DPWH MINDANAO ROAD SECTOR PROJECT BRINGS GAME-CHANGING DEVELOPMENT IN ZAMBOANGA SIBUGAY
A key and long-awaited road project of the Department of Public Works and Highways (DPWH) in Zamboanga Sibugay Province has now contributed to the development of agribusiness, ecotourism, and logistics in the island of Olutanga and the town of Alicia.
According to Senior Undersecretary Emil K. Sadain, in-charge of DPWH infrastructure flagship projects under “Build Better More” program, the once terrible and horrible travel experienced about decades ago because of deep muddy road is already a thing of the past with the concrete paving of a highway known as Lutiman-Guicam-Olutanga Road.
The 29.7-kilometer Lutiman-Guicam-Olutanga Road, one (1) of the three (3) core road projects under the Asian Development Bank (ADB)-assited Improving Growth Corridors in Mindanao Road Sector Project (IGCMRSP) implemented and completed by DPWH thru its Unified Project Management Office (UPMO) - Roads Management Cluster II (Multilateral), is a game changer for the socio-economic growth and development of Alicia and Olutanga Island.
In his report to Secretary Manuel M. Bonoan following an occular inspection on July 7-8, 2023, Senior Undersecretary Sadain said that the construction of an inter-island Guicam Bridge which is a separate non-core component of IGCMRSP connected with the Lutiman-Guicam-Olutanga Road is 43% completed to date and target for completion by 2024.
With an entire project length of 1.21 kilometer, the bridge project to link Barangay Guicam, Alicia to Barangay Hula-Hula, Mabuhay crossing the Canaliso Strait will serve as transport and economic connector between the three (3) municipalities of the Olutanga Island which include Olutanga, Talusan, and Mabuhay and mainland municipality of Alicia toward other towns of Zamboanga Sibugay.
The long-term impact of the project will contribute to sustaining peace and security in the Island, as well as harness the socio-economic opportunities and growth of the communities.
Oluntanga Island has a vast tourism and agro-fishery potential with its long coastline of beaches, snorkeling and diving sites, production of high value aqua and fisheries products especially the fish cage farming of "Lapulapu", dried fish-making, and seaweed industry.
The P25.257 Billion IGCMRSP finance with a loan amounting P19.080 Billion by the Asian Development Bank and P6.117 Billion to be funded by the Government of the Philippines, is composed of eight ( 8 ) sub-projects with portland concrete cement paving of roads of about 151.05 kilometers and construction of 31 bridges with a total length 2,132.62 meters all located in Zamboanga Peninsula, and three (3) bridges with a total gross length of 1,790 lineal meters located in island province of Tawi-Tawi.
Also inspected by Senior Undersecretary with UPMO Project Directors Sharif Madsmo H. Hasim and Benjamin A. Bautista, Stakeholders Relations Service Director Randy R. Del Rosario, and Project Manager Emmanuel M. Supe are the completed 24-kilometer Alicia-Malangas Road with eight ( 8 ) bridges and 17.93-kilometer Siay-Gapol Road with two (2) on-going bridges located in Zamboanga Sibugay Province and the on-going 24.52-kilometer R.T. Lim-Siocon Road with eight ( 8 ) bridges connecting provinces of Zamboanga Sibugay and Zamboanga del Norte.
The DPWH UPMO - Roads Management Cluster II (Multilateral) headed by Project Director Hasim has already completed 122.07 kilometers of paved roads equivalent to 81% and 11 out of 34 bridges.
By end of December 2023, DPWH is targeting to reach the total paved roads into 143.12 kilometers and complete additional eight ( 8 ) bridges.

GOVERNMENT AIMS FOR NOVEMBER 2023 APPROVAL OF LOAN FOR BATAAN-CAVITE INTERLINK BRIDGE PROJECT
Photo credit: The Department of Public Works and Highways
The Department of Public Works and Highways (DPWH) concluded its two (2) weeks discussion with the Asian Development Bank (ADB) Fact-Finding Mission with the aim of obtaining loan approval for the Bataan-Cavite Interlink Bridge (BCIB) Project by this November 2023.
In his report to Secretary Manuel M. Bonoan, Senior Undersecretary Emil K. Sadain said that the meetings from June 16 to July 5, 2023 between the ADB Mission and the DPWH through the Unified Project Management Office - Roads Management Cluster II (UPMO-RMC II) headed by Project Director Sharif Madsmo H. Hasim and Project Manager Teresita V. Bauzon were geared towards appraising overall project readiness prior to the preparation of loan agreement for the 32-kilometer BCIB Project.
Other than the DPWH, the meetings were participated by the detailed engineering design (DED) consultant TY Lin International, Ltd. in joint venture with Pyungwha Engineering & Consulting Co., Ltd. hired by the government for preparation of the project.
In the wrap-up meeting on Wednesday, July 5, 2023, Senior Undersecretary Sadain expressed appreciation for the active engagement of ADB officials headed by Mr. Witoon Tawisok, Ms. Hiet Thi Hong, Ms. Gengwen Zho, and Ms. Myra Evelyn Ravelo; and the participation of relevant offices including the Department of Finance (DOF) during the Fact-Finding Mission.
ADB together with Asian Infrastructure Investment Bank (AIIB) has earlier committed to co-finance the civil works construction of Bataan-Cavite Interlink Bridge Project targeted to start by 2024.
The BCIB project will be divided into seven (7) contract packages with the construction to begin first in the two (2) on-land packages, package 1 which is the five (5) kilometer Bataan Land Approach and package 2 which is the 1.35 kilometer Cavite Land Approach.
Packages 3 and 4 are Marine Viaducts in the North and South with a total length of 20.65 kilometers.
Meanwhile, packages 5 and 6 are the North Channel and South Channel Bridges with a length of 2.15 and 3.15 kilometers, respectively. The 7th package involves a project-wide ancillary works.
No less than President Ferdinand R. Marcos Jr. led on March 31, 2023 a milestone ceremony for the Detailed Engineering Design (DED) of Bataan-Cavite Interlink Bridge Project at the Maritime Academy of Asia and the Pacific in Mariveles, Bataan.
The DED has taken into consideration various technical challenges such as the severe seismic loads and wind speed in the project area, need for navigation channels to accommodate large cargo vessels, seabed depth of approximately 50 meters for placing the caisson foundation, extreme climate condition and seawater rise due to climate change, etc.
As a result, the final design has included a long cable-stayed bridge at the south channel (between Cavite and Corregidor Island) with the tower height of 380 meters from the sea level.
To ensure strength, serviceability, and durability of the key structural elements, the DPWH construction supervision team will be supported by a project management consultant and engineering/design support consultant.
The feasibility study for the BCIB Project was completed under the ADBs Infrastructure Preparation and Innovation Facility (IPIF) in 2019, in which the preliminary architectural and engineering design has been prepared.
Once this bridge is completed, travel time between the provinces of Bataan and Cavite will be reduced from the current 5 1⁄2 hours to just about 45 minutes, saving more than 4 hours travel time and benefitting thousands of commuters.
Article courtesy of The Department of Public Works and Highways