Category:

Estrella Pantaleon Bridge Nears Completion
Finishing works of the Department of Public Works and Highways (DPWH) for the Estrella Pantaleon Bridge Project across Pasig River are in full swing and set to be completed towards the end of July.
Public Works and Highways Secretary Mark Villar said that although the Covid-19 pandemic has impacted construction activity of various flagship infrastructure projects like Estrella Pantaleon Bridge, the DPWH-Unified Project Management Office (UPMO) Team geared up to take up this challenge by keeping focus on the importance of delivering completion and opening this bridge project this early month of the third quarter.
In his report to Secretary Villar, Undersecretary for UPMO Operations Emil K. Sadain said that complete layers of asphalt concrete base, binder and wearing course on the 146 meters main bridge and 66 meters Makati approach bridge are almost done.
Installed successively on main and approach bridge using paving and compaction equipment, the wearing course or the uppermost layer will provide an even profile for the comfort of motorists while providing enough texture to ensure minimum and safe skid resistance, explained Undersecretary Sadain.
Having put up the upper layer, bridge expansion joints are now being installed to allow for continuous traffic between the bridge and the interconnecting abutment structures.
This expansion joints is designed to adjust the bridge length accommodating movement or deformation by external loads, shrinkage, or temperature variations
Among the completed ancillary works for the bridge project with V-shape piers includes protective barriers and railings along both sides of the bridge, storm water drainage structure, and lightings.
Meanwhile, Project Director Benjamin A. Bautista and Project Manager Melchor Kabiling of the UPMO Roads Management Cluster are keeping an eye on the on-going paving works for the 50.5 meters approach road on Estrella Street, Makati City and 243.96 meters approach road at Barangka Drive connected to Pantaleon Street in Mandaluyong City which are being accelerated by successively placing complete layer packages.
The layers of approach road are consists of base course or the foundation made of different aggregate rocks to support the top layers of the pavement; cement-treated base or mixture of aggregates with amounts of portland cement that hardens after compaction and curing to form a strong, durable, frost-resistant paving material; asphalt concrete base or asphalt treated base that acts as waterproof barrier to prevent fines infiltration into the subgrade and pavement structure; finally the binder and wearing course.
The P1.46-billion bridge project will have four lanes and will be a 506.46-meter pre-stressed concrete rigid frame bridge with corrugated steel webs, replacing the temporary two-lane box truss bridge made of modular steel components dismantled in 2019.
The bridge project is one of two grant bridges from China — the other one is Binondo-Intramuros Bridge.

Central Luzon Link Expressway to Open this Week
The Central Luzon Link Expressway (CLLEX) will be opened to the motoring public this week.
This was announced by DPWH Secretary Mark Villar in today, July 14, 2021 final inspection of the four (4)-lane expressway project connecting Tarlac and Nueva Ecija.
“As declared a month ago, we will inaugurate on Thursday, July 15, 2021, the first 18-kilometer section of CLLEX from Subic-Clark-Tarlac Expressway (SCTEX)/Tarlac-Pangasinan-La Union Expressway (TPLEX) connection in Tarlac City up to the intersection of Aliaga-Guimba Road in Aliaga, Nueva Ecija”, said Secretary Villar.
Secretary Villar was joined in the conduct of final safety checking before this new road network is opened to vehicular traffic by Undersecretary for Unified Project Management Office (UPMO) Operations Emil K. Sadain, and Project Director Benjamin A. Bautista.
This toll-free expressway project implemented by DPWH UPMO-Roads Management Cluster 1 is one of the key infrastructure projects with funding assistance from the Japan International Cooperation Agency (JICA) under the Build, Build, Build program.
The partial opening of CLLEX up to Aliaga is expected to provide options to motorists and spread out traffic better.
According to Undersecretary Sadain, the CLLEX sections covered by three (3) contract packages that will be opened are the 4.10 kilometer Tarlac Section, 6.40 kilometer Rio Chico River Bridge Section including 1.5 km Rio Chico Viaduct, and the Aliaga Section with up and down ramps at Guimba-Aliaga Road.
DPWH is committed to complete the entire 30-kilometer expressway project within the term of President Rodrigo Roa Duterte with the 10.3 kilometer Cabanatuan Section under Contract Package 4 already at 88.7 percent while the Zaragoza Interchange Section under Contract Package 5 is at 26.9 percent and expected to gain significant progress as site possessions are secured for the project’s right of way (ROW) requirements.
Once fully operational, the ₱11.811-Billion expressway is expected to shorten the usual travel time of 70 minutes between Tarlac City and Cabanatuan City to just 20 minutes.
This new expressway will also form an important east-west link for the expressway network of Central Luzon to ensure a continuous seamless traffic flow for the motoring public from Metro Manila and vice versa passing thru North Luzon Expressway (NLEX), Subic-Clark-Tarlac Expressway (SCTEX), Tarlac-Pangasinan-La Union Expressway (TPLEX).

Work on BGC-Ortigas Link Road Enters Homestretch Phase
Photo Credit: Department of Public Works and Highways
The Department of Public Works and Highways (DPWH), which has reached a major milestone with the Independence Day opening of 440-meter Kalayaan Bridge connecting Pasig City with Makati City, enters the final stages of fully completing the Bonifacio Global City (BGC)-Ortigas Center Link Road Project.
DPWH Secretary Mark Villar, on the day the new Sta. Monica-Lawton Bridge now dubbed
Kalayaan Bridge across Pasig River was opened to motorists during the 123rd celebration of Philippine Independence, declared that the next goal is to finish the entire BGC-Ortigas Center Link Road Project towards the last quarter of 2021.
Secretary Villar said that once this BGC-Ortigas Center Link Road Project is fully complete and open, about 20 percent of the traffic volume of EDSA and C-5 Road can be accomodated.
The Kalayaan Bridge, the viaduct structure and coupled with our road widening and rehabilitation works will create much better traffic flow to get through BGC and Ortigas business districts quicker, added Secretary Villar.
In his report to Secretary Villar, Undersecretary for Unified Project Management Office (UPMO) Operations Emil K. Sadain said that the construction of 565-meter Lawton Avenue – Global City Viaduct which is another component of the 1.367 kilometer BGC-Ortigas Center Link Road Project has already reached the Kalayaan Avenue intersection.
Simultaneous to the final finishing activities for the Kalayaan Bridge and the up and down ramps to Kalayaan Avenue, construction of the viaduct structure from Lawton Avenue, Makati City moved quickly and will soon be connected to the entrance of Bonifacio Global City’s 8th Avenue, added Undersecretary Sadain.
Assessment of the (4) lane viaduct construction project was conducted by Undersecretary Sadain together with UPMO Roads Management Cluster 1 Project Directors Virgilio C. Castillo and Benjamin A. Bautista, Project Manager Ricarte S. Mañalac, Project Engineer Emmanuel Regodon, and Engr. Reynaldo Perez of Persan Construction Inc.
Now that the viaduct is about to reach the BGC side, the DPWH UPMO team is continuously coordinating with partner stakeholders so that the work that needs to be done is as efficient as possible to finish the viaduct overpass, connect with the roadway and get it open by this last quarter.
Article courtesy of the Department of Public Works and Highways

DPWH Prepares for Independence Day Opening of Sta Monica-Lawton Bridge
The Department of Public Works and Highways (DPWH) will soon open a new road network passing business and industrial hubs of Pasig City, Makati City and Taguig City in a bid to ease decades-old EDSA travel woes.
Secretary Mark Villar said that access ramps of the Sta. Monica-Lawton Bridge, a major component of the Bonifacio Global City - Ortigas Center Road Link Project, are already completed.
With the completion of both up-ramp and down-ramp near Kalayaan Avenue, we will be able to achieved the target partial opening by June 12 of the four-lane two-way Sta. Monica-Lawton Bridge, added Secretary Villar.
Secretary Villar together with Undersecretary for Unified Project Management Office (UPMO) Operations Emil K. Sadain inspected on Thursday, May 6, 2021 the BGC - Ortigas Center Road Link Project which will soon be an alternate corridor from EDSA and C-5 along the section of Guadalupe Bridge and Bagong Ilog Bridge, allowing more economic opportunities.
In his report to Secretary Villar, Undersecretary Sadain said that once the punch listing activities are done, the asphalt overlay of bridge deck surface, the up and down ramps, and abutment 1 will commence by last week of May 2021 in time for the Independence Day partial opening of this high-impact infrastructure project which is part of EDSA Decongestion Master Plan.
The asphalt concrete overlays will protect the bridge and road pavement from water permeation, flexural fatigue, rutting and shoving, added Undersecretary Sadain.
Implemented by UPMO Roads Management Cluster 1 (Bilateral) headed by OIC-Project Director Benjamin Bautista and supervised by Project Manager Ricarte Mañalac, the BGC - Ortigas Center Road Link Project is targetted for full completion by September.
The cantilever box girder bridge is already fully completed with sidewalk, parapet, double arms street light and drainage pipe, with some actitivities for the median barrier.
Improvement thru widening of the connecting roads from the start of the project to Pier 5 at Pasig City side particularly the 228 meters Brixton Street and 248 meters Fairlane Street were also undertaken while finishing touches is on-going at the 159 meters abutment 1 particularly on its drainage and manholes, median, sidewalk and parapet.
Meanwhile, all the 76 pieces of pre-stressed concrete girder for the Lawton to Kalayaan or Section 3 viaduct from Pier 9 to 18 are completed and with deck slab laid with steel for portland cement concrete pouring.
Launching of three out of four bored piles for Section 4 - Pier 19 to end of project along 8th Avenue of BGC were completed with continuous fabrication and installation of reinforcements of pre-stressed girder.












