April 17, 2023

Photo credit: Light Rail Manila Corporation

The first phase of the 11.7-kilometer (km) Light Rail Transit Line 1 (LRT-1) Cavite Extension Project is nearing completion, according to the Light Rail Manila Corporation (LRMC), the private operator of LRT-1.

In a statement on Friday, the LRMC said the progress rate for the project has reached 82.7 percent as of March 2023, for both civil and rail system works since it started the construction in September 2019.

“The viaduct was completed in February 2022, while the ongoing station construction includes architectural, mechanical, electrical, plumbing, fire protection, and safety works. In terms of the rail system, trackwork, and overhead catenary system installation are almost complete,” it said.

The first phase covers 7 km of the 11-km extension, including five new stations: Redemptorist Station (56 percent complete), MIA Station (61 percent complete), Asia World (51 percent complete), Ninoy Aquino Station (55 percent complete), and Dr. Santos Station (60 percent complete).

LRMC president and CEO Juan Alfonso said all civil and equipment installation works for the project are slated to be completed this year, with a focus on commissioning the entire project’s rail line by next year.

“We are optimistic that we can start commercial operations of Phase 1 by the fourth quarter of 2024 as we continue to achieve milestones with our team,” Alfonso said.

To date, the LRMC has invested over PHP30 billion in capital improvement projects to upgrade the existing systems of the LRT-1 and for the construction of the Cavite extension since the operator took over the rail line in 2015.

The LRT-1 Cavite Extension project, a public-private partnership venture that aims to add an 11.7-kilometer Baclaran-Bacoor, Cavite segment to the current 18.1-kilometer train line, will have eight stations.

The new stretch is expected to service up to 800,000 passengers per day and cut down travel time from Pasay City to Cavite from an hour and a half to just 25 to 30 minutes.

The remaining stations between Las Piñas and Niog are scheduled to become fully operational by 2027. By Raymond Carl Dela Cruz

 

Article courtesy of the Philippine News Agency

April 03, 2023

Photo credit: The Department of Public Works and Highways

The Department of Public Works and Highways (DPWH) is looking to start the construction of the Bataan-Cavite Interlink Bridge (BCIB) within the first quarter of 2024.

The 32.15-kilometer, four-lane BCIB will connect Barangay Alas-asin in Mariveles, Bataan to Barangay Timalan Concepcion in Naic, Cavite, reducing travel time from five hours to an estimated 45 minutes.

“Hopefully, we can start packages 1 and 2 this year and we could procure the other packages of this project until next year,” said Teresita Bauzon, DPWH project manager, during the Saturday News Forum in Quezon City.

The entire construction may last until mid-2028, she added.

The project will be financed by loans from the Asian Development Bank (ADB) and Asian Infrastructure Investment Bank.

“Right now, all the negotiations of the National Economic Development Authority and the ADB for funding of the construction are ongoing,” Bauzon said.

On Friday, President Ferdinand R. Marcos Jr. led the milestone ceremony for the detailed engineering design of the project at the Maritime Academy of Asia and the Pacific in Mariveles, Bataan.

Marcos asked DPWH officials, employees, and consultants to remain committed to finishing the BCIB on schedule.

"Do your best always to ensure that civil works for this bridge will commence by October this year," he said. "Do your best also to deliver what we have proposed so that our people and their localities may live out the picture we have painted as our goal as soon as possible."

The feasibility study for the project started in March 2018, funded by the ADB Infrastructure Preparation and Innovation Facility loan. By Ferdinand Patinio

 

Article courtesy of the Philippine News Agency

April 03, 2023

Photo credit: The Department of Public Works and Highways

President Ferdinand R. Marcos Jr. said Friday the PHP175.6 billion Bataan-Cavite Interlink Bridge (BCIB) project is seen to boost the regional economies of the two provinces through improved connectivity.

During the bridge's milestone ceremony in Mariveles, Bataan, Marcos said new economic opportunities would open to Bataan and Cavite and their surrounding provinces because of the easier access that will be made available through the bridge project.

The President noted that the BCIB is projected to reduce the Central Luzon - Calabarzon travel time from 5 hours to just 45 minutes, cutting as much as 86 percent.

“That will be an incredible feat when it happens and would significantly help in decongesting Metro Manila as motorists will be able to travel without passing through the metropolis," he said.

He said the bridge, once completed, would also help bring prices down for goods and services as the transport and logistics costs would decrease, thus generating immense savings all around.

The project will also support the development of seaports in the two provinces, making them potential international shipping gateways of the country, he added.

"As such, I assure you, we will remain committed to developing a highly interconnected network of transport (infrastructure) that will serve as the backbone and strong driving force of our rapid, inclusive, and sustainable (economic) growth," he said.

Marcos called on the officials and employees of the Department of Public Works and Highways, as well as all the consultants to remain committed to finishing this project on schedule.

"Do your best always to ensure that civil works for this bridge will commence by October this year," he said. "Do your best also to deliver what we have proposed so that our people and their localities may live out the picture we have painted as our goal as soon as possible."

The 32.15-km., four-lane, inter-island bridge will connect Barangay Alas-asin in Mariveles, Bataan and Barangay Timalan Concepcion in Naic, Cavite and once completed, it will be the longest bridge in the Philippines.

The BCIB will have two navigational bridges: the 400-meter North Channel Bridge and the 900-meter South Channel Bridge, which will traverse Corregidor Island. About 80 percent of the structure will be over the sea.

Primarily funded through Official Development Assistance loans from the Asian Development Bank (ADB), with co-financing from the Asian Infrastructure Investment Bank, BCIB’s construction is expected to last for 60 months and is scheduled to be completed by the end of the third quarter of 2028.

 

Article courtesy of the Philippine News Agency 

April 03, 2023

The Department of Public Works and Highways (DPWH) longest road mountain tunnel project in Mindanao is on full steam of implementation.

In his report to Secretary Manuel M. Bonoan, Senior Undersecretary Emil K. Sadain, in-charge of the implementation of DPWH infrastructure flagship projects said that tunneling activities for the 2.3-kilometer twin tube bi-lane road mountain tunnel is on the verge of reaching halfway with total length excavated for southbound and northbound direction on both ends of north and south portal at a cumulative distance of about 1-kilometer.

According to Senior Undersecretary Sadain, the tunnel is an important component of the 45.5-kilometer Davao City Bypass Construction Project which is among the infrastructure flagship projects started under the previous administration’s “Build Build Build” program and continue under the administration of President Ferdinand R. Marcos Jr. “Build Better More” development agenda to decongest traffic and reduce travel time.

Senior Undersecretary Sadain, the President Elect of the Philippine Institute of Civil Engineers (PICE) for 2024, allowed the PICE National Officers and Board of Directors headed by President April Frances Agatha Flores and Davao City Chapter President Arnel Bernardino to get an exclusive view of the on-going activities for the construction of the road mountain tunnel adopting Japanese technology with a site visit on Saturday, April 1, 2023.

During the inspection, Senior Undersecretary Sadain reviewed the progress of works and commended the project team from DPWH Unified Project Management Office (UPMO) - Roads Management Cluster 1 (Bilateral) and contractor Shimizu-Ulticon-Takenaka for their hard work and contribution towards fast-track construction.

This is the first project site visit by PICE national leaders to this flagship project of the Philippine government after over three (3) years since the unprecedented challenges of COVID-19 greatly affected everyone.

In his briefing, DPWH UPMO Roads Management Cluster 1 (Bilateral) Project Director Benjamin A. Bautista said that the tunnel construction is part of contract package I-1, the first out of six (6) contract packages, which commenced on December 2020.

This on-going contract package I-1 costing ₱13.23 Billion is financed by Special Terms for Economic Partnership (STEP) Loan between Philippines and Japan International Cooperation Agency under loan agreement numbers PH-P261 and PH-P273.

The tunnel will incorporate facilities to ensure the safety of riding public and will be closely monitored by an operation and control center located in the north portal area.

Targetted for completion by December 2024, contract package I-1 also involves the construction of four (4) lanes 3.35 meters width concrete paved road with the total length of 7.90 kilometers, three (3) pairs of bridge with the total length of 500 linear meters, two (2) underpasses, two (2) overpasses, twelve (12) box culvert (waterway), and four (4) at grade road crossings.

The Davao City Bypass Construction Project begins at Brgy. Sirawan, Toril, Davao City and will end at Brgy. J.P. Laurel in Panabo City.

It will improve the transport logistics and mitigate congestions in Davao City with travel time of just 49 minutes from the current 1 hour and 45 minutes via Maharlika Highway, thereby contributing to the economic and sound urban development of the City and the Davao Region.

For the other packages, procurement activities for packages I-2 and I-3 are currently on-going. Package II-1 started last January 2023 while procurement for package II-2 is also on-going and package II-3 is scheduled on the fourth quarter of this year.

March 31, 2023

Photo: The aerial view of the San Juanico Bridge that connects the islands of Leyte and Samar. The Japan International Cooperation Agency is considering the construction of the second San Juanico Bridge as one of the top priority projects in the country, a regional public works official said Wednesday (March 29, 2023). (Photo courtesy of Lyle Arañas)

The Japan International Cooperation Agency (JICA) is considering the construction of the second San Juanico Bridge as one of the top priority projects in the country, the Department of Public Works and Highways (DPWH) 8 (Eastern Visayas) said.

DPWH-8 Regional Director Edgar Tabacon said JICA would soon start gathering information to prepare the terms of reference for the project’s feasibility study, which will start before the year ends.

Tabacon said JICA Southeast Asia Division Senior Deputy Director Yosuke Nishii and four other JICA officials recently met with DPWH and Regional Development Council officials to understand the rationale and eventual socioeconomic role of the bridge project in the region.

“This project is very timely, now that our existing San Juanico Bridge is on its 50-year term. And we are very much grateful if this will soon materialize,” he said in an interview Wednesday.

While the proposed 1.24-km. second San Juanico Bridge only involves two lanes, Tabacon suggested that a four-lane bridge would be more effective, considering the increasing traffic.

A wider bridge will also complement the ongoing road expansion activities.

The JICA team assured the DPWH that adding more lanes would be considered and that the design of the project would be based on the results of the feasibility study, which will start in the third quarter of 2023.

Civil works for the second San Juanico Bridge are targeted to start in 2025.

In 2022, the DPWH announced that the national government would need PHP9.17 billion to build the second San Juanico Bridge connecting the islands of Leyte and Samar.

The proposed bridge will connect the towns of Babatngon, Leyte and Sta. Rita, Samar.

It will cross the Janbatas Channel, a portion of the San Juanico Strait that separates the region’s two major islands.

The proposed bridge will start in Guintigui-an village in Babatngon, Leyte, and will end in San Pascual village in Sta. Rita, Samar.

In 2019, traffic volume on the San Juanico Bridge stood at 7,200 vehicles daily, close to its 10,000 daily capacity.

In 2030, it is expected to increase to 10,900 daily, more than its limit, and 15,900 by 2040.

Built in 1973, the existing 2.16-km. San Juanico Bridge faces many issues, such as aging and high maintenance costs. By Sarwell Meniano

 

Article courtesy of the Philippine News Agency

March 28, 2023

Photo credit: Department of Public Works and Highways

President Ferdinand R. Marcos Jr. on Monday, March 27, 2023 led the ceremonial inauguration of the first section of the NLEX-SLEX Connector Road Project from C-3 Road in Caloocan City to España Boulevard, Manila.

Joining the President were Department of Public Works and Highways (DPWH) Secretary Manuel M. Bonoan, Department of Transportation Secretary Jaime Bautista, Metro Pacific Tollways Corporation (MPTC) Chairman Manuel Pangilinan, MNTC President Rodrigo Franco, NLEX Corporation President J. Luigi Bautista, and various local government unit officials.

According to DPWH Secretary Bonoan, the opening of the initial section stretching 5.15 kilometers is expected to decongest traffic along busy Manila roads, most specifically along España Boulevard, Abad Santos Avenue, Rizal Avenue, and Lacson, Avenue.

“The newly-opened section will significantly cut travel time between Caloocan and Manila to just five (5) minutes, and will cater to cars, buses, trucks, and motorcycles with displacement of 400cc and above,” said Secretary Bonoan.

Citing a report from MNTC, Secretary Bonoan added that civil works for NLEX-SLEX Connector’s second and final section is currently at 42 percent. The second section starts from España Boulevard to PUP Sta. Mesa, Manila and is 2.75 kilometers in length.

When completed, the approximately 8-kilometer, 4-lane toll road will serve around 35,000 motorists daily, connecting NLEX and SLEX through C3 Road in Caloocan and Skyway Stage 3 in Sta. Mesa, Manila.

 

Article courtesy of the Department of Public Works and Highways

March 22, 2023

As the Marcos administration becomes bullish in utilizing a public-private partnership (PPP) model in infrastructure projects, the Australian government will be providing its technical expertise in rolling out infrastructure projects under the PPP.

Australian Ambassador to the Philippines Hae Kyong Yu PSM told the Philippine News Agency in an interview at her residence Wednesday that the embassy will be launching the Partnerships for Infrastructure (P4I) on March 24.

“Infrastructure is a big area that the Philippines is focusing on, and I know President (Ferdinand R.) Marcos (Jr.) has announced that he wants to utilize PPP more where it’s possible. So we are working closely with the Philippine government to share with them how Australia has done it,” Yu said.

P4I is an Australian government initiative that brings together experts from the public and private sectors as well as the academe to help Philippine government agencies involved in infrastructure development in the preparation stage of projects that would be under a PPP model.

“We can help them with all the project preparation stage. How you do actual cost-benefit analysis of potential projects, and then how you prepare documents for possible procurement, tender processes, and things like that,” the envoy cited.

She said that aside from the PPP Center, the P4I also aims to closely work with other agencies including the Department of Transportation, the Department of Energy, the Department of Finance, and the National Economic and Development Authority (NEDA), among others.

Yu added that the Australian government will be closely working with the administration through the P4I in meeting its diverse infrastructure requirements, including roads, transport, energy, and public investment management.

The Australian envoy said a number of Australian companies have been involved in infrastructure projects in the country.

Early this month, NEDA Secretary Arsenio Balisacan announced that the NEDA Board approved PHP9 trillion worth of flagship infrastructure projects, with 45 of these projects possibly being funded through PPPs.

“The government shall harness the financial and technical resources of the private sector, which allows the public sector to allocate its funds for greater investment in human capital development, especially to address the scarring in health and education due to the pandemic, and provided targeted assistance that protects vulnerable sectors from economic shocks,” Balisacan had said. By Kris Crismundo

 

Article courtesy of the Philippine News Agency

March 21, 2023

Photo credit: Department of Transportation

Several big-ticket infrastructure projects in the transportation sector have been approved or are already being implemented by the administration of President Ferdinand R. Marcos Jr., the Department of Transportation (DOTr) reported Monday.

In a statement, the DOTr said the Cebu Bus Rapid Transit Project, Davao Public Transport Modernization Project, EDSA Greenways, the Light Rail Transit Line 2 (LRT-2) West Extension, and the Light Rail Transit Line 1 (LRT-1) Cavite Extension are all ongoing as of March 9 according to the National Economic and Development Authority (NEDA).

These projects are among the 67 infrastructure flagship projects (IFP) that have been greenlit or are already underway out of the 194 high-impact projects under Marcos’ "Build Better More" program.

In the rail sector, these approved and ongoing projects include the Metro Manila Subway Phase 1, Mindanao Rail Phase 1, Metro Rail Transit Line 3 (MRT-3) rehabilitation, Metro Rail Transit Line 4 (MRT-4), Metro Rail Transit Line 7 (MRT-7), New Cebu International Container Port, New Manila International Airport (Bulacan International Airport), North-South Commuter Railway (NSCR), Philippine National Railways (PNR) South Long Haul, and the Subic Clark Railway.

The New Dumaguete Airport Development Project (Bacong International Airport) and the Integrated Flood Resilience and Adaptation (InFRA) Phase 1 have also both been approved by NEDA, with six projects awaiting approval.

Last week, the NEDA Board, led by Marcos, approved 194 high-impact priority projects with a total cost of around PHP9 trillion.

The board also approved amendments to the 2013 Joint Venture guidelines to support the government’s push for more investments in the country’s infrastructure.

PNR suspension

Meanwhile, Senate President Pro Tempore Loren Legarda has expressed alarm over an impending suspension of select PNR routes due to the NSCR, saying it will affect thousands of commuters, mostly students and workers.

“The welfare of the riding public should always be prioritized yet it remains to be seen whether such proposed solutions would effectively and sufficiently address the riding public's urgent demands in time for the imminent suspension of the operations of the PNR,“ Legarda said in her explanatory note on Senate Resolution No. 546.

The PNR plans to suspend operations of certain routes for up to five years to facilitate the faster construction of the 55-kilometer NSCR.

The construction will start in May and PNR may suspend the routes between Governor Pascual in Malabon City and Calamba City in Laguna, and well as Alabang, Muntinlupa City to Calamba.

The Tutuban, Manila-Alabang route will be suspended in October and will affect between 20,000 and 25-000 passengers daily.

Legarda urged the Committee on Public Order, chaired by Senator Grace Poe, to look into the impending suspension and come up with alternative solutions.

 

Article courtesy of the Philippine News Agency

March 16, 2023

Photo credit: The Department of Public Works and Highways

Progress of the Panguil Bay Bridge Project, the longest water-spanning bridge in Northern Mindanao, is now more visible at 63 percent complete as the Department of Public Works and Highways (DPWH) has started constructing the bridge top slab on both ends in Tangub, Misamis Occidental and Tubod, Lanao del Norte.

DPWH Senior Undersecretary Emil K. Sadain in his report to Secretary Manuel M. Bonoan said that bored piling works on the seabed for the 32 pylon, a structure that provides support for the 3.17-kilometer bridge across Panguil Bay, are all completed and a lot of machinery for bridge construction are in full gear working forward to the main bridge pylons 1 and 2.

“By working round-the-clock and further improve the formulated measures to catch up the delays brought by previous suspension of activities due to COVID-19 pandemic from March 16 - July 2020, we will be able to finish the project toward the goal of having first traffic cross the bridge by first half of 2024”, said Senior Undersecretary Sadain.

Senior Undersecretary Sadain in his inspection on Thursday, March 9, 2023 has instructed anew the contractor Namkwang Engineering & Construction Corporation in Joint Venture with Kukdong Engineering & Construction Co., Ltd. and Gumgwang Construction Co., Ltd. as well as engineering consultant Yooshin Engineering Corporation in joint venture with Pyunghwa Engineering Consultants Ltd. and Kyong-Ho Engineering & Architects Co., Ltd to complete the work at an accelerated pace.

A flagship infrastructure project, the two-way two-lane Panguil Bay Bridge will connect Tangub, Misamis Occidental and Tubod, Lanao del Norte to just 7 minutes.

Present connectivity between Ozamis City/Tangub City and Tubod through Roll-On, Roll Off (RoRo) vessel is about one (1) and a half hour to two (2) and a half hour including loading and unloading time while land travel over a distance of 100 kilometer is at two (2) to two (2) and a half hour.

Senior Undersecretary Sadain was joined in the project visit by DPWH Unified Project Management Office (UPMO) Roads Management Cluster 2 (Multilateral) Project Director Sharif Madsmo H. Hasim; Project Managers Teresita V. Bauzon, Marlon B. Galerio, and Norman I. Puy; and District Engineer Maria B. David.

Costing ₱7.37 Billion and funded by a loan agreement between Government of the Philippines (GOP) and Korean Export-Import Bank (Korea Eximbank), the project will enhance transportation capacity and efficiency in contributing to Mindanao socio-economic development.

The design and build of Panguil Bay Bridge, being implemented by the DPWH UPMO Operations is included in the DPWH program for integrated and seamless transport system to enhance inter-island connectivity through the construction of short and long-span bridges.

The program also involves the improvement of the logistics infrastructure network in Mindanao and develop a transport system that have significant impact on plan of action to boost tourism, agriculture and industrial sectors by the administration of President Ferdinand R. Marcos Jr.

Other DPWH UPMO Operation’s long-span bridge projects are the 3.9 kilometer Samal Island - Davao Bridge, the 32 kilometer Bataan-Cavite Interlink Bridge, construction of 32 kilometer bridges that will connect Panay, Guimaras and Negros, and 3.3 kilometer Cebu-Mactan 4th Bridge.

 

Article courtesy of The Department of Public Works and Highways

March 16, 2023

Photo credit: DPWH

The construction of the PHP175.7-billion Bataan-Cavite Interlink Bridge Project will start towards the latter part of the year, the Department of Public Works and Highways (DPWH) said Tuesday.

In a Palace press briefing, DPWH Secretary Manuel Bonoan said the 32-kilometer project, which was initially expected to begin construction in the first quarter of 2024, will break ground earlier than expected.

“Detailed engineering [design] is now ongoing—it’s about 70 percent complete and we told the President it will be ready within the year to ground break the implementation of this very significant bridge,” he told reporters following his meeting with President Ferdinand R. Marcos Jr. at Malacañan Palace.

He said the DPWH aims to finish the project before the end of the President’s term.

“We intend to start construction towards the latter part of this year 'siguro' (perhaps). If we are able to procure the civil works then it will take maybe about anywhere between five years…We’ll try to have this completed before the term of the President,” he added.

Bonoan said the project is expected to significantly improve economic development not only in Luzon but the entire country.

“No less than the Asian Development Bank (ADB) has indicated that the economic rate of return of this bridge is more than 25 percent and that’s big,” he said.

The Bataan-Cavite Interlink Bridge Project is a cable-stayed bridge to be built over Manila Bay to reduce the travel time between the provinces of Bataan and Cavite from five hours to 20 to 30 minutes.

Its starting point will be in Barangay Alas-asin in Mariveles town, Bataan, crossing Manila Bay, and ending in Naic town, Cavite.

It is being developed with funding from the ADB.

More projects

Meanwhile, Bonoan also bared that the DPWH is going to implement more than 70,000 major and local projects all over the country with a budget allocation of about PHP890 billion.

He said the agency will also prioritize the construction of more classrooms, farm-to-market roads, roads leading to tourist destinations and production areas, among others.

Bonoan likewise expressed hope that there would be minimal delays to the construction of the projects.

“We cannot discount the fact that the Philippines is vulnerable to calamities. The Philippines is visited by about 20 typhoons a year, so we just hope that it will not significantly affect the implementation period of these projects,” he said.

“Some of these projects will require acquisition of right of way and actually inuunahan na namin yung pag acquire ng right of way so that hindi tayo maantala doon sa pag-iimplement (we prioritized the acquisition of right of way so that there would be no delays in the implementation) when civil works start,” he added.

He is also hopeful the DPWH will get “good contractors” that could speed up the implementation of projects.

From July to December last year, the DPWH implemented, maintained, constructed and improved about 1,500 kms of national roads and local roads all over the country.

The DPWH has also undertaken the construction of 161 bridges along national and local roads as well as 851 flood control projects during the past six months.

In a Facebook post, Marcos welcomed the DPWH report that more roads and bridges are being constructed across the country.

“Ipinagmamalaki nating ibahagi ang magandang simula ng ating pamahalaan sa pagpapabuti ng mga daan at tulay sa iba’t ibang parte ng Pilipinas! Layunin nating siguruhin na konektado at sama-samang umuunlad ang ating mga lalawigan (We are proud to share the good start of our government in improving roads and bridges in different parts of the Philippines! Our goal is to ensure that our provinces are connected and develop together)!” he said.

 

Article courtesy of the Philippine News Agency

March 15, 2023

Photo credit: The Department of Public Works and Highways

The Department of Public Works and Highways (DPWH) announced that preparatory survey of the proposed Dalton Pass East Alternative Road Project is on-going and target for completion by third quarter of 2023.

A kick-off meeting between DPWH Secretary Manuel M. Bonoan with Senior Undersecretary Emil K. Sadain and the Fact Finding Mission of the Japan International Cooperation Agency (JICA) led by JICA Headquarters South East Asia Division Senior Deputy Director Yosuke Nishii and JICA Philippines Senior Representative Kenji Kuronoma was held Monday, March 13, 2023 at the DPWH Head Office in Port Area, Manila.

The purpose of the Fact Finding Mission is to obtain information on the relevance, efficiency, effectiveness and sustainability of the project, which will facilitate JICA's review of the proposed Official Development Assistance (ODA) loan financing and will serve as the basis or preparation for the upcoming Appraisal Mission.

The Japanese government through JICA has provided the Philippines over the years, with assistance in planning, construction, and maintenance of crucial infrastructure.

“On behalf of the Filipino nation, allow me take this opportunity to express our sincerest gratitude for JICA’s unwavering dedication to help the Government of the Philippines achieve robust infrastructure development”, Secretary Bonoan said.

According to Senior Undersecretary Sadain, the Department will closely-coordinate and provide necessary assistance to the JICA team until the preparatory phase is complete.

“This is among the flagship projects of the Department under the administration of President Ferdinand R. Marcos Jr. which will not only address safety and connectivity concerns of the existing Dalton Pass, but will also boost economic activity along its route,” added Senior Undersecretary Sadain.

The Dalton Pass East Alternative Road Project is a proposed 23-kilometer road that will decongest the existing Dalton Pass by providing an alternative road connecting Tayabo, San Jose, Nueva Ecija to Aritao, Nueva Vizcaya and vice versa.

Dalton Pass East Alternative Road Project will address the constant dilemma of frequent closure of the existing Dalton Pass due to natural disasters faced by travellers between Nueva Ecija and Nueva Vizcaya to the Cagayan Valley Region

The proposed project as an alternative road will not only prevent isolation of the provinces of Region 2 but will also improve transport and mobility and ensure support for farmers with the Cagayan Valley Region largely an agricultural economy with vast land dedicated to agriculture production for rice and corn.

During the meeting which was also attended by DPWH Unified Project Management Office Roads Management Cluster I Director Benjamin A. Bautista and other DPWH officials, the JICA Study Team presented the scope of the Preparatory Survey as well as target timeline or project implementation schedule.

Upon completion of the 12-month Preparatory Survey, the 15-month Detailed Design and Procurement will be conducted by the DPWH and its 5-year civil works is targeted to commence by 2025.

 

Article courtesy of The Department of Public Works and Highways

March 06, 2023

Photo credit: The Department of Public Works and Highways

The Department of Public Works and Highways (DPWH) met anew with the Asian Development Bank (ADB) mission to plan and assess the way forward for the realization of Laguna Lakeshore Road Network (LLRN) Project – Phase 1 after the detailed engineering design.

DPWH Secretary Manuel M. Bonoan, Senior Undersecretary and LLRN Team Head Emil K. Sadain, Asian Development Bank (ADB) Country Director Kelly Bird, Asian Infrastructure Investment Bank (AIIB) Transport Sector Leader Andres Pizarro, DPWH Project Director Sharif Madsmo H. Hasim of the Unified Project Management Office (UPMO) Roads Management Cluster 2 (Multilateral), and Project Manager Zenaida B. Mauhay headed the three (3)-day reconnaissance mission workshop held on February 27 to March 1, 2023 to present strategic plans and financial assessment for the 37.4-kilometer road network and viaduct south of Metro Manila.

“With 85.1% of the detailed engineering design (DED) for LLRN already complete, DPWH has started negotiations to gather support from possible financing institutions crucial in the realization of this flagship infrastructure project,” said Secretary Bonoan.

According to Senior Undersecretary Sadain, the construction of LLRN Project Phase 1 to connect the southern province of Laguna to Metro Manila via Laguna Lake along the western coastline will provide a safer, faster alternative, and reliable transportation link.

The proposed third highway going south will ease the traffic congestion especially during rush hour at the Manila South Road and South Luzon Expressway to support economic development and growth potential of the provinces of Laguna, Batangas, Quezon and Rizal in the Southern Tagalog Region, said Senior Undersecretary Sadain.

The Laguna Lakeshore Road Network-Phase 1 involves construction of 21.5-kilometer viaduct and 15.9-kilometer embankment along the west shoreline of Laguna Lake, starting from Barangay Lower Bicutan in Taguig to Calamba City in Laguna.

It will also cover construction of eight (😎 interchanges proposed to connect municipal boundaries to the nearest public road along Lower Bicutan, Sucat, Alabang, Tunasan, San Pedro/Biñan, Santa Rosa, Cabuyao, and Calamba, for a total project cost of P175.3-billion.

The reconnaissance mission was the right venue to layout the groundworks in preparation to the fact-finding mission which is an important milestone in the processing and approval of the proposed financing for LLRN.

Discussions focused on funding schemes and loan application process, construction method, preparation of resettlement plan, gender action plan, and environmental impact assessment towards support economic development of the areas in the vicinity of Laguna de Bay.

With the assistance of the experts from ADB and in collaboration with the consultants, we will be able to analyze possible construction and implementation issues, possible project concerns, and plan way ahead the solutions and mitigation measures, added Senior Undersecretary Sadain.

Meanwhile, Feasibility Study for LLRN Phase 2 in the northern to southern coastline via an eastern route is almost complete and the detailed engineering design will be included in the civil works loan for LLRN Phase 1.

DPWH has already submitted the proposed LLRN Project to National Economic and Development Authority (NEDA) for project approval and endorsement to Department of Finance (DOF) for loan application.

The DPWH is proposing a Multi-Tranche Financing Facility for LLRN Phase 1 civil works in which the budget program for the whole project will be made in three (3) tranches.

 

Article courtesy of The Department of Public Works and Highways

March 01, 2023

Photo credit: The Department of Public Works and Highways

Motorists may soon enjoy seamless access from North Luzon Expressway (NLEX) to España Boulevard in Manila City with the completion of the Section 1 of NLEX-SLEX Connector Road.

Department of Public Works and Highways (DPWH) Secretary Manuel M. Bonoan and Department of Transportation (DOTr) Secretary Jaime J. Bautista, together with NLEX Corporation President and General Manager Jose Luigi L. Bautista and Metro Pacific Tollways Corporation President Rodrigo Franco, inspected on Wednesday, March 1, 2023 the first 5.15-kilometer section of the four (4) lane NLEX-SLEX Connector Road extending from the end of NLEX Segment 10 in C3 Road, Caloocan City to the España Interchange along España Boulevard in Manila City.

“We are targeting to open the España Section before Holy Week to help decongest vehicular traffic in Metro Manila especially to and from the Caloocan, Malabon, Navotas, and Valenzuela (Camanava) area,” said Secretary Bonoan.

When completed, the four (4) lane NLEX-SLEX Connector Road will connect NLEX Segment 10 to the end of Metro Manila Skyway Stage 3 at the Polytechnic University of the Philippines (PUP) in Sta. Mesa, greatly reducing travel time from SLEX-Alabang to NLEX-Balintawak from two (2) hours to just 20 minutes.

The P23.2-billion NLEX-SLEX Connector Road is a joint implementation project by the Philippine Government thru DPWH and Manila North Tollways Corporation (MNTC) under the Public-Private Partnership (PPP) Program.

The project alignment has mostly utilized portions of the Philippine National Railways (PNR) road right-of-way.

“Construction of the second section stretching from España Boulevard to Polytechnic University of the Philippines - Sta Mesa is being fast-track to provide trucks with an alternative route from the ports to the south and improve connectivity between Ninoy Aquino International Airport (NAIA) and Clark International Airport,” added Secretary Bonoan.

Also present during the inspection were DPWH Undersecretary Maria Catalina Cabral, DOTr Undersecretary for Legal Affairs Reinier Paul Yebra, DPWH PPP Service OIC Director Pelita V. Galvez, DPWH Planning Service Director Alex G. Bote, Toll Regulatory Board Executive Director Alvin Carullo, DMCI President and CEO Jorge A. Consunji, and officials and representatives of MPTC and NLEX Corporation.

 

Article courtesy of The Department of Public Works and Highways

March 01, 2023

Photo: NLEX-SLEX Connector Road Project

The Department of Public Works and Highways (DPWH) will receive over PHP495 million for the acquisition of right-of-way for the NLEX-SLEX Connector Road Project (NSCRP), the Department of Budget and Management (DBM) announced Tuesday.

This, after DBM Secretary Amenah Pangandaman approved the Special Allotment Release Order (SARO) amounting to PHP495,129,744 to the DPWH.

“This (SARO) is to cover the payment of right-of-way for properties affected by the NLEX-SLEX Connector Road Project,” the DBM said in a statement.

Pangandaman acknowledged that acquiring ROW is crucial in implementing the NSCRP.

“That’s why securing the payment for all affected properties is very important. And we also thank our kababayan (countrymen) for their solidarity and cooperation. Importante po ‘yun para umusad ang proyekto (That’s important for the project to push through),” she said.

The DBM said the fund would be charged against the program, activity, or project under the DPWH’s 2023 budget approved for release by Pangandaman on Feb. 22.

Pangandaman said the fund release would further boost the Marcos administration’s “Build, Better, More” infrastructure development program.

“As we continue the timely release of funds under the 2023 General Appropriations Act, the DBM also ensures that priority projects and programs of the Marcos Jr. administration will be provided with the needed budget at the soonest possible time,” she said.

“The budget for the right-of-way payments for the NSCRP will definitely boost our Build, Better, More program,” Pangandaman added.

In January, DPWH Secretary Manuel Bonoan said civil works for the NSCRP is 69 percent complete, while the ROW acquisition is 94 percent complete.

The construction of the PHP12.20-billion NSCRP began in May 2019.

Targeted to be completed in December 2023, the NSCRP is approximately an eight-kilometer, four-lane elevated toll expressway extending the NLEX southward from the end of Segment 10 in C3 Road, Caloocan City to PUP Sta. Mesa, Manila and connecting to the Skyway Stage 3, and mostly traversing along the PNR rail track.

Upon completion, the travel time from SLEX to NLEX will be reduced from two hours to just 20 minutes. It is projected to benefit 35,000 motorists per day.

The project seeks to help decongest traffic in Metro Manila, as well as stimulate development in Manila, Caloocan, Malabon, Navotas and other surrounding areas.

 

Article courtesy of the Philippine News Agency

March 01, 2023

Delfin Lorenzana, chairperson of the Bases Conversion and Development Authority delivers his message during the BCDA Fellowship for Central Luzon Media at Hilton Clark Sun Valley Resort in Clark, Pampanga province on Tuesday (Feb. 28, 2023). Lorenzana calls on all sectors to unite for the progress and development of New Clark City as well as nearby areas in Central Luzon. (Photo by Marna Del Rosario)

The Bases Conversion and Development Authority (BCDA) is seeking to harness the potential of the New Clark City into a smart, sustainable and inclusive one that could help in accelerating growth in Central Luzon.

This is anchored on the economic agenda and the Build Better More program of the Marcos administration.

BCDA president and chief executive officer Aileen R. Zosa said on Tuesday the new BCDA leadership fully supports the administration’s eight-point socio-economic agenda as reflected in the Philippine Development Plan 2023-2028 and its mission to propel economic and social transformation in the country in order to provide more jobs and lift more Filipinos from poverty

“New Clark City is BCDA’s answer to reach this goal. Through the development of New Clark City, we not only strive to decongest Metro Manila, but we will also provide a catalyst to spread growth in Central Luzon and other provinces,” Zosa said in a statement.

To realize this goal, the BCDA has lined up several high-impact projects and programs in New Clark City, particularly in the fields of sustainable development, renewable energy, information and communication technology (ICT), estate management, transportation, tourism and smart city technologies, among others.

Once fully developed, New Clark City is projected to become the home of about one million residents, and provide job opportunities to around 600,000 Filipinos.

Zosa cited the importance of building strong partnerships with other government agencies, the private sector, and foreign allies to accelerate the development of New Clark City.

“New Clark City is a massive undertaking that the BCDA cannot do alone. We need the support of our partners in the public and private sectors to implement our programs and projects and ensure that Filipinos will really get the world-class metropolis they deserve,” she said.

Meanwhile, BCDA Chairman Delfin Lorenzana underscored the importance of synergy to attain sustainable development goals.

“Synergy means to unite all the areas here such as Bulacan, Tarlac, Pampanga, Subic and Bataan. Hindi tayo magkakakompetensya (We are not competitors). Let us join forces together to develop these areas. This is the natural expansion of Metro Manila. So, expect more developers to come here not only here in Clark but also in other nearby areas,” Lorenza said in his message during the BCDA Fellowship for Central Luzon Media at Hilton Clark Sun Valley Resort on Tuesday.

As of end-2022, investments committed by private and government locators in New Clark City have reached PHP95.51 billion while actual investments infused have already hit PHP14.59 billion.

 

Article courtesy of the Philippine News Agency