Northlink project on Oct. 29, reducing travel time between Quezon City and Valenzuela City from 40 minutes to five minutes, while announcing a proposed P120-billion elevated road linking Balintawak and Bocaue, Bulacan.
The newly opened two-kilometer NLEX-C5 Northlink Segment 8.2 Section 1A connects Quirino Highway in Quezon City to the NLEX Mindanao Toll Plaza in Valenzuela City, providing motorists with an alternative route to major destinations in Metro Manila and Northern Luzon.
Marcos announced that motorists could use the new expressway section toll-free until the end of 2026.
The segment will operate 24 hours a day, seven days a week, accommodate all vehicle classes and is expected to serve approximately 11,000 vehicles daily.
The opening comes ahead of the anticipated increase in traffic during the All Saints' Day and All Souls' Day holidays.
The new road provides motorists traveling from Quirino Highway with direct access to the NLEX Connector, offering an alternative route to Manila, the University Belt and nearby cities while helping reduce traffic congestion along EDSA.
Northbound motorists can also use the new section to reach the NLEX Mindanao Toll Plaza and connect to the NLEX mainline toward Central Luzon.
The route also provides access to the Subic-Clark-Tarlac Expressway (SCTEX), improving connectivity to other destinations in Northern Luzon.
The additional road link is expected to facilitate the movement of people and goods, improve transport efficiency and support logistics and economic activities.
P120B elevated road project
During the inauguration, Marcos announced a proposed P120-billion elevated road project that will connect Balintawak in Quezon City to Bocaue, Bulacan.
The project will be undertaken by the MVP Group in coordination with the San Miguel Corp. (SMC) Group, following the president's call for the two business groups to work together to expand the country's road network and provide motorists with alternative routes.
Marcos said the elevated road would extend through the NLEX-Meycauayan area, providing an additional route alongside the existing highway.
He described the investment as a significant development in the government's efforts to improve traffic flow, reduce travel time and transportation costs, and make daily commutes more convenient for workers.
The president said he had encouraged the two groups to coordinate their infrastructure investments to expand available routes and improve the commuting experience.
The proposed project adds to the administration's efforts to attract private-sector investment in transportation infrastructure and address congestion along major roads connecting Metro Manila and neighboring provinces.
Part of 11.3-kilometer project
Section 1A forms part of the 11.3-kilometer NLEX-C5 Northlink Segment 8.2 project, which will eventually extend from Mindanao Avenue to C5/C.P. Garcia near Katipunan Avenue.
Once completed, the project is expected to improve connectivity between northern and southern Luzon through the eastern side of Metro Manila, providing motorists with additional routes that bypass heavily congested urban roads.
The NLEX-C5 Northlink is being developed under a public-private partnership arrangement between the government and NLEX Corp., a subsidiary of Metro Pacific Tollways Corp. (MPTC).
Under the arrangement, the Toll Regulatory Board serves as the government grantor, while NLEX Corp. acts as the private concessionaire responsible for the project.
Joining Marcos during the inauguration were Transportation Secretary Vince Dizon, Public Works Secretary Giovanni Lopez, MPTC Chairman Manuel Pangilinan, MPTC President and Chief Executive Officer Gilbert Santa Maria, NLEX Corp. President and General Manager Luis Reñon, and Toll Regulatory Board Executive Director Jayart Tugade.
Marcos also inspected the ongoing construction of Phase 1 of the Metro Manila Subway Project and received updates on its progress.
The Mindanao Development Authority (MinDA) is courting China Civil Engineering Construction Corp. (CCECC) and other private investors to help advance the long-delayed Mindanao Railway Project, while exploring potential investments in nickel, copper and gold processing, solar power and other regional infrastructure.
In a press release published on October 21, MinDA said Chairperson and Secretary Leo Tereso A. Magno met with CCECC representatives on October 9 at The Westin Manila in Ortigas to discuss private-sector participation in the railway and investment opportunities in Mindanao.
The meeting focused on identifying railway segments that CCECC could pursue through an unsolicited proposal, as well as potential investments in mineral development and energy projects.
The Department of Transportation (DOTr) has divided the proposed railway into 11 segments, some of which remain open to unsolicited proposals from private investors. Feasibility studies for Segments 1 and 3 are nearing completion, according to MinDA.
Magno encouraged CCECC to identify the segment it would like to pursue and consider submitting a proposal. MinDA offered to coordinate with relevant government agencies, including its railway team in Davao, to facilitate discussions.
“The Mindanao Railway Project remains a key infrastructure priority for us because of its potential to transform connectivity across the island,” Magno said.
“It can make the movement of people and goods faster and more efficient, strengthen links between economic centers, and open up more opportunities for our communities.”
CCECC was represented at the meeting by Philippine Branch General Manager Li Linjiang and Marketing Head Zhang Enhong. Magno was accompanied by MinDA Assistant Secretary and Deputy Executive Director Romeo M. Montenegro.
Private investment sought for long-delayed railway
The push to attract private investors comes as the government continues to explore alternative financing arrangements for the railway, following the abandonment of the original plan to use Chinese official development assistance.
The railway is intended to connect major economic centers across Mindanao, improving the movement of passengers and freight and linking agricultural production areas with markets, ports and industrial centers.
The proposed Mindanao-wide rail network has been envisioned to cover approximately 1,544 kilometers, connecting cities including Davao, General Santos, Cagayan de Oro, Iligan, Cotabato, Zamboanga, Butuan, Surigao and Malaybalay.
The first phase, known as the Tagum-Davao-Digos segment, is designed to cover about 100 kilometers and connect communities in Davao del Norte and Davao del Sur.
The project has faced financing and preparation challenges. In May, BusinessWorld reported that the DOTr was considering public-private partnerships as an alternative to the original Chinese financing arrangement and was updating feasibility studies and ridership assumptions.
The government has also pursued private participation in the third phase, which is being developed as a public-private partnership project.
The third phase is planned as a 61-kilometer passenger and cargo railway serving the industrial and commercial centers of Cagayan de Oro, including connections to Laguindingan International Airport and the Mindanao Container Port. The Public-Private Partnership Center reported in April that the project's pre-feasibility study had been completed and that further feasibility work was being undertaken.
These preparations remain separate from the discussions with CCECC, and no railway construction or financing commitment by the Chinese company was announced.
Other investors express interest
MinDA has also been approaching other prospective investors as it seeks to broaden private-sector participation in the railway.
In a separate report published by the Mindanao Times on October 21, Magno said the agency had met with seven firms to explore possible partnerships, including companies from India, Canada and the United States.
He said the government was scaling up efforts to attract private partners and move the project forward.
The railway's development has been considered a potential means of improving logistics across Mindanao, particularly for agricultural commodities that must be transported from production areas to processing facilities, warehouses, ports and consumers.
A rail network could provide an additional freight option, strengthen links between regional economic centers and reduce dependence on road transport. However, the extent of these benefits will depend on the railway's final design, financing, construction and operating arrangements.
CCECC explores mineral processing
Beyond rail infrastructure, MinDA said CCECC had expressed interest in Mindanao's nickel, copper and gold resources.
The company is considering potential investments covering construction and operations, as well as the possible establishment of a mineral-processing facility in the Philippines.
MinDA said local processing could allow the country to capture more economic value from its mineral resources rather than exporting them primarily as raw materials.
The discussions come as the government seeks to expand domestic mineral processing and downstream industries. Executive Order No. 122, signed by President Ferdinand Marcos Jr. on August 18, 2026, directs the government to promote local mineral processing, attract investments and develop industries that generate greater value from the country's mineral resources.
For Mindanao, investment in processing facilities could create opportunities to connect mineral extraction with industrial activity, infrastructure development and related services.
However, CCECC's interest remains exploratory. MinDA did not announce a finalized investment agreement, a specific processing facility, a project cost or a construction timetable.
Solar and energy projects also discussed
CCECC is also considering solar and other energy-related projects in Mindanao, according to MinDA.
The agency welcomed the company's interest in sectors beyond railway infrastructure, saying these could attract investment, create economic value and support the region's long-term development.
Potential energy investments would complement the broader infrastructure discussions, although MinDA did not disclose proposed project locations, generating capacities, investment amounts or implementation schedules.
“We welcome CCECC’s interest in exploring opportunities beyond railway infrastructure,” Magno said.
“These areas offer opportunities to attract investments, create economic value, and support Mindanao’s long-term growth.”
MinDA said it would continue engaging prospective investors and coordinating with government agencies to advance projects aligned with the region's development priorities.
The discussions with CCECC mark another step in the agency's effort to draw private capital into Mindanao's transport, mineral development and energy sectors. The next stages will depend on whether prospective investors submit formal proposals and whether the projects meet the government's technical, financial and regulatory requirements.
The Philippine government is targeting the award of a key construction contract for the $3.91-billion Bataan-Cavite Interlink Bridge by November, advancing the planned 32.15-kilometre transport link across Manila Bay.
Public Works Secretary Vince Dizon said the government was awaiting concurrence from the Asian Development Bank (ADB) before awarding Package 6, which he described as the most critical part of the project.
“We will award Package 6, which is the most critical part of Bataan-Cavite, within November,” Dizon told reporters on the sidelines of an Infrastructure Forum organised by the Economic Journalists Association of the Philippines on 19 October.
The contract award remains subject to the ADB's clearance, he said, declining to identify the prospective contractor.
The Bataan-Cavite Interlink Bridge is designed to connect Mariveles in Bataan with Naic in Cavite, providing a direct road link between Central Luzon and Calabarzon without requiring motorists to travel through Metro Manila.
The project is expected to reduce travel time between the two provinces to about 45 minutes from the current five and a half hours, improving the movement of passengers and freight while providing an alternative route around the capital's congested roads.
Six construction packages
The project is divided into six contract packages covering land approaches, marine viaducts and cable-stayed bridge sections.
The government has already awarded contracts for the two land approaches connecting the bridge to existing road networks in Bataan and Cavite.
Package 1, covering the Bataan land approach, was awarded to a consortium of China Wu Yi Co. Ltd. and Fujian Road & Bridge Construction Group Co. Ltd.
Package 2, covering the 1.3-kilometre Cavite land approach, was awarded in November 2025 to a consortium comprising China Wu Yi, Jinan Urban Construction Group Co. Ltd. and CM Pancho Construction Inc.
The remaining packages cover the marine viaducts, navigational-channel bridge spans and high-level approaches. Package 6 is among the critical sections needed to advance the main bridge construction.
The planned structure will feature two cable-stayed spans measuring 900 metres and 400 metres, alongside about 24 kilometres of marine and land viaducts and approach roads.
Once completed, it is expected to become the Philippines' longest water-spanning bridge, strengthening connections between Central Luzon, Metro Manila and the Calabarzon region.
Multibillion-dollar financing
The ADB approved financing of up to $2.11 billion for the project in 2023, while the Philippine government committed $664.23 million in counterpart funding, according to the Department of Public Works and Highways.
The bridge is intended to close a major gap in the country's road network around Manila Bay, improve regional connectivity and support the movement of goods and workers between provinces.
The ADB has described the project as a climate-resilient transport link intended to improve road-travel efficiency across Luzon and support economic activity beyond Metro Manila.
The planned November contract award would mark another step towards full-scale construction of the bridge, although the timing remains dependent on the bank's concurrence.
The Department of Transportation (DOTr) is targeting to connect Clark International Airport in Pampanga to Malanday in Valenzuela City by 2029 through the North-South Commuter Railway (NSCR), with the project set to open in phases.
DOTr Undersecretary for Railways Timothy John Batan said the initial 27-kilometer segment, comprising seven stations, is scheduled to begin operations by the end of 2027. The next phase will extend the line by 53 kilometers from Malolos, Bulacan, to Clark airport, with opening targeted between late 2028 and early 2029.
The update followed an inspection of key NSCR facilities by the DOTr, members of the House of Representatives and officials of the Japan International Cooperation Agency (JICA).
Acting Transportation Secretary Giovanni Lopez said the government was working with Congress and project partners to deliver a reliable and safe commuter rail system.
President Ferdinand Marcos Jr. has directed the agency to accelerate construction to improve daily travel for commuters in northern and southern Luzon.
The 147.26-kilometer NSCR will have 35 stations across 30 local government units, connecting Clark International Airport to Calamba, Laguna.
The system is designed to serve about 800,000 passengers daily and reduce end-to-end travel time from more than four hours to two hours once fully operational.
The railway will use 51 commuter train sets and seven express train sets dedicated to direct airport services. All eight cars of the fourth train set have been delivered and stationed at the Malanday Depot in Valenzuela City, according to the DOTr.
The inspection covered operations control centers at Clark and Malanday depots, as well as track and platform construction at Balagtas Station in Bulacan. Lawmakers also tested a train simulator and viewed the electric multiple-unit train sets at Malanday.
Under the updated schedule, the railway's southern segment from Alabang in Muntinlupa City to Calamba is targeted to begin operations by 2031. The central section connecting Valenzuela and Alabang is scheduled for full operations by 2033.
The project is jointly financed by the Japanese government through JICA and the Asian Development Bank.
House Committee on Flagship Programs and Projects Chairman Rep. Kenneth Gatchalian pledged congressional support for the project and its implementation targets.
Once completed, the NSCR is expected to improve connectivity between major urban centers, employment hubs and transport gateways across Luzon, including direct rail access to Clark International Airport.
The Metro Manila Subway Project (MMSP) has achieved its first tunnel breakthrough, connecting the North Avenue and Quezon Avenue stations in Quezon City in a key milestone for the country’s first underground railway system.
The breakthrough was completed Sept. 14 under Contract Package 102 (CP 102), when a tunnel boring machine (TBM) broke through the concrete diaphragm wall of the Quezon Avenue Station after excavating a 1.12-kilometer southbound tunnel from the south end of North Avenue Station.
CP 102, undertaken by the Nishimatsu-DMCI Joint Venture (NDJV), covers about 3.1 kilometers of subway tunnels and the construction of the Quezon Avenue and East Avenue stations.
The diaphragm wall at Quezon Avenue Station was constructed using fiberglass rebar instead of conventional steel reinforcement. DMCI said the design was intended to prevent unnecessary damage to the TBM cutterhead during the breakthrough.
President Ferdinand Marcos Jr. later visited the Quezon Avenue Station to inspect the breakthrough and the tunneling works.
The completed southbound tunnel connects North Avenue and Quezon Avenue stations, with tunneling continuing toward East Avenue Station.
NDJV officials present at the milestone included Nishimatsu Construction Co. Philippine Branch Office General Manager Keiji Matsushita, MMSP CP 102 Project Director Osamu Iwata, DMCI Senior Vice President for Project Partnerships Rebecca E. Civil, DMCI Operations Director Dwight A. Ta-ala and MMSP CP 102 Deputy Project Director Reynaldo T. Lazaro.
The breakthrough marks the first such achievement in the MMSP and highlights the joint venture's use of specialized engineering and construction techniques in building the subway.
The 33.1-kilometer MMSP will have 17 stations connecting Valenzuela City to Ninoy Aquino International Airport Terminal 3 in Pasay City. Once fully operational, the subway is expected to reduce travel time along the route from more than 1 hour and 30 minutes to about 41 minutes.
Transportary Secretary Banoy Lopez and Senate Finance Committee Chairman Sen. JV Ejercito on Thursday inspected major railway projects in Metro Manila, a day after President Ferdinand Marcos Jr. broke ground for the Metro Manila Subway Project (MMSP) Ninoy Aquino International Airport (NAIA) Station.
The inspection covered the ongoing construction of the North-South Commuter Railway (NSCR) and the Metro Manila Subway, as the government moves to accelerate rail projects aimed at improving mobility and easing traffic congestion.
Marcos has directed the Department of Transportation (DOTr) to speed up railway construction to ensure timely project completion and improve the daily commute of Filipinos.
Lopez said the DOTr was expediting construction of the two major rail systems to help commuters save travel time and improve productivity.
“Ang maganda dito na ipakita natin kay Sen JV na ang pagpro-protekta niya, kasamahan niya sa Senado at Kongreso, pagprotekta niya ng pondo ng NSCR at subway. Sen., meron po talagang nararating at kinahihinatnan. We have to push more,” Lopez said.
“Now, we really need this kind of project, itong mga railway, itong subway, itong NSCR,” he added.
Ejercito, meanwhile, assured the DOTr of continued Senate funding support for the projects, saying rail systems are critical modes of transportation that will benefit thousands of commuters.
“Sana ngayon tuloy-tuloy under my [Finance Committee chairmanship], that’s why I wanted to see it for myself to make sure that the funding will not be disrupted anymore para no more delays,” Ejercito said.
He said the goal was to see the NSCR and MMSP become operational as soon as possible, particularly for commuters in Metro Manila, Laguna and Pampanga.
During the inspection, Lopez and Ejercito visited the NSCR West Valenzuela Station and Operations Control Center, the MMSP depot and Quirino Station, and the Philippine Railway Institute (PRI).
They also inspected an NSCR eight-car train set with a capacity of at least 2,200 passengers per trip.
The NSCR and MMSP, both funded with support from the Japan International Cooperation Agency (JICA), are expected to improve connectivity across Metro Manila and nearby provinces while supporting economic activity beyond the capital.
Once operational, the 147-kilometer NSCR, with 35 stations, is expected to serve at least 800,000 passengers daily across Metro Manila, Central Luzon and Southern Luzon.
The 33-kilometer MMSP, meanwhile, is projected to serve about 519,000 passengers in its opening year.
The subway is expected to cut travel time between Valenzuela City and NAIA Terminal 3 to about 40 minutes, from the current estimate of one hour and 35 minutes.
Lopez and Ejercito were joined by Japanese Embassy Minister for Economic Affairs Yokota Naobumi, JICA Senior Representative Takanori Morishima, Transportation Undersecretary for Railways Timothy John Batan, Transportation Undersecretary for the Philippine Railways Institute Anneli Lontoc, and Assistant Secretaries Eduardo Danilo Macabulos and Paul Anthony Pangilinan.
Construction of the 33-kilometer Metro Manila Subway Project has reached nearly 60 percent completion, President Ferdinand Marcos Jr. said Wednesday as the government broke ground for the subway station at Ninoy Aquino International Airport (NAIA) Terminal 3.
“The whole Metro Manila Subway project has achieved nearly 60 percent overall progress, with construction activities underway across much of its alignment,” Marcos said during the groundbreaking ceremony.
The NAIA Terminal 3 station is part of Contract Package (CP) 109, which also includes the construction of connecting tunnels between Taguig City and Pasay City.
Once completed, the subway is expected to cut travel time between Valenzuela City and NAIA from about 1 hour and 30 minutes to 40 minutes.
Marcos said the project has reached two key milestones that would support its completion, including securing the right of way for the entire station area.
The project will also use underpinning technology from Japan, allowing construction to proceed beneath existing infrastructure while maintaining structural integrity.
“This progress reflects the cooperation of the government, the private sector, and all our other development partners,” Marcos said.
He called on contractors, engineers and workers to complete the project safely, efficiently and on schedule.
“I ask that you carry out this project safely, efficiently, and on time, with the quality that generations of Filipinos deserve,” Marcos said.
Right on track
Department of Transportation (DOTr) Acting Secretary Giovanni Z. Lopez said the subway project remains on track for completion by 2031, with operations expected to begin the following year.
Funded by the Japan International Cooperation Agency (JICA), the subway will have about 17 stations and is projected to serve between 400,000 and 800,000 passengers daily once fully operational.
Lopez said only CP 108 remains under procurement. The package will cover the subway section connecting the new Senate building to Lawton in Taguig City.
The subway project was initially targeted for completion in 2027, but the timeline was later moved to 2029 and then to 2032 because of right-of-way issues.
Lopez said one of the most difficult right-of-way issues involved properties inside Corinthian Gardens subdivision in Quezon City.
He said the issue was resolved following the enactment of Republic Act 12289, or the Accelerated and Reformed Right-of-Way (ARROW) Act, last year.
“We no longer have a problem with that; the private owners have indeed agreed to a negotiated sale of their property,” Lopez told reporters in Filipino on the sidelines of the groundbreaking ceremony.
The Metro Manila Subway is intended to provide a high-capacity rail connection across Metro Manila and reduce travel times along one of the country's most congested corridors.
About 30 local and international companies have expressed interest in railway development projects of the Department of Transportation (DOTr), signaling private-sector interest in the government's pipeline of mass transport investments.
The companies participated in the DOTr's two-in-one Market Engagement Conference on Monday at the Asian Development Bank headquarters in Mandaluyong City.
The conference covered two projects: the Institutional Capacity Strengthening: Project Delivery Support for Railway Projects (CDC-1) and the North-South Commuter Railway New Clark City Extension (NSCR-NCC-Ex) Project's detailed engineering design and international checking engineer.
The initiative supports President Ferdinand Marcos Jr.'s directive to accelerate the completion of mass transportation projects.
Acting Transportation Secretary Giovanni Lopez said expanding the country's railway network would improve regional connectivity and the movement of people and goods.
"We thank the companies showing interest in helping us further improve the rail sector for more comfortable and faster travel for passengers," Lopez said.
"We need to add more trains and improve the capabilities of the people behind the projects so we can complete them sooner," he added.
DOTr Assistant Secretary for Railways Infrastructure and Public-Private Partnerships Eduardo Danilo Macabulos said the strong participation demonstrated private-sector confidence in the agency's procurement processes.
"This shows two things. First, many companies and consultants in the Philippines and abroad are ready to help us implement the projects," Macabulos said.
"Second, there is still trust from the private sector to participate in our projects because they believe we can conduct procurement transparently and fairly, and that the DOTr has the capacity to continue our railway pipeline next year," he added.
Macabulos said railway projects would help ease traffic congestion while providing more comfortable transportation between Metro Manila and nearby provinces.
"At the Department of Transportation, we believe that the real answer to traffic is mass transportation," he said. "Our railways will ease the commute not only in Metro Manila but also in nearby provinces such as Pampanga and Laguna, extending to Tarlac."
Under the CDC-1 project, the consultant will help strengthen the institutional capacity of the DOTr's railway-sector project management offices in project delivery, performance management and capability development, according to the DOTr Rail Unified Project Management Office.
Meanwhile, the NSCR-NCC-Ex is an 18.1-kilometer railway extension that will include the construction of an additional station in New Clark City, Tarlac.
The proposed extension is intended to strengthen the transportation network and help ease traffic congestion in the Greater Capital Region by extending the North-South Commuter Railway farther north.
India’s state-owned railway consultancy Rail India Technical and Economic Service Ltd. (RITES) is exploring participation in at least three major Philippine rail projects, including the Mindanao Railway, a mass rail system in Cebu and the extension of the Philippine National Railways (PNR) from Tutuban, as the government seeks to accelerate infrastructure development.
President Ferdinand Marcos Jr. met with RITES officials in New Delhi on September 12 to discuss potential cooperation on the projects, according to the Presidential Communications Office (PCO).
Presidential Communications Office Acting Secretary Dave Gomez said RITES could participate either as a consultant or through a public-private partnership (PPP), while also helping the Philippines explore possible official development assistance (ODA).
“The first priority is the Mindanao Rail System. So they will look at it and study it. Next is the mass rail system in Cebu,” Gomez said in Filipino after the meeting.
“And the third that they will enter is the extension of the PNR from Tutuban,” he added.
The discussions come as the Philippines advances several large-scale railway projects intended to expand intercity connectivity, improve urban transportation and strengthen links between major economic centers.
SCMB railway targets 2027-2028
The potential involvement of RITES comes as the government prepares the next stages of the proposed Subic-Clark-Manila-Batangas (SCMB) Railway, a 250-kilometer rail line being positioned as a cornerstone of the Luzon Economic Corridor (LEC).
Finance Undersecretary Maria Angela Ignacio said last week that construction could begin by the end of 2027 or in 2028, depending on the outcome of ongoing feasibility studies.
The feasibility work is being supported by international partners. The US Trade and Development Agency provided $3.8 million in assistance in 2025 for transport modeling, port-rail integration and legal and institutional frameworks, while Sweden provided P74 million for a study covering signaling systems and operational models.
The Asian Development Bank has also committed $8 million in technical assistance for the SCMB Railway.
The government has pitched the railway to international investors as one of the major projects under the Luzon Economic Corridor, which is intended to strengthen infrastructure and economic links across Luzon.
India offers space technology cooperation
Marcos also met with officials of the Indian Space Research Organisation (ISRO) to discuss potential cooperation with the Philippine Space Agency (PhilSA).
Gomez said India could provide technical expertise and share its experience as the Philippines works toward its long-term goal of launching its own satellite.
A Philippine satellite capability would support applications including communications, weather forecasting, climate monitoring, and defense and security, according to Gomez.
The meetings were held during Marcos’ visit to India to attend the BRICS Summit at the invitation of Indian Prime Minister Narendra Modi. Marcos is participating in the summit in his capacity as chair of the Association of Southeast Asian Nations (ASEAN) for 2026.
Marcos was accompanied during the meetings by Foreign Affairs Secretary Ma. Theresa Lazaro, Finance Acting Secretary Frederick Go, Transportation Secretary Giovanni Lopez, PhilSA Director General Gay Jane Perez, and Philippine Ambassador to India Josel F. Ignacio.
Before the RITES and ISRO meetings, Marcos met officials of the Coalition for Disaster Resilient Infrastructure (CDRI) following the Philippines’ entry into the coalition. Discussions focused on strengthening Philippine infrastructure against disasters and climate-related risks.
The Philippine government is also seeking private investment for other major infrastructure projects. At the inaugural Luzon Economic Corridor Investment Forum, officials presented at least 38 projects worth more than $20 billion to investors and business executives, including the SCMB Railway and a proposed $4.1 billion Sangley Point International Airport package.
Construction of the Sangley Point International Airport (SPIA) in Cavite is targeted to begin in the third quarter of 2027, with financing arrangements now being finalized as the project moves into its initial pre-construction phase, a project adviser said.
Construction is expected to take about 17 quarters, or roughly four years and three months, putting the target for the airport’s initial commercial operations in 2031, according to Sol Castro, managing director and senior adviser at CFP Transaction Advisors. He made the disclosure during last week’s Luzon Economic Corridor Investors Forum.
CFP is part of the project development management and advisory group appointed by the Cavite provincial government for SPIA.
Castro said the project has secured the necessary consents, including the agreement with the provincial government of Cavite and clearance from the Philippine Competition Commission.
Several key approvals and arrangements remain pending, however, including the Philippine Reclamation Authority’s approval of the final reclamation configuration, land-access arrangements with the Department of National Defense, and airspace clearance from the Civil Aviation Authority of the Philippines (CAAP).
The government has moved to expedite those processes. President Ferdinand Marcos Jr. issued Administrative Order No. 44 on June 3 directing concerned national government agencies and encouraging Cavite local government units to prioritize and accelerate permits, clearances, licenses, certifications and other authorizations required for SPIA.
The order also created a joint technical working group co-chaired by the Department of Transportation and the Philippine Reclamation Authority, with representatives from the Department of Environment and Natural Resources, Department of National Defense, Department of the Interior and Local Government, Department of Justice, CAAP and the Cavite provincial government.
The group is tasked with addressing issues that could delay the project and ensuring that reclamation complies with environmental and technical requirements. It is also required to submit quarterly progress reports to the Office of the Executive Secretary.
$2 billion first phase
The first phase of SPIA is estimated to cost about $2 billion and will involve a 251-hectare reclamation development adjoining existing government-owned land.
The phase includes extending the existing runway from 2.1 kilometers to 3.2 kilometers, building a new passenger terminal, apron and cargo facilities, and developing the necessary landside estates.
Castro said the project will rely largely on an enabling reclamation platform and existing government-owned land, reducing land assembly and consolidation requirements.
“There’s going to be minimal displacement except for the Philippine Navy facilities that are there, and that there are no right-of-way risks,” Castro said.
SPIA will be developed around the existing Sangley aerodrome and is planned to accommodate wide-body aircraft and freighters.
The second phase will be incorporated into the airport’s design from the outset and will allow expansion of the development to the full 544-hectare landform as passenger and cargo demand increases.
Boulevard, Cargo City
The broader SPIA development also includes the 4.4-kilometer Sangley Boulevard, a high-speed access expressway and causeway intended to connect the airport directly to the Manila-Cavite Expressway (CAVITEX) and onward to the Cavite-Laguna Expressway (CALAX).
Construction of the boulevard is targeted to start in the first quarter of 2027, ahead of the airport's planned construction start, with completion targeted for the first quarter of 2029.
The project also includes a 190-hectare Cargo City designed for aviation support services, logistics, warehousing and e-commerce fulfillment.
SPIA is envisioned as a modern international hub airport and part of the Greater Capital Region’s multi-airport gateway system, alongside Ninoy Aquino International Airport, Clark International Airport and New Manila International Airport.
Public-private partnership
The Cavite provincial government and SPIA Development Consortium (SDC) signed a joint venture and development agreement for the project in 2023.
The consortium comprises House of Investments Inc., Cavitex Holdings Inc., Samsung C&T Corp., MacroAsia Corp., Munich Airport International GmbH, and Ove Arup & Partners Hongkong Ltd.
SDC was formally awarded the project in September 2022 after no competing firm challenged its unsolicited proposal. The consortium had submitted the proposal in 2021 after the Cavite provincial government declared its second bidding for the airport project unsuccessful.
SPIA is being developed as a public-private partnership intended to expand the Greater Capital Region’s aviation capacity while creating an international passenger and cargo gateway in Cavite.
During the PhilEnergy Expo 2026, Meralco’s Head of Sustainability and Coms, Atty. Christer A. Gaudiano, introduced Meralco PowerGen Corporation (MGEN)’s Terra Solar and discussed the milestones of the project.
He was one of the five guest speakers at The PICC Energy Leadership Forum on June 26, 2026, held at World Trade Center, Pasay City. The forum was hosted by Philippine Infrastructure & Construction Club (PICC) in partnership with PhilEnergy. The forum’s theme is “Accelerating Green Resilience: Powering the Next Decade of Philippine Energy Security”.
The PICC Energy Leadership Forum was held on the final day of the PhilEnergy Expo 2026--a comprehensive 3-day energy trade event that centers on advancing clean energy, sustainable power technologies, and national energy security.
President Ferdinand Marcos Jr. delivered his fifth State of the Nation Address (SONA) on July 27, 2026, at the House of Representatives in Quezon City.
During his 2026 SONA, President Marcos Jr. emphasized the administration's aggressive infrastructure initiatives, focusing on the rehabilitation and reopening of vital bridges, namely: the San Juanico Bridge, Liloan Bridge, and Calbiga Bridge. The three bridges are part of the Maharlika Highway (Pan-Philippine Highway) which is the country’s principal land transportation pathway that connects Luzon to Mindanao.
Since the rebranding of Antrak Philippines to FLS Group Philippines, Inc. in December 2024, the company has been involved in major projects for the country and is geared to accomplish more in the months ahead. This year, The FLS Group partnered with partnered with Miescor (Meralco Industrial Engineering Corporation) who was the EPC for the Meralco PowerGen Corporation (MGEN), MTerra Solar Project to transport 20 heavy-duty power transformers for the massive MTerra Solar project--the world's largest integrated solar power and battery storage facility.
Engineering the impossible, FLS Group navigated NLEX and reinforced 27 bridges for world’s largest solar project. Planning and executing the successful crossing of a 260 MVA power transformer weighing 136.48 tons in NLEX San Fernando is a historic transport operation, as it was the first time such a heavy and oversized load was granted passage on the North Luzon Expressway.
Among other things, FLS Group also won the “Sustainable Excellence in Logistics” award on June 16, 2026, for 'Drive the Change' at the Breakbulk Green World 2026 Awards. This was held at Rotterdam, Netherlands. Breakbulk Green World Awards is an international award that celebrates leading companies, innovative projects, and individuals in the project cargo and breakbulk logistics industry who drive sustainable solutions and a greener future.
Looking back in February 2024, the Company's current local principals successfully acquired full ownership by purchasing all shares previously held by Antrak Logistics (Australia), a former foreign stakeholder and subsidiary of a French Logistics Company. This landmark transaction marked a significant step toward local governance, strengthening the Company's operational independence and positioning it for greater agility and growth in the Philippine market.
Motorists in General Santos City can now use the long-delayed General Santos Underpass after it officially opened to traffic on July 29, two days ahead of the July 31 deadline set by Public Works Secretary Vince Dizon.
Located at the intersection of Mabuhay-Bulaong Road and Digos-Makar Road in Barangay Mabuhay, the underpass is expected to ease congestion along one of the city's busiest transport corridors, improving the movement of commuters, cargo trucks and agricultural products entering and leaving the city.
The project, which began construction in June 2022, was originally scheduled for completion in September 2024. However, it encountered multiple delays, pushing its target completion first to the end of 2025 before finally opening in July 2026.
According to the Department of Public Works and Highways (DPWH), the delays were largely due to a major redesign after engineers encountered sandy volcanic soil and a high groundwater table during excavation. Officials warned that the original design could have caused the underpass to flood during heavy rains.
To address the issue, the DPWH redesigned the drainage system by incorporating a large underground reservoir, perforated drainage pipes and a gravity-fed drainage system that channels water toward the nearby Silway River. The revised design is intended to reduce reliance on mechanical pumps, lower long-term maintenance costs and minimize the risk of flooding.
The project also faced right-of-way constraints and delays in relocating water and power utilities, which slowed construction of the access roads.
The underpass project carries an estimated construction cost of P681 million, although the national government released more than P814 million in funding between 2021 and 2024 to accommodate project requirements and contingencies.
The opening follows President Ferdinand Marcos Jr.'s directive for the DPWH to accelerate the completion of long-delayed infrastructure projects nationwide.
Dizon inspected the underpass on June 9, 2026, where he ordered contractors and DPWH officials to ensure the facility would be operational before the end of July. The project was opened to motorists two days ahead of that deadline.
The General Santos Underpass forms part of the administration's Build Better More infrastructure program, which seeks to improve mobility, reduce travel times and strengthen logistics networks across the country.
General Santos City serves as the economic center of the Soccsksargen region and hosts one of the Philippines' busiest fish ports. The improved road infrastructure is expected to facilitate the movement of goods, support regional trade and reduce daily travel delays for thousands of motorists using the corridor.
In a crucial turn of events in February, the Makati City Government has settled its dispute with Philippine Infradev Holdings Inc. This, in turn, now gives Makati City control and ownership of the discontinued underground rail line.
Philippine Infradev Holdings Inc. is a private proponent of the $3.5-billion Makati Intra-city Subway project (MkTr). The company partnered with Chinese firms for constructions; however, the project was terminated on March 11, 2025 following a Supreme Court ruling in 2023 that granted territorial jurisdiction to Taguig City and transferred 10 Makati City barangays to Taguig City.
Follow on LinkedIn:
Philippine Resources Journal
Be the "First" to get our exclusive Digital Magazine & Weekly Newsletter.