DPWH LEADS KICK-OFF CEREMONY OF DAVAO CITY BYPASS ROAD SOUTH PORTAL TUNNEL
Photo credit: Department of Public Works and Highways
Tunnel boring activity of the Department of Public Works and Highways (DPWH) at south portal of the twin tunnels of Davao City Bypass Construction Project has kicked-off on Thursday, May 12, 2022.
In his report to DPWH Secretary Roger G. Mercado, Undersecretary and Build Build Build Chief Implementer Emil K. Sadain said that the simultaneous tunnel boring activities at north and south portals will result to the speedy construction of the 2.3-kilometer first-ever long distance mountain tunnel in the Philippines.
The kick-off ceremony for the tunnel works on northbound direction of south portal in Barangay Matina Biao, Davao City was attended by Consul General Yoshihisa Ishikawa of the Consular Office of Japan in Davao; DPWH Undersecretary Sadain; Japan International Cooperation Agency (JICA) Chief Representative in the Philippines Takema Sakamoto; and DPWH Assistant Secretary Rolito D. Manalo.
Also witnessing the first excavation on south portal’s northbound direction of the two (2)-tube mountain tunnel project are Project Director Benjamin A. Bautista of DPWH Unified Project Management Office (UPMO) – Roads Management Cluster I (Bilateral); DPWH Region 11 Director Rey Peter B. Gille; Project Managers Joselito B. Reyes and Joweto V. Tulaylay; Davao City District Engineer Richard A. Ragasa; Engr. Earl Nicholas F. Rada; officers of the consultants Nippon Koei Ltd., Katahira & Engineers International, Nippon Engineering Consultants Co., and PhilKoei International Inc.; and other public works officials.
With the simultaneous tunneling works on the north and south portals, the joint venture companies of Shimizu Corporation, Ulticon Builders Inc., and Takenaka Civil Engineering and Construction Company Limited can ramp up their construction towards rapid completion of the project so that people of Mindanao can finally enjoy the convenience and its other benefits, added Undersecretary Sadain.
Designed to have better seismic resiliency by Japanese experts, the tunnel construction activities at the south portal - southbound and northbound directions were earlier started in November 2021 and March 2022, respectively.
Davao City Bypass Construction Project is among the flagship infrastructure projects under the “Build, Build, Build” program implemented by DPWH UPMO Operations headed by Undersecretary Sadain to reduce congestion in Davao City and cut travel time between Toril, Davao City and JP Laurel, Panabo City to 49 minutes from the current one (1) hour and 44 minutes.
The construction of the bypass road will improve transport logistics and mitigate congestion in the Davao City urban center to contribute to the economic and social development of Mindanao.
In his sent message, Presidential son and newly elected Davao City Mayor Sebastian Duterte expressed excitement for the Davao City Bypass Construction Project as it will greatly improve the city's accessibility and traffic condition by the opening of this new road network that will also usher more developments outside the city center.
Undersecretary Sadain said that as the Philippines transitions to a new administration by June 30, DPWH will continue to work hard in delivering the completion of on-going infrastructure flagship projects and is looking forward to build more new pipeline projects towards the next administration to sustain rapid growth, attract investments and attain economic inclusion for all Filipinos.
While construction of the tunnel is the centerpiece of Contract Package 1 - 1, the contract also includes construction of a 7.9 kilometer four (4)-lane road, three (3) pairs of bridges with a total length of 500 meters, two (2) underpasses, two (2) overpasses, a dozen box-culverts (waterways), and four (4) at-grade intersections.
The tunneling activity uses specialized equipment such as drill jumbo, concrete spraying machine and articulated dump hauler to excavate tunnel that has a diameter of 10 meters.
The on-going Contract Package 1-1 costing ₱13.23 Billion is financed by Special Terms for Economic Partnership (STEP) Loan between Philippines and JICA under loan agreement numbers PH-P261 and PH-P273.
Article courtesy of Department of Public Works and Highways

SECRETARY MERCADO DECLARES DPWH COMPASSION IMPROVED PUBLIC TRUST AND CONFIDENCE
Department of Public Works and Highways (DPWH) Secretary Roger G. Mercado spearheaded on Thursday, April 28, 2022 the conduct of DPWH accomplishments review for the first quarter and moving on into the second quarter of CY 2022.
Secretary Mercado proudly declared at the Unified Directors Meeting attended by the Undersecretaries, Assistant Secretaries, Regional Directors, Project Directors, Service Directors, and Bureau Directors including District Engineers of Central Visayas as host Region that the agency has won the trust and confidence of the people who now feel the impact of what the Department has delivered and achieved.
In the survey conducted by Publicus Asia Incorporated for the first quarter of 2022, the DPWH was among the top 10 national government agencies with the highest approval and trust ratings.
People judged us by our deeds and our deeds are measured by how much we have contributed to the national government’s initiatives to improve the quality of life of our people, said Secretary Mercado.
Considering the large number of agencies of the national government, the seventh (7th) rank in approval and tenth (10th) place in trust is an outstanding achievement, added Secretary Mercado.
During the time of the pandemic, DPWH did not only do major infrastructure but also put up much needed quarantine facilities.
The DPWH implemented projects provided jobs to tens of thousands of unemployed to cushion the economic effect of the pandemic.
In the face of widespread devastation caused by calamities like typhoon “Odette”, DPWH deployed both men and equipment in round-the-clock rescue, clearing, and relief operations.
Despite dangers and difficulties, DPWH never daunted and has shown that the organization is filled with brave men and women who are willing to risk their own lives in the face of adversity.
The DPWH Chief attributed the shift of mindset and heart of people to the nurtured seed of compassion at the Deparment.
“It is compassion for our people that keeps us going, when the going gets tough. It is compassion that makes us work the extra mile to perform the task beyond our duty”, said Secretary Mercado.
He encouraged the DPWH leaders to continue to nourish compassion until it fully blooms to create a culture in all offices and every place of work.
Secretary Mercado commended DPWH Regional Office 7 headed by Regional Director Edgar Tabacon for graciously hosting the Unified Directors Meeting for the month of April.
Secretary Mercado had a hands full visit in Cebu City as resource speaker, attendee to project inauguration, and meeting presider.
He was a guest of honor at the District Engineers League of the Philippines (DELP) National Executive Board Meeting on April 27, 2022, providing policy guidelines and instructions to the DPWH field executives.
The national executive board and chapter heads of DELP, the unifying organization for DPWH district and assistant district engineers, took the opportunity to inform Acting Secretary Mercado and Senior Undersecretary Rafael C. Yabut of their issues and concerns as frontliners of the Department across the country.
The DPWH Secretary later joined President Rodrigo Roa Duterte at the inauguration of the Cebu-Cordova Link Expressway (CCLEX) project, an 8.9 kilometer bridge that links mainland Cebu in Cebu City to Mactan Island through the town of Cordova.
Article courtesy of Department of Public Works and Highways

5TH INTER-AGENCY FORUM ON INFRA HIGHLIGHTS BBB PROJECTS; DISCUSSES TRANSITION PLAN FOR NEXT ADMIN
Officials of the Department of Public Works and Highways (DPWH) together with heads of line and oversight agencies and development partners involved in the implementation of infrastructure flagship projects (IFP) under Build Build Build (BBB) Program met on Wednesday, April 27, 2022 for the 5th Inter-agency IFP Forum: Final Project Review of the Working Committee for Forward Transition.
DPWH Undersecretary for Unified Project Management Office (UPMO) Operations Emil K. Sadain, currently serving in his excellent capacity as the Build Build Build Program Chief Implementer, gave the opening remarks of 5th Inter-agency IFP Forum held at the Philippine International Convention Center – Reception Hall in Pasay City.
Since he was directed on November 2021 by President Rodrigo Roa Duterte to supervise and oversee the overall implementation of flagship projects under the BBB Program, Undersecretary Sadain organized a monthly forum to provide an inter-agency reporting for the review of progress on all flagship projects and has closely coordinated with oversight agencies namely National Economic and Development Authority (NEDA), Department of Finance (DOF), and Department of Budget and Management (DBM).
"While the flagship infrastructure projects under BBB Program continued to make progress, it is also setting up the foundation in terms of infrastructure for the next administration and beyond," said Undersecretary Sadain.
Undersecretary Sadain mentioned that the synergy of the Cabinet Infrastructure Cluster headed by DPWH Acting Secretary Roger G. Mercado and Economic Development Cluster led by DOF Secretary Carlos G. Dominguez is instrumental in the desired sustainability and continuity of all infrastructure flagship projects by the next incoming administration.
"As Chief Implementer of BBB program, I take pride in our resiliency, when we stood the ground against the pandemic and other calamities, working even harder amidst the struggles and unprecedented changes to sustain the momentum of the vision of massive infrastructure development," added Undersecretary Sadain.
Meanwhile, Undersecretary Sadain in his role as the Chief Implementer of the BBB Program was given both a certificate and plaque of appreciation signed by Executive Secretary Salvador C. Medialdea in grateful appreciation of his invaluable support and contribution to the success of the BBB Program that ushers the "Golden Age of Infrastructure" in the Philippines.
With the BBB Program on full swing in the last few years even amidst the pandemic crisis, the government disbursement of its funds have reached record high due to strong infrastructure spending and other capital outlays, said Department of Budget and Management (DBM) Undersecretary Rolando U. Toledo.
OIC- Undersecretary Roderick M. Planta of NEDA, the agency responsible for infrastructure planning and investment programming and likewise supervises the appraisal of major capital projects, said that infrastructure projects has strengthened the investment climate needed to bring economic growth to the country.
DOF Undersecretary Bayani H. Agabin cited the vigorous implementation of high impact infrastructure projects in jumpstarting economic recovery from the pandemic.
The IFP Forum was also attended by development partners namely Asian Development Bank (ADB) Country Director Kelly Bird, Japan International Cooperation Agency (JICA) Philippines Chief Representative Takema Sakamoto, World Bank Representative Feng Liu, and Korea Eximbank Country Director Moon Jae Joong.
With DPWH as the leading infrastructure arm of the government, Project Director Rodrigo I. Delos Reyes representing the Unified Project Management Office (UPMO) Operations, summed up in his report the progress of DPWH flagship projects with most impact on the economy.
Executive Director Atty. Alvin Carullo of the Toll Regulatory Board, the agency that regulates and administers toll road facilities provided updates on implemention of the five (5) PPP expressways projects.
The Department of Transportation (DOTr) had a comprehensive report of railways projects by Undersecretary Timothy John Batan; roads and infrastructure sector projects by Undersecretary Mark Steven Pastor; aviation and airports sector projects by Assistant Secretary Jaime Melo; maritime sector projects by Undersecretary George V. Ursabia Jr.; and pipelined projects by Assistant Secretary Ma. Sheilah Napalang.
Metropolitan Waterworks and Sewerage System (MWSS) Administrator Leonor Cleofas gave an insight on the different projects laid out for the water resources and sewerage systems around Metro Manila.
University of the Philippines - Philippine General Hospital (UP-PGH) Vice President Elvira Zamora discussed the new PGH building that will soon rise in Diliman, Quezon City including a new Cancer Center.
The soon-to-be the country's first-ever Virology Science and Technology Institute was presented by Director Annabelle Briones of the Department of Science and Technology - Industrial Technology Development Institute.
National Power Corporation (NPC) Officer-in-Charge Undersecretary Donato Marcos speaks on the power generation projects being implemented by NPC.
DICT Undersecretary Maria Victoria Castro showcased the plans for the enhancement of the information and communications technology (ICT) system all throughout the country.
Department of Health (DOH) Undersecretary of the Health Facilities and Infrastructure Team Dr. Lilibeth C. David provided an overview of the projects implemented by DOH as they lead the fight against the COVID-19 pandemic.
Philippine Statistics Authority (PSA) Assistant Secretary Rosalinda Bautista shared the progress of the Philippine Identification System (PhilSys) project as one (1) of the trailblazing legacies of the Duterte administration.
The latest development on projects geared towards the improvement of water districts nationwide was reported by Local Water Utilities Administration (LWUA) OIC-Administrator Eileen Dela Vega while National Irrigation Administration (NIA) Administrator General Ricardo Visaya elaborated the plans for the betterment of the irrigation networks and facilities nationwide.
Article courtesy of Department of Public Works and Highways

ADB SUPPORTS DPWH CONSTRUCTION OF 3 MARIKINA BRIDGES
Photo credit: Department of Public Works and Highways
The Philippine Government and Asian Development Bank (ADB) have reaffirmed their strong partnership for long-term economic growth through infrastructure projects to accelerate economic recovery by improving connectivity.
Department of Public Works and Highways (DPWH) Secretary Roger G. Mercado announced that ADB will co-financed the construction of three (3) new bridges to help solve the increasingly severe traffic problem in Metro Manila.
“A loan agreement with ADB is an exciting assurance of the construction of three (3) new climate and disaster resilient bridges as well as added training program to strengthen DPWH institutional capacity in bridge operation and maintenance”, said Secretary Mercado.
The ceremonial exchange of the financing agreements between ADB and the Department of Finance (DOF) representing the Government of the Republic of the Philippines for the DPWH Metro Manila Bridges Project was held on Wednesday, March 30, 2022.
Receiving the loan documents on behalf of the Philippine Government is Finance Secretary Carlos G. Dominguez while receiving on behalf of the Asian Development Bank is Managing Director General Woochung Um.
The exchange of documents was witnessed by DPWH Secretary Mercado; DOF Undersecretary Maria Edita Z. Tan; ADB Philippine Country Office Director Kelly Bird; and ADB Deputy Director General Winfried Wicklein.
Also in attendance in the event held at DOF Podium Conference Room, BSP Complex, Roxas Boulevard, Manila were DPWH Undersecretary for Unified Project Management Office (UPMO) Operations and Build Build Build Chief Implementer Emil K. Sadain; Project Director Rodrigo I. Delos Reyes of DPWH UPMO - Bridges Management Cluster; ADB Alternate Executive Director Paul G. Dominguez; DOF Undersecretary Mark Dennis Y.C. Joven and Assistant Secretary Neil Cables; ADB Advisor to the Executive Director Ms. Tuya Darinchuluun; and other DOF, DPWH, and ADB officials.
Loan Agreement 4168-PHI between the Philippine government and ADB amounting to 175 million-dollar will be utilized exclusively for the financing of the Metro Manila Bridges Project. The loan was approved by the ADB Board of Directors and signed by ADB and DOF last December 2021.
As part of the overall Metro Manila Logistics Network with a total of 12 bridges being eyed over Pasig River, Marikina River, and the Manggahan Floodway, the ADB-assisted Metro Manila Bridges Project involves the construction of three (3) new bridges which is aimed at improving efficiency of road travel crossing Marikina River.
These bridges are the Marcos Highway-Saint Mary Bridge (Formerly J.P. Rizal-St. Mary Bridge) with a total length of 1,582.6 meters including the main bridge length of 325 meters; Homeowners Drive-A. Bonifacio Ave. Bridge (Formerly J.P. Rizal-Lopez Jaena Bridge) with a total length of 691 meters including the main bridge length of 461.5 meters; and Kabayani-Matandang Balara Bridge (Formerly Marikina-Vista Real Bridge) with a total length of 723.2 meters including the main bridge length of 364 meters.
To achieve seamless travel and connectivity, three (3) of the bridges in the Metro Manila Logistics Improvement were completed with one (1) due for opening on April 5, 2022, two (2) are in the procurement stage, and three (3) under financing negotiation. Completed across Pasig River are the Bonifacio Global City – Ortigas Center Link Road Project that involves the construction of a 4-lane Sta Monica to Lawton Bridge or Kalayaan Bridge, Estrella - Pantaleon Bridge, and Binondo - Intramuros Bridge.
Secretary Mercado expressed confidence that the construction of new bridges in Marikina City will be effectively and expeditiously implemented by the team of Undersecretary Sadain in the UPMO Operations.
According to Undersecretary Sadain, ADB is involved in other flagship infrastructure projects of DPWH such as the technical and financial assistance for the on-going detailed engineering design of Bataan – Cavite Interlink Bridge and Laguna Lakeshore Road Network Project, and the on-going civil works construction of Improving Growth Network – Mindanao Sector Improvement Project.
These ADB-assisted big-ticket projects will ensure the sustainability of infrastructure development under Build, Build, Build Program even beyond the term of President Rodrigo Roa Duterte, Undersecretary Sadain said.
Article courtesy of The Department of Public Works and Highways

PRRD OPENS 4-LANE BINONDO-INTRAMUROS BRIDGE
Photo credit: The Department of Public Works and Highways
The Department of Public Works and Highways (DPWH) opened on Tuesday, April 5, 2022 the 680-meter Binondo-Intramuros Bridge Project crossing Pasig River in the City of Manila.
No less than President Rodrigo Roa Duterte led the inauguration ceremonies for the iconic bridge project, together with DPWH Secretary Roger G. Mercado.
“The opening of Binondo-Intramuros Bridge is another testament of President Duterte’s political will to deliver in his term vital projects that will traffic ease congestion within Metro Manila,” said Secretary Mercado.
The project is under the supervision of DPWH Unified Project Management Office (UPMO) Operations headed by Undersecretary and Build Build Build Program Chief Implementer Emil K. Sadain.
Binondo - Intramuros Bridge Project is a joint undertaking of the Philippine Government and People’s Republic of China.
It is fully-funded through China-grant, along with the completed Estrella-Pantaleon Bridge.
According to Secretary Mercado, the Binondo-Intramuros Bridge is a basket-handle tied steel arch bridge that links Intramuros at Solana Street and Riverside Drive and Binondo at Rentas Street and Muelle dela Industria having a viaduct structure over Estero de Binondo.
“Built with four (4) lanes measuring 21.65 meter-wide, this new bridge will cater to around 30,000 motorists, going in and out of Intramuros and Binondo daily,” said Secretary Mercado.
Bike lanes with reflective thermoplastic road lines and protected sidewalks on both sides are also features of the project as part of DPWH’s program to build safe infrastructure for non-motorized road users.
The new bridge also conforms to the standard design under DPWH seismic guidelines, criteria and specifications in an effort to make it resilient in the event of large magnitude earthquakes.
“In the coming months, the public can expect a long list of pipeline flagship projects under Build Build Build Program started under the term of President Duterte to be completed and opened, that will lead to sustained inclusive growth for the benefit of our millions of Kababayans nationwide”, Undersecretary Sadain said.
Article courtesy of The Department of Public Works and Highways

DPWH INSTALLS FIRST PRE-CAST FRAMING FOR SUBSTRUCTURE FOUNDATION OF PANGUIL BAY BRIDGE
Photo credit: The Department of Public Works and Highways
The Department of Public Works and Highways (DPWH) announced the successful launching of one (1) of the four (4) open box-shaped pre-cast concrete assembly on top of six (6) underwater pile foundation for the main bridge pylon of the 3.17-kilometer Panguil Bay Bridge Project in Northern Mindanao.
In his inspection report to DPWH Secretary Roger G. Mercado, Undersecretary and Build Build Build Chief Implementer Emil K. Sadain said that the prestressed-concrete (PC) house for main bridge pylon 2 was successfully installed and mounted with welded brackets on permanent steel casing or outer circumferential surface of the pile to prevent the movement of the PC housing.
Undersecretary Sadain, in-charge of Unified Project Management Office (UPMO) Operations implementing large-scale flagship infrastructure projects under the Build Build Build program, explained that the prefabricated PC house will be the foundation for the two (2) pylons each with six (6) piles and piers 17 and 18 with four (4) piles each which are the substructure of the project’s main bridge or the highest segment where marine vessel such as ship could pass underneath.
Waterproof sealing are ongoing to ensure the watertightness between pile and boxlike PC house as this will then filled inside with cast concrete to act as cofferdam or strong foundation to make them stable against various forces which are likely to act on the structure, Undersecretary Sadain reported
This engineering process is to reduce the construction period, secure the concrete quality, and improve the constructability of substructure.
The first PC house, constructed at the fabrication yard in Tubod, Lanao Del Norte and transferred to the marine site using a floating heavy duty crane on barge, was inspected off-shore Panguil Bay on March 26, 2022 by Undersecretary Sadain with Project Director Sharif Madsmo H. Hasim of UPMO Roads Management Cluster 2 (Multilateral).
Also present in the inspection of the on-going flagship project connecting Tubod, Lanao Del Norte and Tangub City, Misamis Occidental are Project Director Benjamin A. Bautista of UPMO Roads Management Cluster 1 (Bilateral), Project Director Rodrigo I. Delos Reyes of UPMO Bridges Management Cluster, and Project Manager Mike Ramos.
Given the previous significant disruptions in the project construction activities caused by the COVID-19 pandemic, DPWH UPMO is committed to further increase its effort to fast-track the completion of the iconic bridge project which will soon be the longest in Mindanao.
Other on-going activities include bored piling works of remaining six (6) of the total 54 units, PC house fabrication, rebar cage installation, abutment rebar and form installation, and pier cap concrete pouring.
The P7.375 Billion inter-island bridge project to connect Tangub City and Tubod across Panguil Bay in just seven (7) minutes is funded by a loan agreement between Government of the Philippines (GOP) and Korean Export-Import Bank (Korea Eximbank).
Under contract with Korean firm Namkwang-Kukdong-Gumgwang Joint Venture, the project is targetted for completion by December 2023.
Article courtesy of The Department of Public Works and Highways

DPWH SPEEDS UP MOUNTAIN TUNNEL OF DAVAO CITY BYPASS PROJECT
The Department of Public Works and Highways (DPWH) - Unified Project Management Office (UPMO) Operations, which is implementing the Davao City Bypass Construction Project, now conducts simultaneous tunneling activities at northbound and southbound directions on north portal of the project’s road mountain tunnel component.
In his report to Secretary Roger G. Mercado, Undersecretary for UPMO Operations and Build Build Build Chief Implementer Emil K. Sadain said that works for the north portal’s northbound direction is now underway that will ramp-up project progress to catch-up on the late arrivals of special equipment/machineries and Japanese experts due to movement restrictions and delayed issuance of travel permits because of the pandemic.
Included in the list of flagship infrastructure projects of President Rodrigo Roa Duterte’s Build Build Build Program, the bypass road will mitigate congestions in Davao City with the travel time between Brgy. Sirawan in Toril District Davao City and Brgy. J.P. Laurel in Panabo City of 1 hour and 44 minutes via Pan-Philippine Highway Diversion Road to be reduced into 49 minutes via Davao City Bypass.
It is expected that the start up of excavation work at the northbound direction of the north portal will significantly speed up project delivery, Undersecretary Sadain reported.
Construction of the soundbound direction was earlier started on November 2021 and has more than 60 meters of road tunnel excavated with shotcrete, steel ribs and rockbolts.
The group of Shimizu-Ulticon-Takenaka led by Project Director Akira Mito is undertaking the construction of contract package 1-1 covering 10.7 kilometers of four-lane highway, inclusive of the 2.3 kilometer tunnel that has a diameter of 10 meters.
According to Undersecretary Sadain, the soon to be first-ever long-distance mountain tunnel in the Philippines was designed to have better seismic resiliency.
This is one of the largest and most important infrastructure project of the President Duterte administration in Mindanao towards the attainment of national development goals of “Ambisyon Natin 2040: Matatag, Maginhawa at Panatag na Buhay”.
Meanwhile, Undersecretary Sadain in his project inspection on March 11, 2022 reminded the contractors and consultants, to put primordial importance to safety management especially that the project, which also seeks to promote transfer of Japanese technology and expertise, is highly complex and have many risk-prone activities like excavation and lining, transportation of materials, drilling, handling of tunnel machinery, etc.
With various groups interested to see the development of the tunnel, the basic aspect of safety such as safe distance, wearing of personal protective equipment, lighting, ventilation, and other safety and health protocols at workplace shall always be observed, added Undersecretary Sadain.
Progress of the on-going bored piling works for the Davao River Bridge was also checked by Undersecretary Sadain together with UPMO Roads Management Cluster 1 (Bilateral) Project Director Benjamin A. Bautista, former Project Director Virgilio C. Castillo, Project Manager Joselito B. Reyes and Engr. Earl Nicholas F. Rada, and the engineering consultants from Nippon Koei – Katahira - Nippon Engineering - Philkoei.
The entire 45.5-kilometer bypass road is divided into six (6) packages: package I-1 (10.7 km), package I-2 (12.8 km), package I-3 (6.1 km), package II-1 (2.7 km), package II-2 (3.5 km), and package II-3 (9.7 km).
Davao City Bypass Construction Project is funded by the Japanese Official Development Assistance under the Special Terms for Economic Partnership (STEP) Loan from Japan International Cooperation Agency under Loan Agreement Nos. PH-P261 and PH-P273.

BINONDO - INTRAMUROS BRIDGE SOON OPENING TO EASE TRAFFIC WITH MORE PEOPLE BEGIN ON-SITE WORK UNDER NEW NORMAL
The Department of Public Works and Highways (DPWH) expressed confidence that the opening of Binondo - Intramuros Bridge Project will provide immediate impact of easing traffic especially with many people begin working on-site as Metro Manila shifted back to alert level 1.
Secretary Roger G. Mercado said that Undersecretary and Build Build Build Chief Implementer Emil K. Sadain is making sure that if good weather stays, the Binondo - Intramuros Bridge project will be opened to traffic this coming Holy Week.
This flagship infrastructure project under President Rodrigo Roa Duterte administration’s Build, Build, Build Program is expected to benefit approximately 30,000 vehicles daily passing between the two (2) busy districts of Intramuros and Binondo in Manila.
Undersecretary Sadain, in-charge of DPWH Unified Project Management Office (UPMO) Operations, visited once again the construction site on Friday, March 4, 2022 with government and private engineers and construction workers continuing the effort to beat the target opening and fully finished the project at the soonest time possible.
“Pretty soon, people can drive, walk, bike, or run across this iconic bridge”, said Undersecretary Sadain.
The Binondo-Intramuros Bridge Project involves construction of 680 linear meter two (2)-way four (4)-lane bridge connecting historic district of Intramuros at Solana Street and Riverside Drive with the bustling district of Binondo at Rentas Street/Plaza del Conde Street and Muelle dela Industria.
Funded by a grant from Government of China, the project is under contract with China Road and Bridge Corporation.
Its basket-handle tied steel arch main bridge over Pasig River is expected to become the new symbol of time-honored friendship between China and the Philippines.
The project is being implemented by UPMO Roads Management Cluster 1 (Bilateral) headed by Project Director Benjamin A. Bautista with Project Manager Melchor Kabiling as project in-charge.
This bridge project in support of Metro Manila Logistics Network Program is currently about 96.8 percent complete, with workers focus on constructing the approaches on a fill and compacted embankment to allow the roadway to meet the elevation of the bridge.
Other workers have started doing finishing works on the bridge structure including painting of steels, installation of guardrails and other safety components for motorists, pedestrians, runners and cyclists.
Construction of the new bridge adopted new project techniques utilizing prefabricated bridge elements with high performance materials sourced directly from China.
The project previously encountered delay due to the COVID-19 pandemic and right of way problems.