August 26, 2024

As the Panguil Bay Bridge Project approaches its completion, Department of Public Works and Highways (DPWH) Senior Undersecretary Emil K. Sadain, along with key officials from the Unified Project Management Office (UPMO) Operations, conducted an on-site inspection on August 23, 2024, to ensure Mindanao’s longest bridge completion is on track for the target September inauguration.

The 3.17-kilometer bridge, which will connect Tangub City in Misamis Occidental and Tubod in Lanao del Norte, is a landmark infrastructure project set to significantly reduce travel time between these two (2) provinces in Northern Mindanao.

The current two-and-a-half-hour journey, which relies on roll-on/roll-off vessels, will be cut down to just seven (7) minutes by land once the bridge is operational.

In his report to Secretary Manuel M. Bonoan, Senior Undersecretary Sadain said that the detailed engineering design and civil works is more than 97.5 percent completed to date.

Panguil Bay Bridge project includes the following major components: a 360-meter approach road leading to a 1,020-meter approach bridge at Tangub City side; a 569-meter approach road connects to a 900-meter approach bridge on the Tubod side; and a Main Bridge with central span that stretches 320 meters, supported by two (2) pylons, each anchored by six (6) cable stays. Additionally, two (2) observatory bays are positioned on both the Tangub and Tubod sides of the pylons for facilitating regular maintenance and ensuring the structural integrity of the bridge.

During the inspection, Senior Undersecretary Sadain, along with UPMO Project Directors Teresita V. Bauzon, Soledad R. Florencio, Ramon A. Arriola III, Benjamin A. Bautista and Rodrigo I. Delos Reyes conducted a detailed assessment of key bridge elements, including the deck slab, approach roads, barrier and median strip concrete, metal guardrail, and ancillary structures.

Also present at the inspection are past UPMO Project Directors namely Sharif Madsmo H. Hasim and Virgilio C. Castillo, Stakeholders Relations Service Director Randy R. Del Rosario; Project Managers Shirley O. Castro, Evangeline L. Carabal, and Norman I. Puy; and Engineers Abdul Khalid C. Lumangcolob, Oliver Hernandez and Ken John B. Barcelona.

The team closely monitored the progress of crucial finishing activities, with a focus on the application of waterproofing and asphalt paving, expansion joint works, the implementation of aesthetic and electrical lighting systems, line markings and the installation of road signage.

In addition to reviewing the physical aspects of the project, the team engaged with the design and build contractor Namkwang Engineering & Construction Corporation along with the project consultant Yooshin Engineering Corporation to discuss the final phases of activities for the upcoming inauguration of the project and any necessary last-minute adjustments to ensure the bridge’s timely completion.

The Panguil Bay Bridge is anticipated to be a transformative project for local transportation and economic activities, said Senior Undersecretary Sadain during the inspection.

Upon completion, it is expected to spur development and improve the quality of life for residents in both provinces.

With the inauguration set for September, the DPWH is working tirelessly to ensure that the project is ready for public use.

The opening of the bridge will mark a significant milestone in the government’s Build Better More infrastructure program, aimed at enhancing connectivity and driving economic growth under Bagong Pilipinas.

The project implemented by DPWH UPMO Roads Management Cluster II (Multilateral), with a total cost of ₱7.375 billion, is financed through a loan agreement between the Government of the Philippines and the Republic of Korea, facilitated by the Korea Export-Import Bank under the Economic Development Cooperation Fund (EDCF) Loan Agreement No. PHL-18.

August 19, 2024

The Department of Public Works and Highways (DPWH) is intensifying its efforts to advance the “Build Better More” agenda of President Ferdinand R. Marcos Jr. administration to accelerate infrastructure development, with continued support from the Asian Development Bank (ADB).

During a consultation meeting held on August 15, 2024, at ADB Headquarters in Mandaluyong City, DPWH Senior Undersecretary Emil K. Sadain and ADB Country Director Pavit Ramachandran led discussions focused on key infrastructure projects designed to drive the Philippines economic growth and development.

The primary agenda of the meeting was to fast-track the implementation of priority infrastructure projects, ensuring alignment with the country’s long-term economic objectives. Key topics included funding strategies, project timelines, and addressing potential challenges through coordinated efforts.

Senior Undersecretary Sadain acknowledged ADB’s steadfast support, emphasizing its crucial role in advancing Philippine infrastructure development.

“On behalf of DPWH Secretary Manuel M. Bonoan, we are deeply grateful for ADB’s consistent support, which is instrumental in delivering critical projects, particularly in highly prioritized regions across Luzon, Visayas, and Mindanao. Their assistance ensures that these infrastructures meet the highest standards of quality, safety, and efficiency,” said Senior Undersecretary Sadain.

Among the discussed projects is the multi-tranche financing facility for the Laguna Lakeshore Road Network (LLRN) Project Phase 1. This project will create a new expressway connecting Laguna Province to Metro Manila via Laguna Lake.

The LLRN Phase I covers a 37.5-kilometer mainline, featuring seven interchanges located in Lower Bicutan (Taguig), Sucat, Alabang, and Tunasan (Muntinlupa City), as well as San Pedro/Biñan, Cabuyao, and Calamba (Laguna Province).

The meeting also covered other significant projects supported by the ADB Infrastructure Preparation and Innovation Facility (IPIF) including the Bataan-Cavite Interlink Bridge (BCIB) Project.

The construction of the BCIB project is structured into seven (7) contract packages, with procurement currently underway for the first tranche, focusing on the on-land components under packages 1 and 2. Tranche 1 includes the 5-kilometer Bataan Land Approach under package 1, the 1.35-kilometer Cavite Land Approach under package 2, and component of other remaining five (5) packages to be procured starting this fourth quarter.

Meanwhile, Tranche 2 in the 2026 budget program and other subsequent tranches will cover the 20.65-kilometer Marine Viaducts in the North and South under packages 3 and 4; the 2.15-kilometer North Channel Bridge under package 5, and the 3.15-kilometer South Channel Bridge under package 6. The 7th package encompasses project-wide ancillary works, with a separate package 8 planned for Operations and Maintenance.

Other projects include the Integrated Flood Resilience and Adaptation Project, Phase 2 (InFRA2) for feasibility study (FS) and detailed engineering design (DED) including technical assistance on land acquisition between 2024 to 2026 to be followed with civil works implementation; and Central Mindanao High-Standard Highway Construction Project for DED and construction in 2027.

Also tackled are the 62 kilometer Central Luzon-Pampanga River Flood Control with DED to start in 2025 and construction in 2027; Urgent Bridges Construction Project for Rural Development for FS in 2025, DED in 2026 towards 2028 construction; and the 300 kilometer Samar and Agusan Daang Maharlika Road Improvement Project for 2026 to 2028 FS and DED with right of way to civil works implementation by 2028 and beyond.

The Central Luzon-Pampanga River Flood Control Project is a crucial initiative designed to provide lasting protection against severe flooding in the region. Engineered to handle a 100-year flood event, this project will deliver significant benefits to the provinces of Pampanga, Bulacan, and Nueva Ecija.

The flood control system will span from the foothills of Mount Arayat, directing floodwaters from the Upper Pampanga River catchment area straight into Manila Bay.

By efficiently managing these floodwaters, the project aims to safeguard communities, protect agricultural lands, and preserve essential infrastructure, offering a robust and sustainable defense against future floods.

Senior Undersecretary Sadain stressed the importance of these projects in realizing “Bagong Pilipinas” vision. He noted that successful completion relies on close collaboration with key agencies like the National Economic and Development Authority (NEDA), the Department of Finance (DOF), and ADB.

DPWH officials present at the meeting included Project Directors Teresita V. Bauzon, Ramon A. Arriola III, Benjamin A. Bautista, and Rodrigo I. Delos Reyes. The NEDA delegation was led by OIC Director Joseph Norley Y. Capistrano, with OIC Assistant Director Calixto M. Mangilin, Jr. The DOF was represented by Atty. Ryan Omar Ching, Ms. Jenevive Lontok, Ms. Joanna Marie Torres, and Ms. Cindy Nuguit.

ADB Country Director Ramachandran reaffirmed ADB’s commitment to supporting the Philippines’ infrastructure goals, emphasizing the importance of sustainable and resilient development.

NEDA and DOF officials echoed this sentiment, underscoring the necessity for timely project execution and proper resource allocation.

The meeting concluded with a collective commitment to continue working closely to ensure that these critical infrastructure projects are completed on time, contributing to the nation’s economic recovery and growth.

August 13, 2024

The Department of Public Works and Highways (DPWH) is preparing to implement the PHP1.5 billion third phase of the Daniel Z. Romualdez Airport's passenger terminal building construction here.

The third phase covers the provision of public toilets, ticketing booths, waiting areas and waiting sheds.

Other components are rescue and firefighting facilities, guardhouses, motor pool and maintenance buildings, pump rooms, fuel stations, and material recovery facilities.

The DPWH will bid out the project within the month and start construction later this year or early next year.

DPWH Eastern Visayas Director Edgar Tabacon said they are finalizing the detailed engineering design while waiting for the completion of the first and second phases.

“Building an airport terminal building is not our regular activity. This is challenging and that is why we asked for assistance from the Department of Transportation and contractors for the first two phases,” Tabacon said in an interview on Friday.

The construction of the terminal building is already 79 percent complete as of May, the supposed target completion month.

The ongoing works for the PHP761-million project focus on the main bridge, electrical and mechanical aspects, fire protection, and masonry.

The Regional Development Council said that although the project experienced delays, the Civil Aviation Authority of the Philippine project management office closely monitors the catch-up plan of the contractor.

The second phase of the new passenger terminal building, with a PHP1.05 billion budget, started on Jan. 26 and is up for completion early 2026. Ongoing works include roofing and architectural works.

The airport was the seventh busiest in 2022 with 1,489,803 inbound and outbound passengers.

August 13, 2024

President Ferdinand R. Marcos Jr. on Friday vowed that his administration would continue pursuing job-generating initiatives that could help in further transforming the Philippine economy.

Marcos made the pledge, as he attributed the 6.3-percent economic growth in the second quarter of 2024 to the increase in investments and construction under the Build Better More program.

“Inuulit ko, balewala lahat ng ating ginagawa kung walang pagbabago sa buhay ng mga Pilipino (I repeat, everything we do is meaningless if there are no changes in the lives of Filipinos),” he said in a video message uploaded on the Presidential Communications Office’s official Facebook page.

“So I assure you, this government will continue to invest in job-generating infrastructure, social protection programs, health and education for all Filipinos. We will not rest on our laurels but use them to propel us forward into social and economic transformation,” he added.

The country’s economic growth accelerated to 6.3 percent in the second quarter of 2024, higher than the 4.3 percent during the same period last year and the 5.8 percent in the first quarter of this year.

He said the government is doing everything to give Filipinos “decent and formal” jobs to elevate them to middle class.

“Kaya patuloy ang ating pagbibigay ng sapat at kalidad na trabaho (That’s why we continue to provide adequate and quality jobs). This June, the unemployment rate dropped to 3.1 percent, one of the lowest on record for the last two decades. Over 50.3 million Filipinos are now employed, with 63.8 percent of them in the formal sector,” Marcos said.

Marcos assured Filipinos of his administration’s commitment to combat poverty, saying the goal is already “within its reach” as the latest poverty rate also dropped to 15.5 percent.

“[That] means we have lifted two and a half million Filipinos out of poverty and only 10.9 percent of Filipino families remain poor. Our goal is to further reduce this rate to 9 percent by 2028, and improve the lives of eight million Filipinos,” Marcos said.

August 05, 2024

Part 1

A group of an all-Filipino Mining Engineers worked under the auspices of Paramina Earth Technologies, Inc. (PARAMINA) for a civil construction tunnel project.  These Mining Engineers developed and excavated an 8m wide x 7m high x 1,011m long tunnel safely, without a single lost time accident (LTA) accident and or rockfall incident as a Subcontractor and without the help of a Civil Engineer.  The project applied the NATM following international tunnel design, plans and standards. Completion of the tunnel project was remarkably ahead of the adjusted timeline including the remediation works.

The project is the Upper Wawa Pumping Station Water Access Tunnel owned by WawaJVCo, a joint venture company of Prime Infrastructure Capital, Inc. an Enrique Razon corporation and the San Lorenzo Builders and Developers Group, the grantee of the water rights of the project.  The joint venture company is developing the Wawa Bulk Water Supply Project, “an infrastructure project of the Philippine Government and will address the growing concern of water scarcity and is expected to minimize the risk of flooding in the capital region and in the nearby province of Rizal.  It will be the biggest water source built since 1967 and will supply at least 518 million liters per day through Manila Water Company. CTTO ”  The main beneficiary of the bulk water supply project will be the eastern communities of Metro Manila and Rizal.

The water access tunnel project is part of the second of two water supply infrastructures of WawaJVCo.  The tunnel designed by Lombardi SA was constructed to ensure that it will last for a minimum period of 100-years, therefore, the group of all-Filipino Mining Engineers who built the tunnel had to pass through very stringent QA/QC requirements which had to be followed and implemented to the minute detail.

The all-Filipino Mining Engineers who developed and excavated the tunnel were Mining Engineers who used to occupy and manage senior positions in various mining and tunneling projects in the Philippines and overseas; supported by a group of experienced junior Mining Engineers who supervised the shift operations.  At least fifty Filipino multi-skilled tunnel equipment operators were at the forefront of the tunnel excavation operations. 

Another group of at least forty Mechanical and Electrical Engineers and technicians formed the equipment maintenance and support group.

Two twin boom and one single boom electro-hydraulic jumbo drill rigs were the main drilling equipment.  Two side dump loaders, three 20-tonne underground trucks and three dump trucks were used for mucking, loading and hauling. Blasting was designed using a computerized shot-plan and varied according to the rock and ground condition. Two robotic shotcrete machines and two high-and-low-pressure grouting machines were used for mechanized shotcreting and grouting respectively.

The tunnel support design was the greatest challenge of the project because there was limited geotechnical information provided.  Every advance or blast was closely monitored as the crown and side supports and the blasthole drilling depths depended on the rock structure which was defined by the RMR of the active face.

Water is life. The Filipino Mining Engineers who built the tunnel are proud to be part of the commitment of WawaJVCo, the owners of the project to provide a new source of potable water, sustainable in the next 100 years.

Purpose and Magnitude of the Project

The “Upper Wawa Pumping Station,” is one crucial component of a Mega-Infrastructure Project better known as the “Wawa Bulk Water Supply Project,” is considered the largest potable water source to be constructed in the country since 1967. It comprises of four (4) major integral components or sub-projects of the Mega Infrastructure, namely, the Upper Wawa Dam and Spillway, Reservoir, Pumping Station and Transmission or Water Conveyance Pipeline. The Water Access Tunnel forms part of the Transmission or Water Conveyance Pipeline component of the Mega-Project.

The primary objective of the Wawa Bulk Water Supply Project is to address the perennial water scarcity issue in Metro Manila. This challenge has been exacerbated by population growth driven by migration, rapid urbanization, and economic opportunities. Once completed, this ambitious undertaking will establish a reliable source of potable water supply for Eastern Metro Manila, specifically serving the so-called East Zone Concession managed by Manila Water Co.

The Upper Wawa Pumping Station plays a pivotal role in achieving this goal. It is designed to supply a minimum of 518 million liters of water daily (MLD), with an additional standby capacity of 259 MLD, resulting in a total pumping capacity of 777 MLD. The Tayabasan River, situated in Barangay Calawis, Sitio Apia, Antipolo, within the Upper Marikina Watershed, serves as the primary raw water source. This river is further supported by several smaller tributaries spread across the Marikina watershed. Through this comprehensive project, the region will gain access to a sustainable and essential water supply, quenching the thirst of East Metro Manila’s residents in the next 100-years.

Scope of Tunnel Project and Technical Description

The scope of work for the Main Access Tunnel, a critical component of the Water Conveyance Pipeline within the larger mega-project, mandates that the tunnel Subcontractor undertake the excavation work by drilling and blasting, as well as the transportation and disposal of the muck through  synchronized activities utilizing specialized equipment such as Furukawa, hydraulic twin boom jumbo drill rigs with man basket, Dali, 20-tonne low profile trucks, SDLG, side dump, 3cu.m. loaders and XCMG, robotic shotcrete machine among the capital equipment used in the project.

As the excavation advanced, the project required the installation of galvanized self-drilling anchor and all threaded rock bolts which were grouted to stabilize the newly exposed tunnel surfaces so that drilling and blasting can immediately commence after the newly excavated ground was fully shotcreted. A vast part of the process entailed the application of 50mm shotcrete immediately after scaling using a Komatsu excavator equipped with a hydraulic breaker, then 100mm thick shotcrete applied thereafter and before the start of drilling. The shotcrete mix is a special concrete mixed with additives and synthetic and or steel fibers and applied using the XCMG mechanized robotic shotcrete machine.

To ensure that ground water is drained and will not accumulate at the crown and sides of the tunnel, drilling of drainage and or weep holes using the MTI Single boom hydraulic jumbo drill was essential. Each weep hole is inserted with perforated drainpipes wrapped with non-woven geotextile.

Additionally, it was also necessary to execute variation works on an as-needed basis. The provision of essential support services is also part of the Bill of Quantities (BOQ), including the supply of adequate ventilation, water, power, and compressed air.

Temporary field offices, equipment maintenance workshop and personnel accommodations, ensuring a comprehensive and supportive environment for the project’s successful completion was also constructed.

Technical Requirements

The tunnel which was required to be driven was 8m wide and 7m high, extending over a total length of 1,011 meters. The specific dimensions for excavation and reinforcement are determined based on the rock mass rating (RMR) for each tunnel segment, as assessed and evaluated by Geologists and Geotechnical Engineers. Depending on the RMR of the tunnel’s face which is evaluated every after blasting, the tunnel designer and the Geotechnical and Geological Engineers considered six distinct support types. The support type spectrum ranged from Support Type P (for Portal), Support Type 5, down to Support Type 1, each tailored to reinforce the crown and sides of the tunnel as the excavation progresses, resisting the impact of drilling and blasting and to maintain the structural integrity of the tunnel to be able to last for 100years.

Support Type P is required to support the tunnel Portal which had Rock Mass Rating (RMR) between 0 and 20 and was intended for the excavation of the East and West portals of the Main Access Tunnel.  The dimensions of Support Type P are 8.38meters wide by 6.74meters high allowing for the installation of Steel Rib Supports (SRS). This support system integrates the installation of Steel Rib Support (SRS) made from 200mm x 200mm H-beams using a specially designed “hook” attached to an excavator; a protective “umbrella” of grouted galvanized Self Drilling Anchor (SDA) rock bolts; a Shotcrete lining, 400mm thick enough to cover the whole SRS. Additionally, the structure is equipped with weep holes, into which eight 50mm diameter perforated drainage pipes wrapped in non-woven geotextiles are installed.  As it was difficult to apply shotcrete at the back of the SRS, the sides of the SRS were drilled with holes in regular distances and were in-fill grouted using high-pressure automatic cement grout machines.

Conversely, Support Type 1 was designed for tunnel sections 7.78m wide by 6.44m high, intended for RMR ranging from 81-100. The support in these areas consists of sporadically placed grouted Dywidag split-set type rock bolts, 46mm diameter and 4 meters long, along with 8-pieces of 50mm diameter perforated drainpipes wrapped with non-woven geotextile. Due to the inherently stable nature of the rock mass, no shotcrete lining is applied in these sections.

Support Type 2 was designed for RMR 61-80 with tunnel dimensions 7.88m wide x 6.49m high. The support consists of 11pcs fully grouted Dywidag hollow all-threaded galvanized rock bolts, 25mm diameter x 4 meters long. Shotcrete thickness was 150mm including the initial 50mm after scaling, after which 50mm drainage holes were drilled and inserted with 50mm diameter perforated drainpipes wrapped in non-woven geotextiles.

Support Type 3 had similar excavation dimension as Support Type 2 but is designed for RMR equivalent to 41-60. The main difference is that the number of rock bolts is 15pcs fully grouted Dywidag hollow all-threaded galvanized rock bolts, 25mm diameter x 4 meters long. The number of drainpipes is the same as Support Type 2, but the shotcrete thickness is 300mm.

Support Type 4 required an excavation dimension of 8.28m wide by 6.69m high, designed for RMR equivalent to 21-40. This category when encountered was supported by a combination of the installation of 200mm x 200mm SRS, grouted galvanized SDA rock bolts, R38 x 4 meters long complete with plates and nuts, 350mm thick shotcrete covering the entire SRS and installed with 50mm diameter x 2m long perforated drainpipes wrapped in non-woven geotextile.

Finally Support Type 5 required an excavation dimension of 8.38 m wide x 6.74 m high for RMR ranging from 0-20. This support type consisted of a combination of the installation of 200mm x 200mm SRS, SDA galvanized rock bolts, R38 x 4m, 400mm thick shotcrete enough to cover the SRS and 8-pieces x 50mm perforated drainpipes wrapped with non-woven geotextile.

The various designs of Support Types ensure the stability and integrity of the tunnel, adapting to the varying rock conditions which were encountered during the actual excavation and were designed for the tunnel to last for 100years.

 

<to be continued> In Part 2 of this article, we will discuss the challenges encountered, the innovations and the milestones achieved.

July 29, 2024

The Department of Public Works and Highways (DPWH) is making significant headway in the Province of Tawi-Tawi, part of the Bangsamoro Autonomous Region in Muslim Mindanao (BARMM), with the construction of key bridges which are visibly progressing aimed at improving regional connectivity and boosting economic growth.

DPWH Senior Undersecretary Emil K. Sadain, in his inspection report to Secretary Manuel M. Bonoan, highlighted the ongoing progress of the Nalil-Sikkiat Bridge No. 1 and Malassa Lupa Pula Bridge No. 3.

These bridges, located in the southwestern tip of the Sulu archipelago, are steadily transforming from their foundations to functional structures that will soon link various islands in the province.

On July 26, 2024, Senior Undersecretary Sadain, along with Project Director Teresita V. Bauzon and Project Managers Emmanuel M. Supe and Evangeline L. Carabal of the DPWH Unified Project Management Office - Roads Management Cluster II (Multilateral), inspected these projects.

Funded by the Asian Development Bank (ADB) under the Improving Growth Corridors in Mindanao Road Sector Project (IGCMRSP), these bridges demonstrate the DPWH commitment to advancing infrastructure projects that not only connect communities but also foster economic growth and development across the Philippines.

The bridges are set to ease congestion on Bongao Island, Tawi-Tawi’s capital, by enhancing connectivity among the province’s islands and municipalities.

These government-initiated projects support BARMM’s economic development and leverage Tawi-Tawi’s strategic location within the Brunei, Indonesia, Malaysia, Philippines-East ASEAN Growth Area (BIMP-EAGA).

“By enhancing local and regional market connectivity, these bridges are expected to attract more investors, stimulate economic activities, and improve the quality of life for the people of Tawi-Tawi,” said Senior Undersecretary Sadain.

The 541-meter Nalil-Sikkiat Bridge No. 1, which spans the Bongao Channel, will connect Bongao Island to Sanga-Sanga Island is set for completion by July 2025.

Awarded to China Wuyi Co., Ltd. with a contract amount of ₱893 million, the project is 64 percent complete, with significant milestones such as the completion of pile caps, backwalls, wingwalls for abutment B, and other key structures.

DPWH UPMO Project Manager Ernante S. Antonio explained that ongoing work includes rebar installation, approach railing and sidewalk construction at abutment B, drilling for pier 9, and pile cap installation at pier 6.

Meanwhile, the on-going 681-meter Malassa Lupa Pula Bridge No. 3 across the Manalik Channel, will link Sanga-Sanga to mainland Tawi-Tawi.

This project, contracted to a consortium of V.T. Lao Construction and China Wuyi Co., Ltd. for ₱1.25 billion, is 32.9 percent complete and expected to be finished by September 2025.

Key accomplishments include the completion of over half of the 99 bored piles and the construction of foundations and initial structures from the channel.

Additionally, the 569-meter Tongsinah–Paniongan Bridge, connecting Pababag Island to Sanga-Sanga Island, has begun civil works after receiving a notice to proceed on July 16, 2024, to the China Wuyi Co., Ltd./ Vicente T. Lao joint venture.

This bridge will provide a direct route between Bongao, a major growth center, and future growth centers in Panglima Sugala and Pababag Island.

Development plans for Pababag Island include a large-scale seaweed processing plant and housing projects, significantly boosting the local economy.

July 24, 2024

President Ferdinand Marcos Jr. received resounding rounds of applause several times during his third State of the Nation Address 2024 (SONA), particularly on the final part of his speech when he announced the ban on Philippine Offshore Gaming Operators (POGO).

The SONA 2024 was held on Monday, July 22, 2024, at the Batasang Pambansa Complex in Quezon City.

Among other things, his State of the Nation Address covered various significant national issues from education, agriculture, defense, cybersecurity, tourism, and more.  

“As we enter the mid-term, our infrastructure development remains sustained, strategic, and on schedule,” the President said.

“Aside from agriculture and disaster risk, our other vital sectors and pillars — such as education, health, energy, low-cost housing, transport, information technology — they all stand to benefit from our aggressive infrastructure development, as befitting our upper middle-income economic target.”

He mentioned that despite the challenges during the past two years into this Administration, there has been a steady progress towards the targets in the medium-term.

“Our power and internet services are continuously being upgraded in both capacity and connectivity.”

Unified Philippine Grid

The President mentioned that the energy sector looks bright and promising with completion of projects and new investments. With that, he expected that the nation’s power supply will increase steadily to meet the growing demands in the future.

He also mentioned that government is urgently addressing power shortages and the systemic causes of blackouts in unserved and underserved areas.

Through microgrids, off-grid systems, and missionary small power utilities that supports solar power, the President said these will provide solutions to places that need a steady supply of electricity.

“Running through Bataan, Pampanga, and Bulacan, the newly inaugurated Mariveles-Hermosa-San Jose transmission line will further strengthen the reliability of the Luzon power grid.”

He announced that in the Visayas, all stages of the Cebu-Negros-Panay backbone project have been completed.

“This project shall serve to stabilize the power situation in Western and Central Visayas, and avert recurrences of power outages experienced in the past,” he noted.

He said that because of these projects, blackouts at Panay Island were prevented from April until June despite the yellow and red alerts in the region.

The President noted that the Dumanjug-Corella Line of the Cebu-Bohol Interconnection Project was energized, enabling the transfer of power between Cebu and Bohol.

“With these systems currently operating at capacity, these major power lines shall contribute to the efficient power exchanges not only between Luzon and the Visayas, but also involving Mindanao. Energy sharing and transfers between, among, and within the three island groups have now been made possible with the energization last January of the Mindanao-Visayas Interconnection.”

“The energization of the Mindanao-Visayas Interconnection is a defining moment not only for the power sector but for the entire country. Finally, we have connected the power grids of all three major island groups.”

“The ‘unified Philippine Grid’ is a fulfillment of the dream, whose seeds were planted in the 80s, through a vision bolstered by R&D, which we accomplished by applying typical Filipino persistence and dedication,” he stated.

Addressing the high cost of electricity, President Marcos Jr. gave assurance that government will continue to add power infrastructure that will contribute to the lowering the electricity rates and providing fair charges to consumers.

Roads and Railway Renaissance

President Marcos Jr. reported that as of May of this year, 12,000 kilometers worth of roads and more than 1,200 bridges have been completed and upgraded across the country.

“Of note, we have provided the budget to upgrade 367 bridges and almost 1,600 kilometers of road along our country’s longest thoroughfare — the Maharlika Highway — from Luzon all the way to Mindanao.”

“Moreover, significant segments of major expressways, which are part of the Luzon Spine Expressway Network, have now been opened to the public.”

By the end of this year, he announced that the C-LEX, NLEX-SLEX Connector, and the Plaridel Bypass will be fully completed, while the CALAX and the C5 South Link will be fully operational by next year.

“Under our Inter-Island Linkage Bridge Program, we expect two major bridges to be opened to motorists this year. One is the Panguil Bay Bridge — touted as the longest water-spanning bridge in Northern Mindanao.”

“This bridge will connect Lanao del Norte to Misamis Occidental. The other is the Guicam Bridge in Zamboanga Sibugay, which shall connect Olutanga Island to the mainland of Mindanao.”

“In addition, travel to and from Clark Airport is now much faster and more convenient, with the inauguration of the 20-kilometer Airport-New Clark City Access Road in Pampanga.”

“We are in the midst as well of a ‘railway renaissance’. The Metro Manila Subway Project has logged significant accomplishments in its tunneling works.”

Additionally, other railway projects such as the MRT-7 and the North-South Commuter Railway are in progress.

He mentioned that government will make sure that the right of way issues are resolved in the most equitable, efficient, and expeditious manner, so that these will not get in the way of the infrastructure development.

As part of the LRT 1 Cavite Extension project, the route of LRT Line 1 in Metro Manila will be extended from Baclaran to Sucat in Paranaque City. This is expected to be open to the public within the year. After a few years, the route will further extent to Bacoor in Cavite. 

He also reported that LRT 1 had an additional 76 new and modern trains. This upgrade will provide a faster and more comfortable commuting experience for passengers.

The recent reopening of the PNR Bicol Line is also a milestone achievement in the list of railway projects. This railway spans out to 100 kilometers from Naga to Legazpi.

President Marcos Jr. also talked about the improvement of the country’s airports and harbors for the benefit of travelers.

With the help of the private sector, the Ninoy Aquino International Airport is expected to improve and provide better services in the years to come.

“Soon, it will be capable of accommodating 48 flights per hour, servicing our ever-increasing local and international flight routes, and catering to more than 62 million passengers per year.”

“More than 70 airport and seaport development projects across the country have been completed, and another 350 ongoing projects are set to be completed by 2028.”

“Notably, the capacities of the Passenger Terminal Buildings of the General Santos Airport and the Bicol International Airport have been expanded by 300 and 500 percent, now catering to 2,000 and 1,600 passengers, respectively. Meanwhile, the Batangas Port PTB, our popular marine gateway to MIMAROPA, the Visayas and to Mindanao, can now accommodate 8,000 travelers at any given time.”

“Thanks to Congress, the Public-Private Partnership, as a crucial funding mechanism for big-ticket projects, is now institutionalized by force of law. PPP is seen to facilitate strategic investments and the timely development of projects under our Build Better More program, especially since around one-fourth of our flagship projects have been envisioned to be funded through this modality.”

He emphasized that the NAIA PPP will go down in history as being the largest and fastest approved PPP, as well as setting the standard in terms of transparency and competitiveness of the process.

“Through this partnership, our foremost aerial gateway is now primed for a revitalization. Once considered among the worst and most stressful airports in the world, it will soon be a world-class international airport that we can be proud of.”

 

Reference:

https://pco.gov.ph/presidential-speech/3rd-state-of-the-nation-address-of-his-excellency-ferdinand-r-marcos-jr-president-of-the-philippines-to-the-congress-of-the-philippines/

July 22, 2024

Progress continues to surge forward on the Davao River (Bucana) Bridge Project of the Department of Public Works and Highways (DPWH) in Davao City.

In his inspection report to DPWH Secretary Manuel M. Bonoan, Senior Undersecretary Emil K. Sadain said that the construction of the 1.34-kilometer, four (4)-lane, six (6)-span extradosed bridge and its approach roads over the Davao River which started in November 2023 has made significant strides, with completion now reaching 32.13%.

Senior Undersecretary Sadain, in charge of DPWH infrastructure flagship projects alongside Unified Project Management Office - Bridges Management Cluster (UPMO-BMC) Project Director Rodrigo I. Delos Reyes conducted a site inspection on July 19, 2024.

Their project visit together with UPMO - Roads Management Cluster I Project Director Benjamin A. Bautista highlighted substantial advancements in the ₱3.126 billion construction of the bridge funded by the Philippine government and a China Aid Grant.

"With active project supervision and management by UPMO-BMC Bucana Bridge Project Team headed by Acting Project Manager Norifel Teddie G. Cadiang and Project Engineer John Christian T. Gaden and the dedication of our partners at China Road and Bridge Corporation (CRBC), we are confident in meeting our target to open the bridge to traffic by end of 2025”, Senior Undersecretary Sadain added.

The bridge project that will complement the Davao City Coastal Road upon completion promises enhanced mobility, connectivity, and economic opportunities for Davao Region.

This project under the “Build Better More” agenda of the administration of President Ferdinand R. Marcos Jr. is an essential transportation infrastructure, providing faster and more efficient roadway to large volume of vehicles and in alleviating the east-west traffic congestion in the coastal areas of Davao City.

Currently, civil works for the bridge include the installation of rebars for pier columns and crossbeams, simultaneous with placement of scaffoldings in preparation for deck construction. Activities such as steel sheet pile driving for cofferdamming and bored piling are also progressing as planned.

July 22, 2024

The highly anticipated modern scenic bridge project, implemented by the Department of Public Works and Highways (DPWH), connecting the Island Garden City of Samal (IGaCoS) and Davao City, has made significant strides in both design and construction.

In his inspection report to DPWH Secretary Manuel M. Bonoan, Senior Undersecretary Emil K. Sadain highlighted that the ongoing bored piling works for the land viaduct structure of the Samal Island-Davao City Connector (SIDC) Project, which began in May 2024, are progressing well.

To date, 42 out of the 72 bored piles in Samal side have been completed, while in Davao City side, 23 out of 72 were finished.

Meanwhile, the Detailed Engineering Design (DED) phase is nearing completion at 94.41%, which comprise the approval of the design plans for substructure and superstructure of the land viaduct, marine viaduct, and navigation bridge.

According to Senior Undersecretary Sadain, despite encountered challenges and legal issues in the project implementation, the DPWH is taking proactive measures to ensure that issues are promptly addressed. This approach aims to keep civil works on schedule, avoiding delays and adhering to the project timeline.

“We are closely coordinating and monitoring every detail of progress in this project, as we aim to open this bridge to traffic within the term of President Ferdinand R. Marcos, Jr. This bridge will serve as one of the pioneering modern transportation infrastructures in Mindanao, enhancing economic growth, connectivity, and access to essential services and activities in IGaCoS and the Davao Region,” said Senior Undersecretary Sadain.

Also present at the site inspection on July 19, 2024 were DPWH Unified Project Management Office - Bridges Management Cluster (UPMO - BMC) Project Director Rodrigo I. Delos Reyes, UPMO Roads Management Cluster I Project Director Benjamin A. Bautista, Project Manager Joweto V. Tulaylay, and Project Engineer John Christian T. Gaden.

With an estimated total cost of ₱23.52 billion, the SIDC Project is funded through Official Development Assistance (ODA) under the Government of China’s concessional loan.

The SIDC Project features a four-lane (two lanes each direction) extradosed bridge with a total length of 4.01 kilometers, a main span of 275 meters, and a vertical navigation clearance of 47 meters across the Pakiputan Strait. The marine crossing is approximately 1.62 kilometers long with a seabed depth of 40 meters, supported by two pylons standing 73 meters above sea level.

Once completed, this iconic bridge will provide a resilient and reliable transportation link between IGaCoS and Davao City, instrumental in spurring economic growth and development in the Southern Philippines.

July 22, 2024

The Department of Public Works and Highways (DPWH) is advancing steadily on the Davao City Bypass Construction Project (DCBCP), with ongoing efforts in tunnel waterproofing and the construction of concrete arch and invert linings for the two (2)-lane northbound and southbound tunnels.

Senior Undersecretary Emil K. Sadain, in-charge of DPWH infrastructure flagship projects, explained that these crucial activities are part of the effort to ensure structural integrity and durability. This is essential to provide a safe and reliable passage for motorists through the 2.3-kilometer twin tube tunnel component of the DCBCP.

The road mountain tunnel is a key part of the ₱13.23 billion DCBCP Contract Package I-1, financed through a Special Terms for Economic Partnership (STEP) Loan from the Japan International Cooperation Agency (JICA).

In his report to Secretary Manuel M. Bonoan, Senior Undersecretary Sadain emphasized that Japan’s engineering expertise and advanced technology are being utilized in the construction of what will soon be the longest road mountain tunnel in Mindanao.

This project also promotes technological transfer between Japan and the Philippines, with provisions for technical assistance and capacity building to ensure successful implementation and sustainability.

During a site inspection on July 19, 2024, Senior Undersecretary Sadain, along with Project Director Benjamin A. Bautista of the Unified Project Management Office (UPMO) - Roads Management Cluster I (Bilateral) and Project Director Rodrigo I. Delos Reyes of the UPMO Bridges Management Cluster, observed the meticulous work on waterproofing and subsequent concrete pouring for the invert arch lining.

The waterproofing efforts, which have covered 1.130-kilometer northbound and 1.135-kilometer southbound, are crucial for preventing water ingress, preserving the tunnel’s longevity, and ensuring operational efficiency.

Meanwhile, 978 meters northbound and 967 meters southbound have already been fitted with invert arch lining concrete, which will reinforce the tunnel structure and improve its ability to withstand various loads and environmental conditions.

The entire Contract Package I-1 involves the construction of a 10.7-kilometer two (2)-lane carriageway for both northbound and southbound roads, divided by a median, from the Mintal Road Intersection at Sta. 12+800 to the Mandug Road Intersection at Sta. 23+500. The package also includes three (3) pairs of river bridges with a total length of 0.5 kilometers and two (2) underpasses.

With an overall accomplishment of 51.5%, Contract Package I-1 also covers the construction of access roads to the bridges and tunnel portals, two (2) Engineer’s offices with laboratories, and main and sub-offices at the north and south portal sides, respectively, for construction supervision and management.

The Engineer’s Offices were designed to meet the standards of a typical school building and are planned for future turnover to the Department of Education as additional learning facilities.

Under contract with the Shimizu - Ulticon - Takenaka joint venture, DPWH field supervision for Contract Package I-1 is managed by Project Manager Joselito B. Reyes, Project Engineer Juan M. Diña Jr., and Engineer Earl Nicholas F. Rada of the UPMO - Roads Management Cluster I (Bilateral).

July 15, 2024

The construction of the 32-kilometer Bataan-Cavite Interlink Bridge is likely to start early or mid 2025, the Department of Public Works and Highways (DPWH) said Thursday. 

With an initial cost of PHP219 billion, the Bataan-Cavite mega bridge is set to be the “biggest and the single most expensive project” of the DPWH, Public Works Undersecretary Maria Catalina Cabral said during the Build Better More Infrastructure Forum at New Clark City in this town.

The bridge, once completed, will reduce the travel time between Bataan and Cavite from five hours to 45 minutes bypassing Metro Manila by crossing Manila Bay.

The detailed engineering design of the mega bridge project has been completed, while the bidding of the initial contract package was held last week, Cabral said.

“Hopefully, it will be started either by early part of next year or middle of next year,” she said.

The project will be funded through an official development assistance (ODA).

ODA loans support developing countries by providing low-interest, long-term and concessional funds to finance development projects.

The construction of the Bataan-Cavite bridge project was supposed to start late 2024.

Asked what caused the delay, Cabral explained that the government took its time in looking for the "best financing package" available.

“Sourcing the funding has been really the problem. We’re trying to get the best financing package for this biggest project of the DPWH and finally we are able to do so," Cabral said.

“I think last week we just held the bidding for the first contract packages,” she added.

Infra program forum

Spearheaded by the Presidential Communications Office (PCO), the Build Better More Infrastructure forum is the third leg of the PCO‘s pioneering initiative, the Bagong Pilipinas Media Engagement and Workshop Series of 2024, following the successful culmination of the Food Security Cluster Communications Workshop and National Security Cluster Communications Workshop in March and April 2024, respectively.

It seeks to provide a platform to allow government agencies to engage and collaborate with the media and government communicators to enhance the quality and value of public discourse on the Build Better More Infrastructure Program – the flagship infrastructure development agenda of the Marcos administration.

The program includes 187 infrastructure flagship projects.

July 15, 2024

A ₱23.36 billion Public-Private Partnership (PPP) contract has been signed between the Department of Public Works and Highways (DPWH) and San Miguel Holdings Corp. (SMHC) for the construction of 59.4-kilometer extension of Tarlac-Pangasinan-La Union Expressway (TPLEX) all the way to the surfing capital of the north in San Juan, La Union.

DPWH Secretary Manuel M. Bonoan and SMHC Chairman and President Ramon S. Ang presented to President Ferdinand R. Marcos Jr. on Wednesday, July 10, 2024 the concession agreement, which was signed on July 3, 2024 at the DPWH Head Office in Port Area, Manila, and witnessed by DPWH Undersecretary for Planning and PPP Services Maria Catalina E. Cabral, and Mr. Raoul Eduardo Romulo of the project concessionaire SMC TPLEX Extension Infrastructure Corp. (STEIC) among others.

Also present in the event held at the Kalayaan Hall of Malacañang Palace are Executive Secretary Lucas Bersamin; National Economic and Development Authority Secretary Arsenio M. Balisacan; DPWH Undersecretaries Cabral, Eugenio R. Pipo Jr., Roberto R. Bernardo, Ador G. Canlas, and Carlos G. Mutuc; and DPWH Public-Private Partnership Service Director Pelita V. Galvez.

“With the signed PPP contract, the STEIC and DPWH can now proceed with detailed engineering design (DED), parcellary plan, right-of-way (ROW) acquisition for all the segments, so that we can commence civil works by July 2025,” said Secretary Bonoan.

According to Secretary Bonoan, the TPLEX Extension Project will be divided in three (3) segments, with first segment aimed for completion before the end of President Marcos’ term in 2028.

Segment 1 will start from the last exit of TPLEX at Rosario and end in Tubao, which is an additional 18.5-kilometer of 4-lane road, while Segment 2 will cover the 23.1-kilometer section from Tubao to Naguilian; and Segment 3 which extends 17.8-kilometer from Naguilian to San Juan, La Union.

The TPLEX Extension will have five (5) interchanges namely Rosario, Tubao, Naguilian, Bauang, and San Juan.

When completed, the TPLEX Extension will reduce travel time from Rosario going to San Juan, La Union from the current one (1) and a half hour to just 40 minutes, further promoting investments and economic development up north.

July 08, 2024

Construction for the Metro Manila Subway Project (MMSP) is expected to speed up with the arrival of two more tunnel boring machines (TBM) by yearend, for a total of six so far.

At the Pre-SONA (State of the Nation Address) Special over state-run People’s Television Network on Friday, Department of Transportation (DOTr) Secretary Jaime Bautista said four TBMs are currently in operation and the project construction is in full blast.

“Meron na tayong apat na TBMs na almost 24 hours ang operations niya. Within the year ay magiging anim yan (We already have four TBMs that are operating almost 24 hours a day. Within the year, that will become six),” Bautista said.

He said the TBMs will increase to at least 19 working simultaneously in the coming years.

According to DOTr data, an estimated 1.2 million cubic meters of soil using cut-cover and TBMs are to be excavated for the partial operability section of the MMSP, equivalent to 500 Olympic-sized swimming pools.

“For the tunnels alone, the excavation will be around 711,000 cubic meters or an equivalent of 285 Olympic size swimming pools,” he said.

The DOTr is also working with the MMSP’s contractors to fast-track the construction of subway stations.

“Itong Metro Manila Subway, ang more challenging part of the construction ‘yung mga stations kasi maraming stations ‘yan -- 17 stations (For the MMSP, the challenging part of the construction are the stations because there will be 17 of them),” he said.

Once completed, the MMSP will cut across eight cities in Metro Manila, stretching from Valenzuela City to FTI-Bicutan in Parañaque City with a spur line to Ninoy Aquino International Airport (NAIA) Terminal 3 in Pasay City.

The 33-kilometer subway line aims to cut travel time between Quezon City and NAIA from the current average of one hour and 10 minutes to just 35 minutes.

July 08, 2024

Top officials from the Department of Public Works and Highways (DPWH), alongside local leaders from Misamis Occidental and Lanao del Norte, held on July 4, 2024 the final concrete pouring ceremony between the two (2) extra-dosed main bridge of the Panguil Bay Bridge Project (PBBP).

This significat event saw the participation of DPWH Secretary Manuel M. Bonoan; Senior Undersecretary Emil K. Sadain; DPWH Undersecretaries Eugenio R. Pipo Jr. and Carlos G. Mutuc; Assistant Secretary Rey Peter Gille; Misamis Occidental Governor Henry S. Oaminal Sr.; Lanao del Norte Governor Imelda Quibranza Dimaporo; Ozamis City Mayor Henry “Indy” F. Oaminal Jr.; Korea Export Import Bank (KEXIM) Deputy Country Director Yun Hak Lee; Project Directors Teresita V. Bauzon, Soledad R. Florencio, Benjamin A. Bautista, Rodrigo I. Delos Reyes, and Najib D. Dilangalen; DPWH Regional Office 10 Director Zenaida Tan; Stakeholders Service Director Randy R. Del Rosario; and other public works and locals officials and staff.

The topping-off ceremony marked the completion of the bridge’s pre-stressed concrete box girder between pylon 1 in Tangub City, Misamis Occidental, and pylon 2 in Tubod, Lanao del Norte, signifying a crucial milestone for the project.

Secretary Bonoan highlighted the importance of this milestone, stating that it brings the vision of a fully connected Panguil Bay Bridge closer to reality, promising numerous possibilities for the nation.

In his opening remarks, Senior Undersecretary Sadain praised the final construction stage as a testament to the dedication and hard work of everyone involved, heralding a new era of connectivity and economic growth for Mindanao and the entire Philippines.

The Panguil Bay Bridge, soon to be the longest bridge in Mindanao at 3.169 kilometers, includes a 320-meter extra-dosed main bridge, a 1,920-meter pre-stressed concrete girder approach bridge, and a 929-meter approach road.

The bridge is expected to catalyze economic activities, improve quality of life, and open new opportunities for trade, tourism, and investment, significantly benefiting local communities and contributing to national development.

The project is implemented by the DPWH Unified Project Management Office (UPMO) Operations under supervision of Senior Undersecretary Sadain and more specifically by the Roads Management Cluster II (Multilateral) led by former Project Director Sharif Madsmo H. Hasim and now headed by OIC Project Director Bauzon.

Funded by a loan agreement between the Government of the Philippines and the Republic of Korea through the Korea Export-Import Bank Economic Development Cooperation Fund (KEDCF) under Loan Agreement No. PHL-18, the Panguil Bay Bridge stands as a beacon of international cooperation and shared progress.

Despite commencing civil works at the height of the pandemic and facing significant challenges in weather conditions, material supply, and health restrictions, the DPWH relentlessly pushed the design and build contractor, Namkwang Engineering & Construction Corporation, in joint venture with Kukdong Engineering & Construction Co., Ltd. and Gumgwang Construction Co., Ltd., along with the project consultant, Yooshin Engineering Corporation, in joint venture with Pyunghwa Engineering Consultants Ltd. and Kyong-Ho Engineering & Architects Co., Ltd., to exert their utmost effort to accelerate the construction activities of this infrastructure flagship project.

Costing ₱7.375 Billion, the project has an overall weighted accomplishment of 93.3 percent and targetted for completion within this third quarter of 2024.

July 08, 2024

A top official of the Department of Public Works and Highways (DPWH) has issued a stern reminder to all government engineers, consultants and contractors involved in the on-going projects under the Improving Growth Corridors in Mindanao Road Sector Project (IGCMRSP).

In a recent coordination meeting at Ipil, Zamboanga Sibugay, Senior Undersecretary Emil K. Sadain stressed the importance of executing projects efficiently and effectively, adhering to the highest standards of quality and safety.

“It is imperative that we approach our work with a strong sense of responsibility and dedication. Delays and substandard work are unacceptable and will not be tolerated,” Senior Undersecretary Sadain said.

He emphasized Secretary Manuel M. Bonoan’s marching order for a heightened sense of urgency, unwavering commitment, and full accountability in the execution of projects. These efforts will play a significant role in the economic development and connectivity of Mindanao under Bagong Pilipinas.

The ₱14.5 Billion IGCMRSP is funded through an Official Development Assistance (ODA) loan from the Asian Development Bank (ADB) and is being implemented by the DPWH Unified Project Management Office - Roads Management Cluster II-Multilateral (UPMO - RMC II).

IGCMRSP supports the goal of improved physical connectivity, which is vital to the country’s development efforts as outlined in the President Ferdinand R. Marcos, Jr. administration’s Philippine Development Plan 2023-2028 and the 8-Point Socioeconomic Agenda.

The project encompasses the construction or improvement of seven (7) road subprojects with a total length of 151.97 kilometers, including 28 bridges and one (1) sea-crossing bridge sub-project, the Guicam Bridge, which spans 1.21 kilometers, all located in the Zamboanga Peninsula. Additionally, the project includes the construction of three (3) bridges with a total length of 1,790.66 lineal meters, including approaches, located in the Province of Tawi-Tawi.

To date, DPWH UPMO - RMC II has achieved an overall accomplishment of more than 71 percent for IGCMRSP. This includes 140 kilometers of concrete cement paved road and the completion of 14 bridges.

During the meeting, Senior Undersecretary Sadain conducted an in-depth review of the accomplishments against the timeline of each sub-projects and directed field engineers, contractors, and consultants to adopt adaptive planning to mitigate further delays.

Efforts to expedite work include deploying additional machinery and manpower and implementing round-the-clock work shifts to compensate for lost time on delayed sub-projects. The delays have been attributed to logistical challenges, weather conditions, and unforeseen technical issues.

A site inspection was conducted by Senior Undersecretary Sadain at the Guicam Bridge sub-project in Zamboanga Sibugay. He was accompanied by UPMO Project Directors Teresita V. Bauzon, Soledad R. Florencio, Benjamin A. Bautista, and Rodrigo I. Delos Reyes; Project Managers Emmanuel M. Supe and Evangeline L. Carabal; and Engrs. Barley H. Sali and Nancy C. Mari.

Senior Undersecretary reminded the contractor, Grace Construction Corporation of the strict timelines and performance benchmarks set for the project. To date, the Guicam Bridge has completed abutments A and B, and piers 1, 2, 3, 9, 10 and 11 and is targeted for full completion by mid-2025.

The realization of this inter-island bridge project complementing the 29.70-kilometer Lutiman-Guicam-Olutanga Road, a completed sub-project of IGCMRSP, is poised to enhance the economic activities and logistics in the municipalities of Alicia and Olutanga Island towards other towns of Zamboanga Sibugay.

Meanwhile, the construction of the 541-meter Nalil-Sikkiat Bridge in Tawi-Tawi Province by China Wuyi Co., Ltd. and under the supervision of UPMO Project Manager Ernante S. Antonio is progressing rapidly.

At more than 60% completed, the fast-paced construction reflects the commitment to delivering crucial infrastructure that benefits local communities and stimulates growth in the area.

This project is part of the national government’s efforts to enhance infrastructure in the Bangsamoro Autonomous Region for Muslim Mindanao, improving connectivity and supporting economic development.

Other on-going sub-projects are the 33.05-kilometer Curuan-Sibuco Road connecting Zamboanga City to Zamboanga Del Norte with accomplishment of 87% by the joint venture contract of M. Abubakar Construction and Engineering Inc. and Sino Road and Bridge Group; 24.52-kilometer R.T. Lim - Siocon Road connecting Zamboanga Sibugay and Zamboanga Del Norte at 88% and 7.38-kilometer Gutalac-Baliguian Alternative Road in Zamboanga Del Norte at 52% under China Wuyi Co. Ltd.; 17.93-kilometer Siay-Gapol Road in Zamboanga Sibugay under ESR Construction & Development Corporation in venture with Qingdao Municipal Construction Group Co. Ltd at 71%; and Malassa-Lupa Pula Bridge in Tawi-Tawi at 31% under Vicente T. Lao Construction and China Wuyi Co. Ltd.